R/2018/0244/CA

Planning Application Details - Official Consultation has expired.

Location
PLOT 4 CHERRY TREE CROFT HIGH STREET BROTTON
Proposal
DETACHED DWELLING WITH ATTACHED DOUBLE GARAGE WITH ASSOCIATED LANDSCAPING (AMENDED SCHEME)
Application Type
Conservation Area
Status
Approved
Parish(es)
Skelton and Brotton CP
Applicant
MR WARREN SPRINGGAY
Applicant's Address
17 EDGEHILL GARDENS BROTTON SALTBURN TS12 2BZ
Agent
MR WARREN SPRINGGAY
Agent's Address
17 EDGEHILL GARDENS BROTTON SALTBURN TS12 2BZ
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
11/05/2018
Weekly List Expiry Date
24/05/2018
Date Received
27/04/2018
Date Valid
08/05/2018
Expiry
03/07/2018
Consultation Expiry
08/06/2018
associated_bldreg
R/2019/0314/BR
Decision
GRANT PLANNING PERMISSION
Decision Date
03/07/2018
Decision Level
Delegated

Conditions table
# Condition Details
1 The development shall not be begun later than the expiration of THREE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2 The development hereby permitted shall be carried out in accordance with the following approved plans: Site Layout (Sheet 2 of 5) received by the Local Planning Authority on 27/04/18 Site Sections (Sheet 3 of 5) received by the Local Planning Authority on 27/04/18 Proposed Floor Plans and Sections (Sheet 4 of 5) received by the Local Planning Authority on 27/04/18 Proposed Elevations (Sheet 5 of 5) received by the Local Planning Authority on 27/04/18 REASON: To accord with the terms of the planning application.
3 The development shall be built in the materials as identified on the application form received by the Local Planning Authority on 27/04/18. REASON: To ensure the use of satisfactory materials.
4 A minimum of two car parking spaces shall be provided within the curtilage of each dwelling prior to first occupation and thereafter retained for parking purposes. Details of the surface treatments to be used shall be submitted to and agreed in writing with the Local Planning Authority prior to construction of the parking spaces. REASON: To ensure that there is adequate on-site car parking to serve the development.
5 Prior to the first occupation of the development boundary walls and fences shall have been erected in accordance with a scheme that has first been agreed in writing with the Local Planning Authority and shall thereafter be maintained. REASON: In the interests of visual and residential amenity.
6 Prior to the commencement of the development, details of the methods to be used to protect the existing trees on the site from construction work shall be submitted to and approved in writing by the Local Planning Authority, and such measures as approved shall be carried out before the development commences and be maintained throughout the period of construction until the completion of the development. REASON: To ensure that existing trees/hedges on and adjacent to the site which are to be retained, are protected from vehicles and works involved in the construction of the development.
7 A landscaping scheme shall be submitted to, and approved in writing by, the Local Planning Authority prior to the commencement of development. The details shall include size, type and species of plant and indicate the proposed layout and surfacing of all open areas. A programme of work shall also be submitted and implemented in accordance with the approved details. REASON: To reserve the rights of the Local Planning Authority with regard to these matters.
8 All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in the first planting and seeding season following the occupation of the buildings or the completion of the development, whichever is sooner, and any trees or plants which within a period of ten years from the completion of the development die, are removed, or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species unless the Local Planning Authority gives written consent to any variation. REASON: To ensure the satisfactory implementation of the approved scheme in the interests of the visual amenities of the locality.
9 In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken and where remediation is necessary a remediation scheme must be prepared, which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority. REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
10 Site clearance shall avoid the bird breeding season (March to September inclusive) unless the land is first checked by the project ecologist who will confirm the absence of nests. REASON: To ensure satisfactory protection of protected species.
11 The working hours for all construction activities on this site are limited to between 08:00 and 18:00 Mondays to Friday and 08:00 to 13:00 Saturdays and not at all on a Sunday or Bank Holidays. REASON: In the interest of neighbour amenity.
12 STATEMENT OF COOPERATIVE WORKING: The Local Planning Authority consider that the application as originally submitted is a satisfactory scheme and therefore no negotiations have been necessary.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 394 kb 27/04/2018
Consultee Responses
Consultee response - Public Rights of Way 26 kb 14/05/2018
Consultee response - Environmental Protection (Contaminated Land) 19 kb 17/05/2018
Consultee response - Environmental Protection (Nuisance) 11 kb 17/05/2018
Consultee response - Engineers (Drainage LLFA) 26 kb 18/05/2018
Consultee response - Development Engineers 16 kb 22/05/2018
Consultee response - Northumbrian Water 40 kb 23/05/2018
Consultee response - Strategic Planning (Conservation) 41 kb 04/06/2018
Consultee response - Ramblers 35 kb 04/06/2018
Decision
Decision Notice 49 kb 03/07/2018
Location Plan
Location and Site Survey Plans 193 kb 27/04/2018
Plans
Floor Plans, Elevations and Site Sections 98 kb 27/04/2018
Site Layout Plan 39 kb 27/04/2018
Supporting Documentation
Design and Access Statement 37 kb 27/04/2018
Facing Brick Details 81 kb 27/04/2018
Concrete Grey Tile Details 69 kb 27/04/2018
Screening Assessment Form 259 kb 08/05/2018
Consultee Name Date Letter Sent Consultation Expiry Date
Aboricultural Officer 11/05/2018 -
Councillor B Hunt (BROTTON) 11/05/2018 -
Councillor M Dick (BROTTON) 11/05/2018 -
Councillor M S Griffiths (HUTTON) 11/05/2018 -
Engineering Team (Highways) 11/05/2018 -
Engineers (Local Lead Flood Authority) 11/05/2018 -
Environmental Protection Team 11/05/2018 -
Housing Area Services 11/05/2018 -
Northumbrian Water Ltd 11/05/2018 -
Public Rights of Way 11/05/2018 -
Ramblers Association 11/05/2018 -
Skelton and Brotton Parish Council 11/05/2018 -
Strategic Planning Team (CA & LB) 11/05/2018 -
Address Date Sent Date Reconsulted Expiry Date
1 CHERRY TREE CROFT HIGH STREET BROTTON SALTBURN BY THE SEA TS12 2PN 11/05/2018 - 01/06/2018
44 EDGEHILL GARDENS BROTTON SALTBURN BY THE SEA TS12 2BZ 11/05/2018 - 01/06/2018
46 EDGEHILL GARDENS BROTTON SALTBURN BY THE SEA TS12 2BZ 11/05/2018 - 01/06/2018
48 EDGEHILL GARDENS BROTTON SALTBURN BY THE SEA TS12 2BZ 11/05/2018 - 01/06/2018
42 HIGH STREET BROTTON SALTBURN BY THE SEA TS12 2PG 11/05/2018 - 01/06/2018
43 HIGH STREET BROTTON SALTBURN BY THE SEA TS12 2PG 11/05/2018 - 01/06/2018
44 HIGH STREET BROTTON SALTBURN BY THE SEA TS12 2PG 11/05/2018 - 01/06/2018
45 HIGH STREET BROTTON SALTBURN BY THE SEA TS12 2PG 11/05/2018 - 01/06/2018
46 HIGH STREET BROTTON SALTBURN BY THE SEA TS12 2PG 11/05/2018 - 01/06/2018
47 HIGH STREET BROTTON SALTBURN BY THE SEA TS12 2PG 11/05/2018 - 01/06/2018
48 HIGH STREET BROTTON SALTBURN BY THE SEA TS12 2PG 14/05/2018 - 04/06/2018
49 HIGH STREET BROTTON SALTBURN BY THE SEA TS12 2PG 14/05/2018 - 04/06/2018
Site or Press Description Display Date Expiry Date
B CONSERVATION AREA SEC 73 18/05/2018 08/06/2018