Location
DWELLINGS AND LAND AT CAERNARVON CLOSE, SOMERSET ROAD, CHEDDAR CLOSE, AVONDALE CLOSE, MONMOUTH ROAD, ABERDARE ROAD, BRIDGEND CLOSE,
GRANGETOWN
Proposal
DEMOLITION OF 19 DWELLINGHOUSES; HYBRID APPLICATION FOR FULL PLANNING PERMISSION FOR REFURBISHMENT OF 289 DWELLINGHOUSES AND ALTERATIONS TO EXISTING ROAD INFRASTRUCTURE TO ALLOW FOR NEW PARKING AND OPEN SPACES; OUTLINE APPLICATION FOR FUTURE RESIDENTIAL DEVELOPMENT FOR 32 DWELLINGHOUSES
Application Type
Major Application
Status
Approved
Parish(es)
Applicant
BEYOND HOUSING
Applicant's Address
CHRISTOPHER EVANS
14 ENNIS SQUARE
DORMANSTOWN
TS10 5JR
Agent
LOGIC ARCHITECTURE
Agent's Address
MR KEVIN POTTS
BOHO ONE
BRIDGE STREET WEST
BOHO ZONE
MIDDLESBROUGH
TS2 1AE
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
16/07/2019
Weekly List Expiry Date
31/07/2019
Date Received
20/06/2019
Date Valid
12/07/2019
Expiry
11/10/2019
Consultation Expiry
19/08/2019
associated_bldreg
R/2021/0257/IN
Decision
GRANT PLANNING PERMISSION
Decision Date
21/01/2020
Decision Level
Delegated
| # | Condition Details |
|---|---|
| 1 | The development shall not be begun later than the expiration of THREE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990. |
| 2 | The development hereby permitted shall be carried out in accordance with the following approved plans: Location Plan received by the Local Planning Authority on 20/06/19 Proposed Site Plan Sheet 1 of 2 (Rev P7) received by the Local Planning Authority on 15/01/2020 Proposed Site Plan Sheet 2 of 2 (Rev P7) received by the Local Planning Authority on 15/01/2020 Proposed Boundary Treatment Plan Sheet 1 of 2 (Rev P1) received by the Local Planning Authority on 15/01/2020 Proposed Boundary Treatment Plan Sheet 2 of 2 (Rev P1) received by the Local Planning Authority on 15/01/2020 Proposed Elevations Type A (Dwg No. 17.35/201) received by the Local Planning Authority on 20/06/19 Proposed Elevations Type B (Dwg No. 17.35/202) received by the Local Planning Authority on 20/06/19 Proposed Elevations Type C (Dwg No. 17.35/203) received by the Local Planning Authority on 20/06/19 Proposed Elevations Type D (Dwg No. 17.35/204) received by the Local Planning Authority on 20/06/19 Proposed Floor Plans Type A (Dwg No. 17-35 P105) received by the Local Planning Authority on 20/06/19 Proposed Floor Plans Type A (Dwg No. 17-35 P106) received by the Local Planning Authority on 20/06/19 Proposed Floor Plans Type A (Dwg No. 17-35 P107) received by the Local Planning Authority on 20/06/19 Proposed Floor Plans Type A (Dwg No. 17-35 P108) received by the Local Planning Authority on 20/06/19 REASON: To accord with the terms of the planning application. |
| 3 | Prior to any works to the external elevations of the existing dwellings details of the external materials to be used (including samples) shall have first been submitted to, and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure that the appearance of the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan. |
| 4 | Prior to the construction of the final surface treatment, for any hard surfaced areas, details of the materials to be used shall have first been submitted to, and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure that the appearance of the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan. |
| 5 | Prior to the commencement of the development, or in such extended time as may be agreed in writing with the Local Planning Authority, details shall be submitted and approved of the surface water drainage scheme and the development shall be completed in accordance with the approved scheme. The design of the drainage scheme shall include; (i) Restriction of surface water greenfield run-off rates (QBAR value) with sufficient storage within the system to accommodate a 1 in 30 year storm. (ii)The method used for calculation of the existing greenfield run-off rate shall be the ICP SUDS method. The design shall also ensure that storm water resulting from a 1 in 100 year event, plus climate change surcharging the system, can be stored on site with minimal risk to persons or property and without overflowing into drains, local highways or watercourses. (iii) Full Micro Drainage design files (mdx files) including a catchment plan (iv) The flow path of flood waters for the site as a result on a 1 in 100 year event plus climate change REASON: To ensure the development is supported by a suitably designed surface water disposal infrastructure scheme and to minimise the risk flooding in the locality. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation. |
| 6 | Prior to the commencement of the development, or in such extended time that may be agreed with the Local Planning Authority, details of a Surface Water Drainage Management Plan shall be submitted and approved by the Local Planning Authority. The Management Plan shall include; (i) The timetable and phasing for construction of the drainage system (ii) Details of any control structure(s) (iii) Details of surface water storage structures (iv) Measures to control silt levels entering the system and out falling into any watercourse during the construction process The development shall, in all respects, be carried out in accordance with the approved Management Plan. REASON: To ensure the development is supported by an appropriately designed surface water disposal infrastructure scheme and to minimise the risk of increased flooding and contamination of the system during the construction process. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation. |
| 7 | The development shall not be occupied until a Management & Maintenance Plan for the surface water drainage scheme has been submitted to and approved by the Local planning Authority; the plan shall include details of the following; (i) A plan clearly identifying the sections of surface water system that are to be adopted (ii) Arrangements for the short and long term maintenance of the SuDS elements of the surface water system REASON: To ensure that the surface water drainage infrastructure is maintained to minimise the risk flooding in the locality. |
| 8 | Prior to commencement of demolition, construction or refurbishment works, a Consturction Environmental Method Plan (CEMP) shall be submitted to and approved in writing by the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide the following; i) The parking of vehicles for site operatives and visitors; ii) ii) Loading and unloading of plant and materials; iii) Storage of plant and materials used in constructing the development; iv) The erection and maintenance of security hoarding including decorative displays; v) Wheel washing facilities; vi) Methods of demolition; vii) Measures to control the emission of noise dust and vibration during the construction period. viii) A scheme for recycling/disposing of waste resulting from demolition and construction works. REASON: To protect the amenity of nearby residents and in the interests of highway safety. REASON FOR PRE COMMENCMENT: The details required for the CEMP relate to setting up of the site and early construction activities. |
| 9 | Within six months of the date of this permission a landscaping scheme shall be submitted to, and approved in writing by, the Local Planning Authority. The details shall include size, type and species and a programme of work. The development shall be completed in accordance with the approved details. REASON: To ensure that the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan. |
| 10 | All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out no later that the first planting and seeding season following the completion of the development, and any trees or plants which within a period of ten years from the completion of the development die, are removed, or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species unless the Local Planning Authority gives written consent to any variation. REASON: To ensure the satisfactory implementation of the approved scheme in the interests of the visual amenities of the locality. |
| 11 | The working hours for all construction activities on this site are limited to between 08:00 and 18:00 Mondays to Friday and 08:00 to 13:00 Saturdays and not at all on a Sunday or Public Holiday. REASON: To ensure that the any activity during the construction development would not have a significant adverse impact in relation to noise and disturbance in accordance with policy SD4 of the Local Plan. |
| 12 | In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken, and where remediation is necessary a remediation scheme must be prepared which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority Following completion of the development a report must be submitted confirming that unexpected contamination was not encountered during the development Reason : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 13 | Informative Note: At no point shall the adopted highway be blocked up with out the prior consent of the Councils Engineering team who can be contacted on 01287 612536. |
| 14 | Informative Note: The applicant is reminded that it is the responsibility of anybody carrying out building work to ensure mud, debris or deleterious material is not deposited from the site onto the public highway and, if it is, it shall be cleared by that person. |
| 15 | Details of the appearance, landscaping, layout and scale, (hereinafter called "the reserved matters") shall be submitted to and approved in writing by the Local Planning Authority before the expiration of three years from the date of this permission. REASON: To reserve the rights of the Local Planning Authority with regard to these matters and required to be imposed pursuant to Sections 91 and 92 of the Planning & Compulsory Purchase Act 2004. |
| 16 | The development hereby permitted shall be begun not later than the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last of the reserved matters to be approved, whichever is later. REASON: Required to be imposed pursuant to Sections 91 and 92 of the Planning & Compulsory Purchase Act 2004. |
| 17 | Development shall not commence until a detailed scheme for the disposal of foul water from the development hereby approved has been submitted to and approved in writing by the Local Planning Authority in consultation with Northumbrian Water and the Lead Local Flood Authority. Thereafter the development shall take place in accordance with the approved details. REASON: To prevent the increased risk of flooding from any sources in accordance with the NPPF. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation. |
| 18 | Prior to the commencement of the development, or in such extended time as may be agreed in writing with the Local Planning Authority, details shall be submitted and approved of the surface water drainage scheme and the development shall be completed in accordance with the approved scheme. The design of the drainage scheme shall include; (i) Restriction of surface water greenfield run-off rates (QBAR value) with sufficient storage within the system to accommodate a 1 in 30 year storm. (ii)The method used for calculation of the existing greenfield run-off rate shall be the ICP SUDS method. The design shall also ensure that storm water resulting from a 1 in 100 year event, plus climate change surcharging the system, can be stored on site with minimal risk to persons or property and without overflowing into drains, local highways or watercourses. (iii) Full Micro Drainage design files (mdx files) including a catchment plan (iv) The flow path of flood waters for the site as a result on a 1 in 100 year event plus climate change REASON: To ensure the development is supported by a suitably designed surface water disposal infrastructure scheme and to minimise the risk flooding in the locality. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation. |
| 19 | Prior to the commencement of the development, or in such extended time that may be agreed with the Local Planning Authority, details of a Surface Water Drainage Management Plan shall be submitted and approved by the Local Planning Authority. The Management Plan shall include; (i) The timetable and phasing for construction of the drainage system (ii) Details of any control structure(s) (iii) Details of surface water storage structures (iv) Measures to control silt levels entering the system and out falling into any watercourse during the construction process The development shall, in all respects, be carried out in accordance with the approved Management Plan. REASON: To ensure the development is supported by an appropriately designed surface water disposal infrastructure scheme and to minimise the risk of increased flooding and contamination of the system during the construction process. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation. |
| 20 | The development shall not be occupied until a Management & Maintenance Plan for the surface water drainage scheme has been submitted to and approved by the Local planning Authority; the plan shall include details of the following; (i) A plan clearly identifying the sections of surface water system that are to be adopted (ii) Arrangements for the short and long term maintenance of the SuDS elements of the surface water system REASON: To ensure that the surface water drainage infrastructure is maintained to minimise the risk flooding in the locality. |
| 21 | Prior to commencement of demolition, construction or refurbishment works, a Construction Environmental Management Plan (CEMP) shall be submitted to and approved in writing by the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide the following; i) The parking of vehicles for site operatives and visitors; ii) ii) Loading and unloading of plant and materials; iii) Storage of plant and materials used in constructing the development; iv) The erection and maintenance of security hoarding including decorative displays; v) Wheel washing facilities; vi) Methods of demolition; vii) Measures to control the emission of noise dust and vibration during the construction period. viii) A scheme for recycling/disposing of waste resulting from demolition and construction works. REASON: To protect the amenity of nearby residents and in the interests of highway safety. REASON FOR PRE COMMENCEMENT: The details required for the CEMP relate to setting up of the site and early construction activities. |
| 22 | Prior to any development above damp proof course details of the external materials to be used in the carrying out of this permission (including samples) shall have first been submitted to, and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure that the appearance of the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan. |
| 23 | Prior to the construction of the final surface treatment, for any hard surfaced areas, details of the materials to be used shall have first been submitted to, and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure that the appearance of the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan. |
| 24 | Prior to the first occupation of the development, hereby approved, boundary walls and fences shall have been erected in accordance with a scheme that has first been submitted to and agreed in writing with the Local Planning Authority. The boundary walls and fences shall thereafter be maintained unless the express consent of the Local Planning Authority is given. REASON: To ensure that any boundary treatments would accord with policy SD4 of the Redcar and Cleveland Local Plan by respecting the character of the site and the surroundings and raising no significant adverse impact on neighbouring occupiers. |
| 25 | All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in the first planting and seeding season following the occupation of the buildings or the completion of the development, whichever is sooner, and any trees or plants which within a period of ten years from the completion of the development die, are removed, or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species unless the Local Planning Authority gives written consent to any variation. REASON: To ensure the satisfactory implementation of the approved scheme in the interests of the visual amenities of the locality. |
| 26 | The working hours for all construction activities on this site are limited to between 08:00 and 18:00 Mondays to Friday and 08:00 to 13:00 Saturdays and not at all on a Sunday or Public Holiday. REASON: To ensure that the any activity during the construction development would not have a significant adverse impact in relation to noise and disturbance in accordance with policy SD4 of the Local Plan. |
| 27 | In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken, and where remediation is necessary a remediation scheme must be prepared which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority Following completion of the development a report must be submitted confirming that unexpected contamination was not encountered during the development Reason : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 28 | Informative Note: The applicant is reminded that it is the responsibility of anybody carrying out building work to ensure mud, debris or deleterious material is not deposited from the site onto the public highway and, if it is, it shall be cleared by that person. |
| 29 | Informative Note: At no point shall the adopted highway be blocked up with out the prior consent of the Councils Engineering team who can be contacted on 01287 612536. |
| 30 | The working hours for all construction activities on this site are limited to between 08:00 and 18:00 Mondays to Friday and 08:00 to 13:00 Saturdays and not at all on a Sunday or Public Holiday. REASON: To ensure that the any activity during the construction development would not have a significant adverse impact in relation to noise and disturbance in accordance with policy SD4 of the Local Plan. |
| 31 | Statement of Co-operative Working: The Local Planning Authority considers that the application as originally submitted did not meet with the local policies and guidance. Following discussions with the applicant / agent a satisfactory scheme has been negotiated. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Adult Services | 16/07/2019 | - |
| Cleveland Police ALO - Steve Cranston | 16/07/2019 | - |
| Councillor A Brook (GRANGETOWN) | 16/07/2019 | - |
| Councillor L Pallister (GRANGETOWN) | 16/07/2019 | - |
| Engineering Team (Highways) | 16/07/2019 | - |
| Engineers (Local Lead Flood Authority) | 16/07/2019 | - |
| Environmental Protection Team | 16/07/2019 | - |
| Executive Management Team | 16/07/2019 | - |
| Housing Area Services | 16/07/2019 | - |
| Michael Greene | 16/07/2019 | - |
| Northumbrian Water Ltd | 16/07/2019 | - |
| Place Investment Team | 16/07/2019 | - |
| Public Rights of Way | 16/07/2019 | - |
| Schools Capital Officer | 16/07/2019 | - |
| Strategic Planning (Roger Kay) | 16/07/2019 | - |
| Strategic Planning Team (Policy) | 16/07/2019 | - |
| Address | Date Sent | Date Reconsulted | Expiry Date |
|---|---|---|---|
| - | - | - | - |
| LANCASTER HOUSE AVONDALE CLOSE ESTON | 16/07/2019 | - | 06/08/2019 |
| LEICESTER HOUSE BANGOR CLOSE ESTON | 16/07/2019 | - | 06/08/2019 |
| NORTHAMPTON HOUSE CALDICOT CLOSE ESTON | 16/07/2019 | - | 06/08/2019 |
| 1 ARUNDEL ROAD GRANGETOWN MIDDLESBROUGH TS6 7QZ | 16/07/2019 | - | 06/08/2019 |
| 3 ARUNDEL ROAD GRANGETOWN MIDDLESBROUGH TS6 7QZ | 16/07/2019 | - | 06/08/2019 |
| 5 ARUNDEL ROAD GRANGETOWN MIDDLESBROUGH TS6 7QZ | 16/07/2019 | - | 06/08/2019 |
| 70 ARUNDEL ROAD GRANGETOWN MIDDLESBROUGH TS6 7QZ | 16/07/2019 | - | 06/08/2019 |
| 89 ARUNDEL ROAD GRANGETOWN MIDDLESBROUGH TS6 7QZ | 16/07/2019 | - | 06/08/2019 |
| 42 ATTLEE ROAD GRANGETOWN MIDDLESBROUGH TS6 7NA | 16/07/2019 | - | 06/08/2019 |
| 2 BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SL | 16/07/2019 | - | 06/08/2019 |
| 3 BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SL | 16/07/2019 | - | 06/08/2019 |
| 4 BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SL | 16/07/2019 | - | 06/08/2019 |
| 5 BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SL | 16/07/2019 | - | 06/08/2019 |
| 6 BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SL | 16/07/2019 | - | 06/08/2019 |
| 22 CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SN | 16/07/2019 | - | 06/08/2019 |
| 23 CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SN | 16/07/2019 | - | 06/08/2019 |
| 24 CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SN | 16/07/2019 | - | 06/08/2019 |
| 25 CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SN | 16/07/2019 | - | 06/08/2019 |
| 26 CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SN | 16/07/2019 | - | 06/08/2019 |
| 27 CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SN | 16/07/2019 | - | 06/08/2019 |
| 28 CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SN | 16/07/2019 | - | 06/08/2019 |
| 29 CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SN | 16/07/2019 | - | 06/08/2019 |
| 30 CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SN | 16/07/2019 | - | 06/08/2019 |
| 226 CHURCH LANE ESTON MIDDLESBROUGH TS6 9RB | 16/07/2019 | - | 06/08/2019 |
| 228 CHURCH LANE ESTON MIDDLESBROUGH TS6 9RB | 16/07/2019 | - | 06/08/2019 |
| 230 CHURCH LANE ESTON MIDDLESBROUGH TS6 9RB | 16/07/2019 | - | 06/08/2019 |
| 232 CHURCH LANE ESTON MIDDLESBROUGH TS6 9RB | 16/07/2019 | - | 06/08/2019 |
| 234 CHURCH LANE ESTON MIDDLESBROUGH TS6 9RB | 16/07/2019 | - | 06/08/2019 |
| 236 CHURCH LANE ESTON MIDDLESBROUGH TS6 9RB | 16/07/2019 | - | 06/08/2019 |
| 238 CHURCH LANE ESTON MIDDLESBROUGH TS6 9RB | 16/07/2019 | - | 06/08/2019 |
| 240 CHURCH LANE ESTON MIDDLESBROUGH TS6 9RB | 16/07/2019 | - | 06/08/2019 |
| 242 CHURCH LANE ESTON MIDDLESBROUGH TS6 9RB | 16/07/2019 | - | 06/08/2019 |
| 244 CHURCH LANE ESTON MIDDLESBROUGH TS6 9RB | 16/07/2019 | - | 06/08/2019 |
| 1 SANDRINGHAM ROAD GRANGETOWN MIDDLESBROUGH TS6 7QT | 16/07/2019 | - | 06/08/2019 |
| 3 SANDRINGHAM ROAD GRANGETOWN MIDDLESBROUGH TS6 7QT | 16/07/2019 | - | 06/08/2019 |
| 5 SANDRINGHAM ROAD GRANGETOWN MIDDLESBROUGH TS6 7QT | 16/07/2019 | - | 06/08/2019 |
| 7 SANDRINGHAM ROAD GRANGETOWN MIDDLESBROUGH TS6 7QT | 16/07/2019 | - | 06/08/2019 |
| 9 SANDRINGHAM ROAD GRANGETOWN MIDDLESBROUGH TS6 7QT | 16/07/2019 | - | 06/08/2019 |
| 11 SANDRINGHAM ROAD GRANGETOWN MIDDLESBROUGH TS6 7QT | 16/07/2019 | - | 06/08/2019 |
| 15 SANDRINGHAM ROAD GRANGETOWN MIDDLESBROUGH TS6 7QT | 16/07/2019 | - | 06/08/2019 |
| 17 SANDRINGHAM ROAD GRANGETOWN MIDDLESBROUGH TS6 7QT | 16/07/2019 | - | 06/08/2019 |
| 19 SANDRINGHAM ROAD GRANGETOWN MIDDLESBROUGH TS6 7QT | 16/07/2019 | - | 06/08/2019 |
| 21 SANDRINGHAM ROAD GRANGETOWN MIDDLESBROUGH TS6 7QT | 16/07/2019 | - | 06/08/2019 |
| 23 SANDRINGHAM ROAD GRANGETOWN MIDDLESBROUGH TS6 7QT | 16/07/2019 | - | 06/08/2019 |
| 18 ST PATRICKS ROAD GRANGETOWN MIDDLESBROUGH TS6 7LA | 16/07/2019 | - | 06/08/2019 |
| 20 ST PATRICKS ROAD GRANGETOWN MIDDLESBROUGH TS6 7LA | 16/07/2019 | - | 06/08/2019 |
| 22 ST PATRICKS ROAD GRANGETOWN MIDDLESBROUGH TS6 7LA | 16/07/2019 | - | 06/08/2019 |
| 24 ST PATRICKS ROAD GRANGETOWN MIDDLESBROUGH TS6 7LA | 16/07/2019 | - | 06/08/2019 |
| 26 ST PATRICKS ROAD GRANGETOWN MIDDLESBROUGH TS6 7JY | 16/07/2019 | - | 06/08/2019 |
| 28 ST PATRICKS ROAD GRANGETOWN MIDDLESBROUGH TS6 7JY | 16/07/2019 | - | 06/08/2019 |
| 30 ST PATRICKS ROAD GRANGETOWN MIDDLESBROUGH TS6 7JY | 16/07/2019 | - | 06/08/2019 |
| 32 ST PATRICKS ROAD GRANGETOWN MIDDLESBROUGH TS6 7JY | 16/07/2019 | - | 06/08/2019 |
| 36 TAWNEY ROAD ESTON MIDDLESBROUGH TS6 9RR | 16/07/2019 | - | 06/08/2019 |
| 38 TAWNEY ROAD ESTON MIDDLESBROUGH TS6 9RR | 16/07/2019 | - | 06/08/2019 |
| 40 TAWNEY ROAD ESTON MIDDLESBROUGH TS6 9RR | 16/07/2019 | - | 06/08/2019 |
| 91 TAWNEY ROAD ESTON MIDDLESBROUGH TS6 9RD | 16/07/2019 | - | 06/08/2019 |
| 93 TAWNEY ROAD ESTON MIDDLESBROUGH TS6 9RD | 16/07/2019 | - | 06/08/2019 |
| 95 TAWNEY ROAD ESTON MIDDLESBROUGH TS6 9RD | 16/07/2019 | - | 06/08/2019 |
| 97 TAWNEY ROAD ESTON MIDDLESBROUGH TS6 9RD | 16/07/2019 | - | 06/08/2019 |
| 99 TAWNEY ROAD ESTON MIDDLESBROUGH TS6 9RD | 16/07/2019 | - | 06/08/2019 |
| 2 TENNYSON AVENUE GRANGETOWN MIDDLESBROUGH TS6 7NU | 16/07/2019 | - | 06/08/2019 |
| 4 TENNYSON AVENUE GRANGETOWN MIDDLESBROUGH TS6 7NU | 16/07/2019 | - | 06/08/2019 |
| 7 TENNYSON AVENUE GRANGETOWN MIDDLESBROUGH TS6 7NT | 16/07/2019 | - | 06/08/2019 |
| 1 WINDSOR COURT GRANGETOWN MIDDLESBROUGH TS6 7QY | 16/07/2019 | - | 06/08/2019 |
| 2 WINDSOR COURT GRANGETOWN MIDDLESBROUGH TS6 7QY | 16/07/2019 | - | 06/08/2019 |
| 3 WINDSOR COURT GRANGETOWN MIDDLESBROUGH TS6 7QY | 16/07/2019 | - | 06/08/2019 |
| 5 WINDSOR COURT GRANGETOWN MIDDLESBROUGH TS6 7QY | 16/07/2019 | - | 06/08/2019 |
| 25 WINDSOR COURT GRANGETOWN MIDDLESBROUGH TS6 7QY | 16/07/2019 | - | 06/08/2019 |
| 1 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 2 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 3 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 4 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 5 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 6 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 7 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 8 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 9 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 10 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 11 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 12 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 13 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 14 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 15 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 16 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 17 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 18 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 19 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 20 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 21 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 22 LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| FLAT 67 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 68 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 69 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 70 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 71 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 72 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 73 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 74 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 75 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 76 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 77 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 78 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 79 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 80 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 81 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 82 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 83 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 84 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 85 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 86 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 87 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 88 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 89 LEICESTER HOUSE BANGOR CLOSE ESTON MIDDLESBROUGH TS6 9SJ | 16/07/2019 | - | 06/08/2019 |
| FLAT 23 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 24 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 25 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 26 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 27 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 28 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 29 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 30 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 31 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 32 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 33 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 34 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 35 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 36 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 37 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 38 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 39 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 40 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 41 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 42 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 43 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 44 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| SCHOOL HOUSE 12 TENNYSON AVENUE GRANGETOWN MIDDLESBROUGH TS6 7NP | 16/07/2019 | - | 06/08/2019 |
| THE PRIORY DAY NURSERY 18 GRANGE CLOSE GRANGETOWN MIDDLESBROUGH TS6 7LD | 16/07/2019 | - | 06/08/2019 |
| ST MARYS CATHOLIC VOLUNTARY PRIMARY ACADEMY TENNYSON AVENUE GRANGETOWN MIDDLESBROUGH TS6 7AD | 16/07/2019 | - | 06/08/2019 |
| PATHWAYS SCHOOL TENNYSON AVENUE GRANGETOWN MIDDLESBROUGH TS6 7NP | 16/07/2019 | - | 06/08/2019 |
| STEWARDS RESIDENCE ST MARYS SOCIAL CLUB GRANGE FARM ROAD GRANGETOWN MIDDLESBROUGH TS6 7HP | 16/07/2019 | - | 06/08/2019 |
| COMMUNICATIONS STATION NORTHAMPTON HOUSE CALDICOT CLOSE ESTON | 16/07/2019 | - | 06/08/2019 |
| 1A LANCASTER HOUSE AVONDALE CLOSE ESTON MIDDLESBROUGH TS6 9SQ | 16/07/2019 | - | 06/08/2019 |
| 2A LANCASTER HOUSE AVONDALE CLOSE ESTON | 16/07/2019 | - | 06/08/2019 |
| FLAT 21 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON MIDDLESBROUGH TS6 9SW | 16/07/2019 | - | 06/08/2019 |
| FLAT 22 NORTHAMPTON HOUSE CALDICOT CLOSE ESTON | 16/07/2019 | - | 06/08/2019 |
| 66 LEICESTER HOUSE BANGOR CLOSE ESTON | 16/07/2019 | - | 06/08/2019 |
| CAEDMON PRIMARY SCHOOL ATTLEE ROAD GRANGETOWN MIDDLESBROUGH TS6 7NA | 16/07/2019 | - | 06/08/2019 |
| ST MARYS SOCIAL CLUB GRANGE FARM ROAD GRANGETOWN MIDDLESBROUGH TS6 7HP | 16/07/2019 | - | 06/08/2019 |
| OFFICE GRANGE CLOSE GRANGETOWN MIDDLESBROUGH TS6 7LD | 16/07/2019 | - | 06/08/2019 |
| Site or Press | Description | Display Date | Expiry Date |
|---|---|---|---|
| B | ARTICLE 15 | 19/07/2019 | 09/08/2019 |
| S | ARTICLE 15 | 29/07/2019 | 19/08/2019 |