Location
LAND AT TEESPORT
TEES DOCK ROAD
GRANGETOWN
Proposal
DISCHARGE OF CONDITIONS 9; 13 - 15; 23 - 24; 31 & 43 OF SECRETARY OF STATES CONSENT NOTICE R/2008/0671/EA FOR CONSTRUCTION OF 300 MWe BIOMASS FIRED POWER STATION
Application Type
Condition Discharge
Status
Approved
Parish(es)
Applicant
MGT
Applicant's Address
-
Agent
TECNICAS REUNIDAS UK
Agent's Address
TEESREP BIOMASS POWER STATION
TEES DOCK ROAD
MIDDLESBROUGH
TS6 6UD
Agent's work phone
Agent's email
Case Officer
Mrs L Hall
Case Officer Telephone
01287 612343
Case Officer Email
Lyndsey.Hall@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
22/03/2017
Date Received
28/02/2017
Date Valid
08/03/2017
Expiry
03/05/2017
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
28/04/2017
Decision Level
Delegated
| # | Condition Details |
|---|---|
| 1 | The commencement of the main development shall not take place until there has been submitted to, approved in writing by, and deposited with the Council a scheme which shall including provisions for the: i) details of siting, design, dimensions, external appearance and floor levels of all buildings and structures which are to be retained following the completion of the construction of the development. ii) details of the colour, materials and surface finishes in respect of those buildings and structures referred to in i) above. iii) details of vehicular circulation roads, parking, hardstandings, loading and unloading facilities and turning facilities on the site iv) details of artificial lighting required during the operation of the development v) details of all new or modified permanent fencing and gates required on the site vi) details of any proposed landscaping on the site vii) details of fire suppression measures and access of sire appliances to all major buildings, structures and storage areas; and viii) phasing of works included in the scheme. |
| 2 | The commencement of the Development shall not take place until there has been submitted to, approved in writing by and deposited with the Council a scheme for impact pile, or other means of pile driving, including methods and duration and shall state the selection criteria. The approved scheme shall be adhered to during the period of construction of the Development. |
| 3 | The commencement of the Development shall not take place until there has been submitted to, approved in writing by, and deposited with the Council, in consultation with the Environment Agency, a scheme showing the method and working of drainage facilities on the site. Such facilities shall be put in place in accordance with the approved scheme. |
| 4 | The scheme referred to in Condition 23 shall include: i) measures to ensure that no leachate or any contaminated surface water from the Site shall be allowed at any time to enter directly or indirectly into any watercourse or underground strata or onto adjoining land; ii) provision so as to ensure that all existing drainage systems continue to operate and that riparian owners upstream and downstream of the site are not adversely affected; iii) provision for trapped gullies in car parks, hardstandings and roadways; iv) measures to ensure that all foul sewage must drain to an approved foul sewerage and/or sewage disposal system; v) provisions to distinguish between temporary and permanent parts of the works; and vi) phasing of works. |
| 5 | The commencement of the Development shall not take place until a traffic management plan for the construction phase of the Development, to include details of the site access, the Company has been submitted, approved in writing by, and deposited with the Council, in consultation with the Highways Agency. |
| 6 | The commencement of the development shall not take place until the company has submitted to the Council the main findings and conclusions of an investigation as to whether an existing waterway and/or railway could be utilised to provide a practical, economical and environmentally advantageous (when compared and contrasted with road transportation) means of transportation to the Site of construction materials associated with the development. The results of the investigation shall be submitted to, agreed in writing by, and deposited with the Council. |
| 7 | (61) The commencement of the Development shall not take place until the Company has undertaken, in consultation with Natural England, an investigation to establish the likelihood of protected species being present on the Site. Should the investigation indicate that protected species are likely to be present on the Site then the Company shall carry out a comprehensive investigation to establish species presence and if found submit a detailed scheme of mitigation measures for approval in writing by the Council, in consultation with Natural England. Reason: To ensure that any adverse impact on protected species is avoided. |
| 8 | Prior to the commissioning of the Development the Complany shall provide a verification report on completion of the works set out in Condition (35)(c) confirming the remediation measures that have been undertaken in accordance with the methos statement and setting out measure for maintenance, further monitoring and reporting. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Consultee Responses | |||
| Consultee response - Environmental Protection (Nuisance) | 13 kb | 20/03/2017 | |
| Plans | |||
| Condition No. 23 - 24: Site Drainage - Surface Water Drainage Plan | 1576 kb | 28/02/2017 | |
| Condition No. 9: Site Details - Layout Plan | 2281 kb | 28/02/2017 | |
| Supporting Documentation | |||
| Condition No. 31 & 43: Traffic and Transport - Transport Management Plan | 8395 kb | 28/02/2017 | |
| Build Consent Design Specifications | 22 kb | 28/02/2017 | |
| Condition No. 13 - 15: Piling - Method Statement | 4487 kb | 28/02/2017 | |
| Covering Letter | 316 kb | 28/02/2017 | |
| Application Documents | |||
| PDF Compliance Decision Notice | 66 kb | 28/04/2017 | |
| PDF Compliance Decision Notice | 58 kb | 14/08/2017 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Condition Discharge - David Pedlow | 13/03/2017 | - |
| Condition Discharge - Peter Armstrong | 13/03/2017 | - |
| Engineers (Local Lead Flood Authority) | 13/03/2017 | - |
| Environmental Protection Team | 13/03/2017 | - |