R/2018/0382/VC

Planning Application Details - Official Consultation has expired.

Location
178 HIGH STREET MARSKE BY THE SEA TS11 7NB
Proposal
VARIATION OF CONDITION 1 OF PLANNING PERMISSION R/2018/0102/CA TO SUBSTITUTE FLAT ROOF WITH PITCHED ROOF WITH ADDITION OF REAR DOOR AND FIRST FLOOR WINDOWS TO CONVERTED FLATS
Application Type
Variation Condition
Status
Approved
Parish(es)
Saltburn, Marske and New Marske CP
Applicant
AMG PROPERTIES LTD
Applicant's Address
C/O 12 CHESTNUT AVENUE REDCAR EAST REDCAR TS10 3PB
Agent
MR GARRY PHILLIPSON
Agent's Address
12 CHESTNUT AVENUE REDCAR TS10 3PB
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
29/08/2018
Weekly List Expiry Date
05/09/2018
Date Received
25/06/2018
Date Valid
23/08/2018
Expiry
18/10/2018
Consultation Expiry
21/09/2018
associated_bldreg
-
Decision
GRANT PLANNING PERMISSION
Decision Date
16/10/2018
Decision Level
Delegated

Conditions table
# Condition Details
1 The development hereby permitted shall be carried out in accordance with the following approved plans: Application R/2018/0382/VC Proposed Flat Elevations (Drg No. 05 Rev A) received by the Local Planning Authority on 22/08/18 Proposed Ground Floor Plan (Drg No. 03 Rev A) received by the Local Planning Authority on 09/10/18 Proposed First Floor Plan (Drg No. 04 Rev A) received by the Local Planning Authority on 09/10/18 Application R/2018/0102/CA Proposed House Elevations (Drg No. 06) received by the Local Planning Authority on 21/02/18
2 Within 2 months of the date of this approval details of the external materials to be used in the carrying out of this permission (including samples) shall be submitted to the Local Planning Authority. The development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials.
3 Within 2 months of the date of this approval details of materials to be used for all hard surfaces shall be submitted to the Local Planning Authority. The development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials.
4 Development other than that required to be carried out as part of an approved scheme of remediation must not commence until parts (a) to (c) have been complied with. If unexpected contamination is found after development has begun, development must be halted on that part of the site affected by the unexpected contamination to the extent specified by the Local Planning Authority in writing until condition (e) has been complied with in relation to that contamination. (a) Site Characterisation An investigation and risk assessment, in addition to any assessment provided with the planning application, must be completed in accordance with a scheme to assess the nature and extent of any contamination on the site, whether or not it originates on the site. The contents of the scheme are subject to the approval in writing of the Local Planning Authority. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The written report is subject to the approval in writing of the Local Planning Authority. The report of the findings must include: (i) a survey of the extent, scale and nature of contamination; (ii) an assessment of the potential risks to: • human health, • property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes, • adjoining land, • groundwaters and surface waters, • ecological systems, • archeological sites and ancient monuments; (iii) an appraisal of remedial options, and proposal of the preferred option(s). This must be conducted in accordance with DEFRA and the Environment Agency’s ‘Model Procedures for the Management of Land Contamination, CLR 11’. (b) Submission of Remediation Scheme A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. (c) Implementation of Approved Remediation Scheme The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report as a validation report) that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval in writing of the Local Planning Authority. (d) Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken in accordance with the requirements of part (a) and where remediation is necessary a remediation scheme must be prepared in accordance with the requirements of part (b), which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority. (e) Long Term Monitoring and Maintenance A monitoring and maintenance scheme to include monitoring the long-term effectiveness of the proposed remediation over a period of 10 years, and the provision of reports on the same must be prepared, both of which are subject to the approval in writing of the Local Planning Authority. Following completion of the measures identified in that scheme and when the remediation objectives have been achieved, reports that demonstrate the effectiveness of the monitoring and maintenance carried out must be produced, and submitted to the Local Planning Authority. This must be conducted in accordance with DEFRA and the Environment Agency’s ‘Model Procedures for the Management of Land Contamination, CLR 11’ REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
5 The working hours for all construction activities on this site are limited to between 08:00 and 18:00 Mondays to Friday and 08:00 to 13:00 Saturdays and not at all on a Sunday or Public Holidays. REASON: In the interest of neighbour amenity.
6 Within 2 months of the date of this approval a Construction Method Statement shall be submitted to the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide the following; i The parking of vehicles for site operatives and visitors; ii Loading and unloading of plant and materials, iii Storage of plant and materials used in constructing the development; iv Wheel washing facilities; v Methods of demolition; vi Measures to control the emission of noise, dust and vibration during the construction period, vii A scheme for recycling/disposing of waste resulting from demolition and construction works. REASON: To protect the amenity of nearby residents and highway safety.
7 Within 2 months of the date of this approval a scheme for the disposal of foul and surface water from the development hereby approved has been submitted to the Local Planning Authority. Thereafter the development shall be implemented in accordance with the approved details. REASON: To prevent the increased risk of flooding from any sources.
8 The residential use hereby permitted shall not commence until details of the arrangements for the storage of refuse have been submitted to, and approved in writing by, the Local Planning Authority. The development shall be not be carried out other than in accordance with any approval given and shall be completed prior to any part of the development hereby approved being brought into use. The use of the refuse storage area agreed shall thereafter be retained at all times. REASON: To safeguard the amenity of the area.
9 Within 2 months of the date of this approval a landscaping scheme shall be submitted to the Local Planning Authority. The details shall include size, type and species of plant and indicate the proposed layout and surfacing of all open areas. A programme of work shall also be submitted and implemented in accordance with the approved details. The development shall thereafter be carried out in accordance with the approved details. REASON: To reserve the rights of the Local Planning Authority with regard to these matters.
10 All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in the first planting and seeding season following the occupation of the buildings or the completion of the development, whichever is sooner, and any trees or plants which within a period of ten years from the completion of the development die, are removed, or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species unless the Local Planning Authority gives written consent to any variation. REASON: To ensure the satisfactory implementation of the approved scheme in the interests of the visual amenities of the locality.
11 Prior to any part of the residential development hereby permitted being occupied, car parking shall be provided in accordance with a layout (including showing the proposed bollards) and parking allocation plan that has been submitted to and approved in writing by the Local Planning Authority. The approved scheme shall thereafter be maintained. REASON: In the interests of achieving satisfactory car parking provision at this site.
12 The boundary walls and fences shall be erected in accordance with the approved plans prior to the first occupation of the final dwelling of the development hereby approved and shall thereafter be maintained. REASON: In the interests of visual and residential amenity.
13 Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order, 2015, (or any Order revoking or re-enacting that Order) no enlargement of the dwelling(s) the subject of this permission shall be carried out without the express consent of the Local Planning Authority. REASON: To safeguard the character and appearance of the development.
14 Notwithstanding the provisions of the Town and Country Planning General Development Order, 2015 (or any Order revoking or re-enacting that Order), no detached buildings shall be erected within the curtilage of the dwelling(s) the subject of this permission, without the express consent of the Local Planning Authority. REASON: To safeguard the character and appearance of the development.
15 Statement of Co-operative Working: The Local Planning Authority considers that the application as originally submitted did not meet with the local policies and guidance. Following discussions with the applicant / agent a satisfactory scheme has been negotiated.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 328 kb 25/06/2018
Consultee Responses
Consultee response - Parish/Town Council 87 kb 31/08/2018
Consultee response - Strategic Planning (Conservation) 199 kb 07/09/2018
Decision
Decision Notice 151 kb 16/10/2018
Plans
Proposed Layout 306 kb 25/06/2018
Elevations as Existing 2180 kb 13/08/2018
Proposed Ground Floor Layout - SUPERSEDED 354 kb 22/08/2018
Proposed Flats Elevations 2312 kb 22/08/2018
Proposed First Floor Layout - SUPERSEDED 318 kb 23/08/2018
Proposed Elevations APPROVED 119 kb 23/08/2018
Proposed Ground Floor Plan APPROVED 144 kb 23/08/2018
Proposed First Floor Plan APPROVED 126 kb 23/08/2018
Ground Floor Layout Plans as Proposed - AMENDED 09 10 2018 3656 kb 09/10/2018
First Floor Layout Plans as Proposed - AMENDED 09 10 2018 312 kb 09/10/2018
Consultee Name Date Letter Sent Consultation Expiry Date
Councillor D Dowson (ST GERMAINS) 29/08/2018 -
Councillor K King (ST GERMAINS) 29/08/2018 -
Councillor M Wilson (ST GERMAINS) 29/08/2018 -
Saltburn, Marske and New Marske Parish Council 29/08/2018 -
Strategic Planning Team (CA & LB) 29/08/2018 -
Address Date Sent Date Reconsulted Expiry Date
1 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
3 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
5 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
7 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
9 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
11 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
13 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
15 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
17 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
19 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
24 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
26 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
28 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
30 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
32 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
34 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
36 CHURCH STREET MARSKE BY THE SEA REDCAR TS11 7ND 29/08/2018 - 19/09/2018
LONGARTH 143A HIGH STREET MARSKE BY THE SEA REDCAR TS11 6JX 29/08/2018 - 19/09/2018
166A HIGH STREET MARSKE BY THE SEA REDCAR TS11 7NB 29/08/2018 - 19/09/2018
168 HIGH STREET MARSKE BY THE SEA REDCAR TS11 7NB 29/08/2018 - 19/09/2018
FIRST FLOOR FLAT 170 HIGH STREET MARSKE BY THE SEA REDCAR TS11 7NB 29/08/2018 - 19/09/2018
GROUND FLOOR FLAT 170 HIGH STREET MARSKE BY THE SEA REDCAR TS11 7NB 29/08/2018 - 19/09/2018
172 HIGH STREET MARSKE BY THE SEA REDCAR TS11 7NB 29/08/2018 - 19/09/2018
174 HIGH STREET MARSKE BY THE SEA REDCAR TS11 7NB 29/08/2018 - 19/09/2018
176 HIGH STREET MARSKE BY THE SEA REDCAR TS11 7NB 29/08/2018 - 19/09/2018
180 HIGH STREET MARSKE BY THE SEA REDCAR TS11 7NB 29/08/2018 - 19/09/2018
180A HIGH STREET MARSKE BY THE SEA REDCAR TS11 7NB 29/08/2018 - 19/09/2018
2 ST GERMAINS LANE MARSKE BY THE SEA REDCAR TS11 7LG 29/08/2018 - 19/09/2018
176 High Street, Marske-by-the-sea, TS11 7NB 29/08/2018 - 19/09/2018
Site or Press Description Display Date Expiry Date
B CONSERVATION AREA SEC 73 31/08/2018 21/09/2018