Location
ASDA
2 NORTH STREET
SOUTH BANK
TS6 6AB
Proposal
DEMOLITION OF EXISTING PETROL FILLING STATION AND JET WASH; REPLACE WITH NEW 3 PUMP FULLY AUTOMATED PETROL FILLING STATION INCLUDING NEW FORECOURT CANOPY; CONTROL UNIT; AIR/WATER UNIT; CCTV/LIGHTING COLUMNS AND ASSOCIATED WORKS
Application Type
Full
Status
Approved
Parish(es)
Applicant
ASDA STORES LTD
Applicant's Address
ASDA HOUSE
SOUTHBANK
GREAT WILSON STREET
LEEDS
WEST YORKSHIRE
LS11 5AD
Agent
C & A DESIGN LTD
Agent's Address
2B - 3B HATHERSAGE BUSINESS PARK
HEATHER LANE
HATHERSAGE
SHEFFIELD
DERBYSHIRE
S321DP
Agent's work phone
Agent's email
Case Officer
Mrs C Griffiths
Case Officer Telephone
01287 612629
Case Officer Email
claire.griffiths@redcar-cleveland.gov.uk
Consultation Start
08/12/2015
Weekly List Expiry Date
16/12/2015
Date Received
24/11/2015
Date Valid
02/12/2015
Expiry
27/01/2016
Consultation Expiry
01/01/2016
associated_bldreg
R/2015/0706/SB
Decision
GRANT PLANNING PERMISSION
Decision Date
27/01/2016
Decision Level
Delegated
| # | Condition Details |
|---|---|
| 1 | The development shall not be begun later than the expiration of THREE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990. |
| 2 | The development hereby permitted shall be carried out in accordance with the following approved plans: (PA) 03 Rev A received by the Local Planning Authority on 24.11.2015 (PA) 05 Rev A received by the Local Planning Authority on 24.11.2015 (PA) 07 Rev A received by the Local Planning Authority on 24.11.2015 (PA) 08 Rev A received by the Local Planning Authority on 24.11.2015 (PA) 09 Rev A received by the Local Planning Authority on 24.11.2015 (PA) 10 Rev A received by the Local Planning Authority on 24.11.2015 REASON: To accord with the terms of the planning application. |
| 3 | 1. Site characterization An investigation and risk assessment, in addition to any assessment provided with the planning application, must be completed in accordance with a scheme to assess the nature and extent of any contamination on the site, whether or not it originates on the site. The contents of the scheme are subject to the approval in writing of the Local Planning Authority. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The written report is subject to the approval in writing of the Local Planning Authority. The report of the findings must include: (i) a survey of the extent, scale and nature of contamination; (ii) an assessment of the potential risks to: • human health • property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes • adjoining land • groundwaters and surface waters • ecological systems • archeological sites and ancient monuments (iii) an appraisal of remedial options, and proposal of the preferred option(s). This must be conducted in accordance with DEFRA and the Environment Agency’s ‘Model Procedures for the Management of Land Contamination, CLR 11’. 2. Submission of Remediation Scheme A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. 3. Implementation of Approved Remediation Scheme The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report (referred to in PPS23 as a validation report) that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval in writing of the Local Planning Authority. 4. Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken in accordance with the requirements of part 1, and where remediation is necessary a remediation scheme must be prepared in accordance with the requirements of part 2, which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority in accordance with part 3. REASON: To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 4 | The Local Planning Authority considers that the application as originally submitted is a satisfactory scheme and therefore no negotiations have been necessary. |
| 5 | Informative Note: Under the Environmental Permitting (England and Wales) Regulations 2010 (as amended), the existing site is permitted by the Local Authority to operate the unloading of petrol into storage at a petrol station and unloading of petrol into road vehicles. Please contact with the Environmental Protection Team regarding any variation to the existing permit reference: RCBC/P020/15. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Consultee Name | Date Letter Sent | Consultation Expiry Date |
|---|---|---|
| Engineering Team (Highways) | 08/12/2015 | - |
| Environment Agency | 08/12/2015 | - |
| Environmental Protection Team | 08/12/2015 | - |
| Environmental Protection Team | 08/12/2015 | - |
| Health & Safety-Food (Food Team) | 08/12/2015 | - |
| Lyndsey Hall - SUDS Officer | 08/12/2015 | - |
| Address | Date Sent | Date Reconsulted | Expiry Date |
|---|---|---|---|
| R I CONSTRUCTION LTD TILBURY ROAD SOUTH BANK MIDDLESBROUGH TS6 6AW | 08/12/2015 | - | 29/12/2015 |
| DECORATIVE AGGREGATES SMITHS DOCK ROAD SOUTH BANK MIDDLESBROUGH TS6 6AL | 08/12/2015 | - | 29/12/2015 |
| TDH GROUP LTD UNIT 2D NELSON COURT SOUTH BANK MIDDLESBROUGH TS6 6BL | 08/12/2015 | - | 29/12/2015 |
| Site or Press | Description | Display Date | Expiry Date |
|---|---|---|---|
| S | SITE NOTICE ONLY | 11/12/2015 | 01/01/2016 |