Location
LAND NORTH OF MIDDLESBROUGH ROAD
GUISBOROUGH
Proposal
DISCHARGE OF CONDITION 5, 10, 11, 20 & 21 OF PLANNING PERMISSION R/2014/0563/FFM RESIDENTIAL DEVELOPMENT OF 14 DETACHED DWELLINGS INCLUDING ASSOCIATED SITE INFRASTRUCTURE AND DRAINAGE
Application Type
Condition Discharge
Status
Approved
Parish(es)
Guisborough CP
Applicant
GENTOO HOMES
Applicant's Address
AKELER HOUSE
1 EMPEROR WAY
DOXFORD INTERNATIONAL
BUSINESS PARK
SUNDERLAND
SR3 3XR
Agent
GENTOO HOMES
Agent's Address
AKELER HOUSE
1 EMPEROR WAY
DOXFORD INTERNATIONAL
BUSINESS PARK
SUNDERLAND
SR3 3XR
Agent's work phone
Agent's email
Case Officer
Mrs L Hall
Case Officer Telephone
01287 612343
Case Officer Email
Lyndsey.Hall@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
19/07/2016
Date Received
16/06/2016
Date Valid
06/07/2016
Expiry
31/08/2016
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
08/08/2016
Decision Level
Delegated
| # | Condition Details |
|---|---|
| 1 | Prior to the first occupation of the development boundary walls and fences shall have been erected in accordance with a scheme that has first been agreed in writing with the Local Planning Authority and shall thereafter be maintained. REASON: In the interests of visual and residential amenity. |
| 2 | Unless otherwise agreed by the Local Planning Authority in writing, development other than that required to be carried out as part of an approved scheme of remediation must not commence until parts (a) to (c) have been complied with. If unexpected contamination is found after development has begun, development must be halted on that part of the site affected by the unexpected contamination to the extent specified by the Local Planning Authority in writing until condition (e) has been complied with in relation to that contamination. (a) Site Characterisation An investigation and risk assessment, in addition to any assessment provided with the planning application, must be completed in accordance with a scheme to assess the nature and extent of any contamination on the site, whether or not it originates on the site. The contents of the scheme are subject to the approval in writing of the Local Planning Authority. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The written report is subject to the approval in writing of the Local Planning Authority. The report of the findings must include: (i) a survey of the extent, scale and nature of contamination; (ii) an assessment of the potential risks to: • human health, • property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes, • adjoining land, • groundwaters and surface waters, • ecological systems, • archeological sites and ancient monuments; (iii) an appraisal of remedial options, and proposal of the preferred option(s). This must be conducted in accordance with DEFRA and the Environment Agency’s ‘Model Procedures for the Management of Land Contamination, CLR 11’. (b) Submission of Remediation Scheme A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. (c) Implementation of Approved Remediation Scheme The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report (referred to in PPS23 as a validation report) that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval in writing of the Local Planning Authority. (d) Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken in accordance with the requirements of part (a) and where remediation is necessary a remediation scheme must be prepared in accordance with the requirements of part (b), which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority. (e) Long Term Monitoring and Maintenance A monitoring and maintenance scheme to include monitoring the long-term effectiveness of the proposed remediation over a period of 10 years, and the provision of reports on the same must be prepared, both of which are subject to the approval in writing of the Local Planning Authority. Following completion of the measures identified in that scheme and when the remediation objectives have been achieved, reports that demonstrate the effectiveness of the monitoring and maintenance carried out must be produced, and submitted to the Local Planning Authority. This must be conducted in accordance with DEFRA and the Environment Agency’s ‘Model Procedures for the Management of Land Contamination, CLR 11’ REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 3 | A minimum of 10% of the sites energy requirements shall be provided by embedded renewable energy, unless otherwise first agreed in writing with the Local Planning Authority. REASON: In the interests of sustainability. |
| 4 | Prior to the commencement of development a traffic management plan shall be submitted to and agreed in writing with the Local Planning Authority. The scheme hereby approved shall then be implemented in accordance with the traffic management plan unless first agreed in writing with the Local Planning Authority. REASON: In the interest of highways safety. |
| 5 | Prior to the commencement of development, details shall be submitted to and agreed in writing by the Local Planning Authority, of proposals to provide contractors car parking and material storage within the site. The details approved shall be retained for use until completion of the development unless first agreed in writing with the Local Planning Authority. REASON: In the interest of highway safety. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 136 kb | 23/06/2016 | |
| Plans | |||
| Condition 5 - Pier Caps | 80 kb | 23/06/2016 | |
| Condition 5 - Timber Fencing | 96 kb | 23/06/2016 | |
| Condition 5 - Boundary Railings | 70 kb | 23/06/2016 | |
| Condition 5 - Boundary walls | 78 kb | 23/06/2016 | |
| Condition 5 - Site Layout | 1789 kb | 23/06/2016 | |
| Condition 5 - Boundary walls | 75 kb | 23/06/2016 | |
| Condition 21 - Materials Layout | 428 kb | 23/06/2016 | |
| Supporting Documentation | |||
| Condition 20 - Reclamation Method Statement | 2094 kb | 23/06/2016 | |
| Condition 20 - Geotechnical & Contamination report | 11735 kb | 23/06/2016 | |
| CONDITION DISCHARGE APPLICATION | |||
| Additional condition discharge 10 and 11 | 453 kb | 06/07/2016 | |
| Word compliance decision notice | 101 kb | 08/08/2016 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Condition Discharge - Environmental Protection | 21/07/2016 | - |
| Condition Discharge - Janet Horne | 21/07/2016 | - |