R/2019/0183/OOM

Planning Application Details - Official Consultation has expired.

Location
LAND SOUTH OF SPENCERBECK FARM NORMANBY ROAD ORMESBY
Proposal
DEMOLITION OF EXISTING OUTBUILDINGS TO ALLOW OUTLINE PLANNING PERMISSION (WITH SOME MATTERS RESERVED) FOR RESIDENTIAL DEVELOPMENT (52 DWELLINGS)
Application Type
Outline Application Major
Status
Approved
Parish(es)
Applicant
MR R ROBERTS
Applicant's Address
Agent
ELG PLANNING
Agent's Address
MR IAN LYLE GATEWAY HOUSE 55 CONISCLIFFE ROAD DARLINGTON DL3 7EH
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
04/04/2019
Weekly List Expiry Date
11/04/2019
Date Received
22/03/2019
Date Valid
01/04/2019
Expiry
22/01/2021
Consultation Expiry
28/04/2019
associated_bldreg
-
Decision
GRANT OUTLINE CONSENT
Decision Date
20/01/2021
Decision Level
-

Conditions table
# Condition Details
1 Details of the appearance, landscaping, layout and scale, (hereinafter called "the reserved matters") shall be submitted to and approved in writing by the Local Planning Authority before the expiration of three years from the date of this permission. REASON: To reserve the rights of the Local Planning Authority with regard to these matters and required to be imposed pursuant to Sections 91 and 92 of the Planning & Compulsory Purchase Act 2004.
2 The development hereby permitted shall be begun not later than the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last of the reserved matters to be approved, whichever is later. REASON: Required to be imposed pursuant to Sections 91 and 92 of the Planning & Compulsory Purchase Act 2004.
3 Prior to occupation of the first completed dwelling on the site a landscaping scheme shall be submitted to, and approved in writing by, the Local Planning Authority. The details shall include size, type and species and a programme of work. The development shall be completed in accordance with the approved details. REASON: To ensure that the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan.
4 All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in the first planting and seeding season following the occupation of the buildings or the completion of the development, whichever is sooner, and any trees or plants which within a period of ten years from the completion of the development die, are removed, or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species unless the Local Planning Authority gives written consent to any variation. REASON: To ensure the satisfactory implementation of the approved scheme in the interests of the visual amenities of the locality.
5 Prior to any development above damp proof course details of the external materials to be used in the carrying out of this permission (including samples) shall have first been submitted to, and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure that the appearance of the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan.
6 Prior to the construction of the final surface treatment, for any hard surfaced areas, details of the materials to be used shall have first been submitted to, and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure that the appearance of the development would respect the site and the surroundings in accordance with policy SD4 of the Local Plan.
7 Prior to the first occupation of any dwelling, hereby approved, the boundary walls or fences relating to that plot shall have been erected in accordance with a scheme that has first been submitted to and agreed in writing with the Local Planning Authority. The boundary walls and fences shall thereafter be maintained unless the express consent of the Local Planning Authority is given. REASON: To ensure that any boundary treatments would accord with policy SD4 of the Redcar and Cleveland Local Plan by respecting the character of the site and the surroundings and raising no significant adverse impact on neighbouring occupiers.
8 Unless otherwise agreed by the Local Planning Authority in writing, development other than that required to be carried out as part of an approved scheme of remediation must not commence until parts (a) to (c) have been complied with. If unexpected contamination is found after development has begun, development must be halted on that part of the site affected by the unexpected contamination to the extent specified by the Local Planning Authority in writing until condition (e) has been complied with in relation to that contamination. (a) Site Characterisation An investigation and risk assessment, in addition to any assessment provided with the planning application, must be completed in accordance with a scheme to assess the nature and extent of any contamination on the site, whether or not it originates on the site. The contents of the scheme are subject to the approval in writing of the Local Planning Authority. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The written report is subject to the approval in writing of the Local Planning Authority. The report of the findings must include: (i) a survey of the extent, scale and nature of contamination; (ii) an assessment of the potential risks to: • human health, • property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes, • adjoining land, • groundwaters and surface waters, • ecological systems, • archeological sites and ancient monuments; (iii) an appraisal of remedial options, and proposal of the preferred option(s). This must be conducted in accordance with Environment Agency’s Land Contamination Risk Management Guidance (b) Submission of Remediation Scheme A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. (c) Implementation of Approved Remediation Scheme The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval in writing of the Local Planning Authority. (d) Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken in accordance with the requirements of part (a) and where remediation is necessary a remediation scheme must be prepared in accordance with the requirements of part (b), which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority. (e) Long Term Monitoring and Maintenance A monitoring and maintenance scheme to include monitoring the long-term effectiveness of the proposed remediation over a period of 10 years, and the provision of reports on the same must be prepared, both of which are subject to the approval in writing of the Local Planning Authority. Following completion of the measures identified in that scheme and when the remediation objectives have been achieved, reports that demonstrate the effectiveness of the monitoring and maintenance carried out must be produced, and submitted to the Local Planning Authority. This must be conducted in accordance with Environment Agency’s Land Contamination Risk Management Guidance REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to land contamination details which are often the first works on site and relate to site preparation.
9 Prior to construction of foundations on site a Construction Environmental Management Plan (CEMP) shall be submitted to and approved in writing by the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide the following; i) The parking of vehicles for site operatives and visitors; ii) Loading and unloading of plant and materials; iii) Storage of plant and materials used in constructing the development; iv) The erection and maintenance of security hoarding including decorative displays; v) Wheel washing facilities; vi) Measures to control the emission of noise dust and vibration during the construction period. vii) A scheme for recycling/disposing of waste resulting from demolition and construction works. REASON: In the interest of neighbour amenity and highways safety and in accordance with policy SD4 of the Redcar and Cleveland Local Plan.
10 Prior to the commencement of development plans showing the existing and proposed ground levels over the site together with finished floor levels and maximum building heights shall be submitted to and approved in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details. REASON: To ensure a satisfactory relationship between existing and proposed buildings in accordance with policy SD4 of the Local Plan. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site as construction activity and site preparation can change existing levels resulting in increased ground levels which the authority needs to consider.
11 Prior to the commencement of the development, or in such extended time as may be agreed in writing with the Local Planning Authority, details shall be submitted and approved of the surface water drainage scheme and the development shall be completed in accordance with the approved scheme. The design of the drainage scheme shall include; (i) Restriction of surface water greenfield run-off rates (QBAR value) with sufficient storage within the system to accommodate a 1 in 30 year storm. (ii)The method used for calculation of the existing greenfield run-off rate shall be the ICP SUDS method. The design shall also ensure that storm water resulting from a 1 in 100 year event, plus climate change surcharging the system, can be stored on site with minimal risk to persons or property and without overflowing into drains, local highways or watercourses. (iii) Full Micro Drainage design files (mdx files) including a catchment plan (iv) The flow path of flood waters for the site as a result on a 1 in 100 year event plus climate change REASON: To ensure the development is supported by a suitably designed surface water disposal infrastructure scheme and to minimise the risk flooding in the locality. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation.
12 Prior to the commencement of the development, or in such extended time that may be agreed with the Local Planning Authority, details of a Surface Water Drainage Management Plan shall be submitted and approved by the Local Planning Authority. The Management Plan shall include; (i) The timetable and phasing for construction of the drainage system (ii) Details of any control structure(s) (iii) Details of surface water storage structures (iv) Measures to control silt levels entering the system and out falling into any watercourse during the construction process The development shall, in all respects, be carried out in accordance with the approved Management Plan. REASON: To ensure the development is supported by an appropriately designed surface water disposal infrastructure scheme and to minimise the risk of increased flooding and contamination of the system during the construction process. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site it relates to drainage details which are often the first works on site and relate to site preparation.
13 The development shall not be occupied until a Management & Maintenance Plan for the surface water drainage scheme has been submitted to and approved by the Local planning Authority; the plan shall include details of the following; (i) A plan clearly identifying the sections of surface water system that are to be adopted (ii) Arrangements for the short and long term maintenance of the SuDS elements of the surface water system REASON: To ensure that the surface water drainage infrastructure is maintained to minimise the risk flooding in the locality.
14 Development shall not commence until a detailed scheme for the disposal of foul water from the development hereby approved has been submitted to and approved in writing by the Local Planning Authority in consultation with Northumbrian Water and the Lead Local Flood Authority. Thereafter the development shall take place in accordance with the approved details. REASON: To prevent the increased risk of flooding from any sources in accordance with the NPPF in accordance with policy SD4 of the Local Plan. REASON FOR PRE-COMMENCEMENT: The information is required prior to any works commencing on site as it relates to drainage details which are often the first works on site and relate to site preparation.
15 There shall be no site vegetation clearance between March to the end of August unless the project ecologist has first undertaken a checking survey immediately prior to the clearance and confirms in writing to the Local Planning Authority that no active nests are present. REASON: To conserve protected species and their habitat in accordance with policy N4 of the Local Plan.
16 The working hours for all construction activities on this site are limited to between 08:00 and 18:00 Mondays to Friday and 08:00 to 13:00 Saturdays and not at all on a Sunday or Public Holiday. REASON: To ensure that the any activity during the construction development would not have a significant adverse impact in relation to noise and disturbance in accordance with policy SD4 of the Local Plan.
17 Statement of Co-operative Working: The Local Planning Authority considers that the application as originally submitted did not meet with the local policies and guidance. Following discussions with the applicant / agent a satisfactory scheme has been negotiated.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 322 kb 01/04/2019
Consultee Responses
Consultee response - Public Rights of Way 39 kb 04/04/2019
Consultee response - Cleveland Police 40 kb 05/04/2019
Consultee response - Natural Heritage Manager 34 kb 11/04/2019
Consultee response - Ramblers 36 kb 23/04/2019
Consultee response - Environmental Protection (Contaminated Land) 26 kb 23/04/2019
Consultee response - Environmental Protection (Nuisance) 16 kb 23/04/2019
Consultee response - Northumbrian Water (1) 65 kb 23/04/2019
Consultee response - Development Engineers 39 kb 24/04/2019
Consultee response - Strategic Planning (Policy) 35 kb 25/04/2019
Consultee response - Natural England 243 kb 25/04/2019
Consultee response - Schools 75 kb 02/05/2019
Consultee response - Archaeological Consultant 172 kb 03/05/2019
Consultee response - Northumbrian Water (2) 46 kb 01/07/2019
Consultee response - Engineers (Local Lead Flood Authority) 47 kb 18/07/2019
Decision
Decision Notice 140 kb 20/01/2021
Location Plan
Location Plan 130 kb 22/03/2019
Officer Report
Officer Report 159 kb 20/01/2021
Plans
Site Layout Plan 170 kb 22/03/2019
Supporting Documentation
Biodiversity Survey and Report 2669 kb 22/03/2019
Design and Access Statement 814 kb 22/03/2019
Flood Risk Assessment SUPERSEDED 5628 kb 22/03/2019
Planning Statement 934 kb 22/03/2019
Transport Assessment 2236 kb 22/03/2019
Tree Survey 91 kb 22/03/2019
Desk Top Study 11643 kb 01/04/2019
Flood Risk Assessment Revised 14.6.2019 2960 kb 14/06/2019
Application Documents
Section 106 Agreement 1830 kb 22/01/2021
Consultee Name Date Letter Sent Consultation Expiry Date
Aboricultural Officer 04/04/2019 -
Adult Services 04/04/2019 -
Asset Management - Brian Masterton 25/03/2020 -
Asset Management - Chris Black 25/03/2020 -
Asset Management Team Fao Guy Allen 25/03/2020 -
Cleveland Police ALO - Steve Cranston 04/04/2019 -
Councillor B Ayre (NORMANBY) 04/04/2019 -
Councillor B Dennis (NORMANBY) 04/04/2019 -
Councillor C Foley-McCormack (NORMANBY) 04/04/2019 -
Engineering Team (Highways) 04/04/2019 -
Engineers (Local Lead Flood Authority) 04/04/2019 -
Engineers (Local Lead Flood Authority) 17/06/2019 -
Environment Agency 17/06/2019 -
Environment Agency 04/04/2019 -
Environmental Protection Team 04/04/2019 -
Executive Management Team 04/04/2019 -
Housing Area Services 04/04/2019 -
Natural England 04/04/2019 -
Natural Heritage Manager 04/04/2019 -
NEAR Ltd (Archaeological Services) 04/04/2019 -
Northumbrian Water Ltd 04/04/2019 -
Northumbrian Water Ltd 17/06/2019 -
Place Investment Team 04/04/2019 -
Public Rights of Way 04/04/2019 -
Ramblers Association 04/04/2019 -
Schools Capital Officer 04/04/2019 -
Strategic Planning (Roger Kay) 04/04/2019 -
Strategic Planning (Roger Kay) 25/03/2020 -
Strategic Planning Team (Policy) 04/04/2019 -
Address Date Sent Date Reconsulted Expiry Date
26 CRICKET LANE NORMANBY MIDDLESBROUGH TS6 0HR 04/04/2019 - 27/04/2019
28 CRICKET LANE NORMANBY MIDDLESBROUGH TS6 0HR 04/04/2019 - 27/04/2019
30 CRICKET LANE NORMANBY MIDDLESBROUGH TS6 0HR 04/04/2019 - 27/04/2019
32 CRICKET LANE NORMANBY MIDDLESBROUGH TS6 0HR 04/04/2019 - 27/04/2019
34 CRICKET LANE NORMANBY MIDDLESBROUGH TS6 0HR 04/04/2019 - 27/04/2019
2 NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
4 NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
6 NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
2 WILLOW DRIVE NORMANBY MIDDLESBROUGH TS6 0HP 04/04/2019 - 27/04/2019
4 WILLOW DRIVE NORMANBY MIDDLESBROUGH TS6 0HP 04/04/2019 - 27/04/2019
6 WILLOW DRIVE NORMANBY MIDDLESBROUGH TS6 0HP 04/04/2019 - 27/04/2019
1 ROBERTS COURT NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
2 ROBERTS COURT NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
3 ROBERTS COURT NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
4 ROBERTS COURT NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
5 ROBERTS COURT NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
1A SPENCERBECK COTTAGE FLATS NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
1B SPENCERBECK COTTAGE FLATS NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
1 ROBERTS ROW NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
2 ROBERTS ROW NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
3 ROBERTS ROW NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
4 ROBERTS ROW NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
5 ROBERTS ROW NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
6 ROBERTS ROW NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
7 ROBERTS ROW NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
6 ROBERTS COURT NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
7 ROBERTS COURT NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
SPENCERBECK COTTAGE FLATS NORMANBY ROAD ORMESBY 04/04/2019 - 27/04/2019
1C SPENCERBECK COTTAGE FLATS NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
1D SPENCERBECK COTTAGE FLATS NORMANBY ROAD ORMESBY MIDDLESBROUGH TS7 9NS 04/04/2019 - 27/04/2019
Site or Press Description Display Date Expiry Date
B ARTICLE 15 05/04/2019 28/04/2019