R/2015/0462/FF

Planning Application Details - Official Consultation has expired.

Location
TEESPORT TEES DOCK ROAD GRANGETOWN
Proposal
DEVELOPMENT AND OPERATION OF A WOOD CHIP DRYER
Application Type
Full
Status
Approved
Parish(es)
Applicant
MGT TEESSIDE LIMITED
Applicant's Address
TEESDOCK GRANGETOWN MIDDLESBOROUGH TS6 6UD
Agent
MGT TEESSIDE LIMITED
Agent's Address
TEESDOCK GRANGETOWN MIDDLESBOROUGH TS6 6UD
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
03/08/2015
Weekly List Expiry Date
07/08/2015
Date Received
27/07/2015
Date Valid
22/07/2015
Expiry
16/09/2015
Consultation Expiry
27/08/2015
associated_bldreg
R/2015/0499/SB
Decision
GRANT PLANNING PERMISSION
Decision Date
16/09/2015
Decision Level
Delegated

Conditions table
# Condition Details
1 The development shall not be begun later than the expiration of THREE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2 The development hereby permitted shall be carried out in accordance with the following approved plans: Drawing No 38893-PLN-002-0002 received by the Local Planning Authority on 22/07/15 Proposed Elevations received by the Local Planning Authority on 09/03/15 REASON: To accord with the terms of the planning application.
3 Details of the external materials to be used in the carrying out of this permission shall be submitted to, and approved in writing by the Local Planning Authority, prior to the commencement of development and the development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials.
4 Details of materials to be used for all hard surfaces shall be submitted to, and approved in writing by the Local Planning Authority, prior to the commencement of the development and the development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials.
5 Prior to the commencement of development details of a scheme for surface water drainage shall be submitted to and approved in writing by the Local Planning Authority. The surface water drainage scheme shall be based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the development. The scheme shall include provision for all surface water drainage from parking areas, hardstanding and the access road and shall include details of how the scheme shall be maintained and managed after completion. The development shall be carried out in accordance with the approved details before any part of the development is first brought into use and shall be retained and maintained in accordance with the approved details thereafter. REASON: To ensure adequate provision for drainage.
6 All activities associated with the demolition of existing buildings and structures on the Site and the construct ion of the Development shall be carried out in accordance with British Standard 5228, Parts l and 2: 1997 and Part 4: 1992 ; Noise and Vibration Control on Construction and Open Sites. REASON: To ensure any demolition works do not have an adverse impact on neighoburing land users/occupiers
7 The commencement of the Development shall not take place until there has been submitted to, approved in writing by the Local Planning Authority, a scheme for the monitoring of noise generated during the demolition of existing buildings and structures on the Site and construction of the Development. The development will then be constructed in accordance with the approved scheme. REASON: To ensure that noise generated during the demolition of existing buildings and construction activities is suitability monitored and controlled
8 The commencement of the Development shall not take place until there has been submitted to, approved in writing by the Local Planning Authority, a scheme for impact pile, or other means of pile driving, including methods and duration and shall state the selection criteria. The approved scheme shall be adhered to during the period of construction of the Development. REASON: To ensure that suitable piling techniques are used that do not adversely impact on neighbouring land users/occupiers
9 No impact piling approved shall take place on the Site on any Sunday or Bank Holiday or any other day except the between the following hours: Monday to Saturdays 0800 - 1900 Unless such work - (a) is associated with an emergency; or (b) is carried out with the prior written approval of the Council. REASON: To protect the neighbouring land users and occupiers
10 Notwithstanding the terms of Condition (9) all impact pile driving shall only take place during the months of April to October Inclusive. REASON: In the interest of local ecology both on land and within the River Tees
11 The noise generated by the normal commercial operation of the Development shall not exceed a rating level of 40 dB( A) (measured as an LA eg over 1 hour during the day and 5 minutes at night) when measured generally in accordance with BS 4142 1997 at the facades of any existing residential property at the date of this permission. REASON: To protect the amenity of neighbouring properties and occupiers
12 Such noise shall exhibit no tonal or impulse content at those properties in all weather conditions. These limitations as to noise level shall be adhered to at all times except in an emergency or in accordance with any lower noise level which may be approved by the Council pursuant to Condition (11). REASON: To protect the amenity of neighbouring properties and occupiers
13 The Local Planning Authority considers that the application as originally submitted is a satisfactory scheme and therefore no negotiations have been necessary.
14 The applicant is advised to consider the construction impacts of the development along with the York Potash construction programme.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 124 kb 27/07/2015
Consultee Responses
Consultee response - Development Engineers 33 kb 04/08/2015
Consultee response - Environmental Protection (Contaminated Land) 13 kb 05/08/2015
Decision
Decision Notice 390 kb 14/09/2022
Plans
Site Plan 2031 kb 22/07/2015
Illustrative Traffic Information 355 kb 22/07/2015
Plans and Elevations as Proposed 6425 kb 29/07/2015
Supporting Documentation
Preliminary Process Information 1523 kb 22/07/2015
Supporting Documentation 213 kb 22/07/2015
Design and Access Statement 360 kb 22/07/2015
Flood Risk Assessment 118 kb 29/07/2015
Environmental Site Investigation and Risk Assessment 1072 kb 29/07/2015
Consultee Name Date Letter Sent Consultation Expiry Date
Engineering Team (Highways) 03/08/2015 -
Environmental Protection - M Gent 03/08/2015 -
Environmental Protection Team 03/08/2015 -
Health & Safety-Food 03/08/2015 -
Address Date Sent Date Reconsulted Expiry Date
WINCHESTER HOUSE 1 GREAT WINCHESTER STREET LONDON EC2N 2DB 03/08/2015 - 24/08/2015
17-27 QUEENS SQUARE MIDDLESBROUGH TS2 1AH 03/08/2015 - 24/08/2015
SABIC UK PETROCHEMICALS LTD TEESPORT TEES DOCK ROAD GRANGETOWN 03/08/2015 - 24/08/2015
TEES AND HARTLEPOOL PORT AUTHORITY DOCKSIDE ROAD SOUTH BANK MIDDLESBROUGH TS6 6UD 03/08/2015 - 24/08/2015
Site or Press Description Display Date Expiry Date
S SITE NOTICE ONLY 06/08/2015 27/08/2015