Location
LAND OFF
PHEASANTS FIELD LANE
SKELTON
Proposal
DISCHARGE OF CONDITIONS 3, 4, 5, 7, 8 AND 16 OF PLANNING PERMISSION R/2014/0452/FFM FOR RETAIL FOODSTORE WITH VEHICULAR ACCESS, CAR PARKING, SERVICING AREA AND ASSOCIATED LANDSCAPING
Application Type
Condition Discharge
Status
Approved
Parish(es)
Skelton and Brotton CP
Applicant
ALDI STORES LTD
Applicant's Address
ALDI UK
FAVERDALE INDUSTRIAL ESTATE
DARLINGTON
COUNTY DURHAM
DL3 0UW
Agent
PROJEKT ARCHITECTS
Agent's Address
MEDIA EXCHANGE 2
COQUET STREET
NEWCASTLE UPON TYNE
TYNE AND WEAR (MET COUNTY)
NE1 2QB
Agent's work phone
Agent's email
Case Officer
Mrs L Hall
Case Officer Telephone
01287 612343
Case Officer Email
Lyndsey.Hall@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
15/01/2016
Date Valid
15/01/2016
Expiry
11/03/2016
Consultation Expiry
-
associated_bldreg
-
Decision
CONDITION DISCHARGE GRANTED
Decision Date
27/04/2016
Decision Level
-
| # | Condition Details |
|---|---|
| 1 | Prior to the commencement of development, details shall be submitted to and agreed in writing by the Local Planning Authority, of proposals to provide contractors car parking and material storage within the site. The details approved shall be retained for use until completion of the development unless first agreed in writing with the Local Planning Authority. REASON: In the interest of highways safety. |
| 2 | Prior to the commencement of development a traffic management plan for the construction phase of the development shall be submitted to and agreed in writing with the Local Planning Authority. The scheme hereby approved shall then be implemented in accordance with the details provided within the traffic management plan unless first agreed in writing with the Local Planning Authority. REASON: In the interest of highways safety. |
| 3 | Prior to commencement of any development works on the site, the whole development shall be subject to a Stage 1 & 2 Road Safety Audit. The Audit shall be carried out in accordance with DMRB HD19/03 and shall be submitted to and approved in writing by the local planning authority. The development shall be carried out in accordance with the approved audit. REASON: In the interests of safety and the free flow of traffic on surrounding roads and junctions. |
| 4 | Prior to the commencement of development details of a surface water drainage scheme for the site, based on sustainable drainage principles and as assessment of the hydrological and hydrogeological context of the development, shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall ensure that surface water from the parking and hardstanding areas will pass through oil interceptors prior to discharge and also include details on how the system shall be maintained and managed for the design life of the development. The scheme shall subsequently be implemented in accordance with the approved details before the development is completed. REASON: To prevent the increased risk of flooding, to improve and protect water quality, improve habitat and amenity and ensure future maintenance of the surface water drainage system. |
| 5 | Prior to the commencement of development additional gas monitoring should be carried out on the site in accordance with details agreed with the Local Planning Authority. The results together with further recommendations shall be submitted to and agreed in writing with the Local Planning Authority. Any recommendations proposed and agreed by the Local Planning Authority shall be installed prior to the completion of the development. The scheme hereby approved shall be implemented in accordance with the recommendations approved by the Local Planning Authority. REASON: To ensure than any risks from gas migration are minimised. |
| 6 | The retail development shall be implemented in accordance with the sustainability strategy received by the Local Planning Authority on 15.07.2014. Prior to the commencement of the construction of the food store the strategy will be reviewed to determine whether any alternative technologies have been advanced in the interim period which are a viable and preferable alternative to those set out in the strategy. Details of any alternative technologies shall be submitted to and agreed in writing. The scheme shall be implemented in accordance with the details agreed. REASON: To ensure a sustainable form of development. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Form | |||
| Application Form | 108 kb | 15/01/2016 | |
| Plans | |||
| Site Set-up and Traffic Management Plan | 992 kb | 15/01/2016 | |
| Drainage Layout Sheet 1 | 527 kb | 15/01/2016 | |
| Drainage Layout Sheet 2 | 1291 kb | 15/01/2016 | |
| Drainage Layout | 626 kb | 15/01/2016 | |
| Supporting Documentation | |||
| Gas Monitoring Record | 65 kb | 15/01/2016 | |
| Sustainability Statement | 164 kb | 15/01/2016 | |
| Stage 1 and 2 (Part) Road Safety Audit | 5004 kb | 15/01/2016 | |
| Road Safety Audit Form | 51 kb | 15/01/2016 | |
| CONDITION DISCHARGE APPLICATION | |||
| PA comments | - kb | 17/03/2016 | |
| email from S Kerr | 58 kb | 24/03/2016 | |
| DP comments | 56 kb | 24/03/2016 | |
| MG comments | 98 kb | 24/03/2016 | |
| Email to Agent request further info. | 39 kb | 24/03/2016 | |
| update given and additional req | 99 kb | 24/03/2016 | |
| information req | 452 kb | 24/03/2016 | |
| info req and extension | 52 kb | 04/04/2016 | |
| Email C Barr | 1484 kb | 06/04/2016 | |
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Condition Discharge - David Pedlow | 03/02/2016 | - |
| Condition Discharge - Environmental Protection | 03/02/2016 | - |
| Condition Discharge - Peter Armstrong | 03/02/2016 | - |
| Engineers (Local Lead Flood Authority) | 03/02/2016 | - |