Location
LOCKWOOD BECK
Proposal
PARTIAL DISCHARGE OF CONDITIONS 3, 4, 5, 6, 8, 9, 15, 18, 19, 25 & FULL DISCHARGE 26 & 27 OF PLANNING PERMISSION R/2014/0627/FFM FOR THE WINNING AND WORKING OF POLYHALITE BY UNDERGROUND METHODS INCLUDING THE CONSTRUCTION OF A MINEHEAD AT DOVE'S NEST FARM INVOLVING ACCESS, MAINTENANCE AND VENTILATION...
Application Type
Condition Discharge
Status
Approved
Parish(es)
Lockwood CP
Applicant
SIRIUS MINERALS PLC
Applicant's Address
7-10 MANOR COURT
MANOR GARTH
SCARBOROUGH
YO11 3TU
Agent
LICHFIELDS
Agent's Address
3RD FLOOR
15 ST PAUL'S STREET
LEEDS
LS1 2JG
Agent's work phone
Agent's email
Case Officer
Mrs L Hall
Case Officer Telephone
01287 612343
Case Officer Email
Lyndsey.Hall@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
22/02/2017
Date Received
10/02/2017
Date Valid
10/02/2017
Expiry
07/04/2017
Consultation Expiry
-
associated_bldreg
R/2017/0104/SB
Decision
CONDITION DISCHARGE GRANTED
Decision Date
27/03/2017
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | 3. Prior to the commencement of development, details shall be submitted to and agreed in writing by the Local Planning Authority, of proposals to provide contractors car parking and material storage within the site. The details approved shall be retained for use until completion of the development unless first agreed in writing with the Local Planning Authority. REASON: Required in the interests of highway safety to be agreed before this project commences. |
| 2 | 4. Prior to the commencement of development a construction traffic management plan shall be submitted to the Local Planning Authority for approval in writing. The approved plan shall be implemented in its entirety unless first agreed in writing with the Local Planning Authority REASON: Required in the interests of highway safety to be agreed before this project commences. |
| 3 | 5. Prior to the commencement of the use a travel plan for the construction phase shall be submitted to the Local Planning Authority for approval in writing. The approved scheme shall be implemented in its entirety unless first agreed in writing with the Local Planning Authority. REASON: Required in the interests of highway safety to be agreed before this project commences. |
| 4 | 6. Notwithstanding the landscaping details submitted a landscaping scheme shall be submitted to, and approved in writing by, the Local Planning Authority within the period of six months after the commencement of development. The details shall include a phasing plan, size, type and species of plant and indicate the proposed layout and surfacing of all open areas. A programme of work shall also be submitted and implemented in accordance with the approved details. REASON: To ensure that the landscape impacts are mitigated from the outset of the project. |
| 5 | 8. Prior to the commencement of development a phasing plan shall be submitted to the local planning authority setting out the proposed sequence of development and any associated temporary operations. REASON: Required in the interests of amenity and the operation of the highway at the outset of the project. |
| 6 | 9. Prior to the commencement of development, a Construction Environmental Management Plan (CEMP) shall be submitted to the Local Planning Authority for approval in writing. The CEMP shall include details of: a. the size, location and design of any site compounds, including how any potentially polluting materials will be stored to minimise the risk of pollution; b. all fuel/oil which shall be stored in proprietary tanks with integral bunding with a capacity equal to not less than 110% of the capacity of the tank. Such tanks shall be located on a bunded, impervious hardstanding with a capacity of not less than 110% of the largest tank or largest combined volume of connected tanks; c. all replenishment of tanks and containers and all refuelling of vehicles, plant and equipment which shall take place within that bunded, impervious hardstanding; d. a protocol to deal with any pollution that may occur during the course of construction e.g. provision of spill kits close to storage areas/compounds. This shall include training staff on their correct use; e. a protocol to deal with contaminated ground, should this be encountered, to ensure protection of water resources, e.g. appropriate sampling, laboratory testing and risk assessment; f. plant and wheel washing, which is to be carried out in a designated area of hard standing at least 10 metres from any watercourse or surface water drain; g. run-off from plant, wheel and boot washing collected in a sump, with settled solids removed regularly and water recycled and reused where possible; h. a strategy for recycling/disposing of waste; i. dust suppression and mitigation measures set out in the air quality assessment, submitted as part of the Environmental Impact Assessment shall be implemented for the period of construction. j. the process for dissemination of the approved CEMP requirements to all relevant staff/contractors throughout the construction period. k. the location of the site notice board, which shall show: i. a representative of the operators who would be available to deal promptly with any complaints; ii. the telephone number of the Minerals Planning Authority in respect of any queries regarding l. parking, loading, unloading, security and lighting during construction, to include: • the parking of vehicles of site operatives and visitors clear of the highway •loading and unloading of plant and materials storage of plant and materials used in constructing the Development •erection and maintenance of security fencing • a scheme for recycling/disposing of waste resulting from demolition and construction works •the use of lighting such that the safety of highways users is not affected; m. a protocol for prior notification of nearby occupiers of any blasting and/or piling operations. Development shall be carried out in accordance with the measures set out in the approved CEMP unless otherwise agreed in writing with the Local Planning Authority. REASON: In the interest of public amenity, highway safety, to reduce the risk of pollution to ground and surface water it is required at the outset of the project. |
| 7 | 15. Notwithstanding the details submitted prior to the construction of any buildings or other structures details of external materials including samples shall be submitted to the Local Planning Authority for approval in writing. The development shall not be carried out except in accordance with the approved materials. REASON: To ensure the use of satisfactory external cladding materials and an acceptable form of external treatment. |
| 8 | 18. A lighting plan for both the construction and operational phases of the project shall be submitted to the Local Planning Authority for approval in writing prior to the installation of any lighting at any of the sites. The plan shall be implemented in accordance with the approved scheme unless otherwise agreed with the local planning authority. REASON: To ensure the satisfactory implementation of the approved scheme in the interests of any birds and bats within the area. |
| 9 | 19. Prior to commencement of development written details of vegetation to be retained, established and created and the provision of bird and bat boxes to be installed shall be submitted to the Local Planning Authority for approval in writing. The approved details shall be implemented prior to the completion of the development and thereafter maintained. REASON: Required from the outset in the interests of habitat protection and enhancement. |
| 10 | 25. Notwithstanding the information submitted detailed plans shall be submitted for ecological mitigation and enhancement for each of the sites (and shall include a phasing plan) to the Local Planning Authority for approval in writing prior to the removal of any vegetation at the sites. The approved scheme shall be implemented unless otherwise first agreed in writing with the Local Planning Authority. REASON: Required in the interests of biodiversity prior to the removal of any vegetation. |
| 11 | 26. Prior to its construction details of the temporary bridge proposed over Lockwood Beck shall be submitted to the Local Planning Authority for approval in writing. The approved scheme shall be implemented in its entirety and thereafter be maintained. REASON: In the interests of the appearance of the site. |
| 12 | 27. Prior to the commencement of construction at the Lockwood Beck site, a pre-construction otter survey of the whole site shall be conducted by a suitably qualified and experienced ecologist. Should evidence of otter activity be found, adequate mitigation proposals must then be submitted to, and approved in writing by the Local Planning Authority. Development shall then proceed only in strict accordance with these proposals, and any timing/phasing contained therein. REASON: In order to ensure the protection of otter from the outset of the project and throughout the development. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Condition Discharge - Janet Horne | 15/02/2017 | - |
| Condition Discharge - Natural England | 15/02/2017 | - |
| Condition Discharge - Peter Armstrong | 15/02/2017 | - |
| Condition Discharge - Policy | 15/02/2017 | - |
| Environmental Protection Team | 15/02/2017 | - |
| Natural England | 15/02/2017 | - |
| Natural Heritage Manager | 15/02/2017 | - |
| North York Moors National Park | 01/03/2017 | - |