R/2015/0011/FFM

Planning Application Details - Official Consultation has expired.

Location
LAND OFF WESTFIELD WAY LOFTUS
Proposal
DETACHED PART TWO/PART THREE STOREY BUILDING FOR 60 EXTRA CARE APARTMENTS INCLUDING COMMUNAL FACILITIES; INSTALLATION OF 2.4M BOUNDARY FENCING AND1.5M HIGH RAILINGS INCLUDING ASSOCIATED CAR PARKING AND LANDSCAPING SCHEME
Application Type
Major Application
Status
Approved
Parish(es)
Loftus CP
Applicant
GALLIFORD TRY
Applicant's Address
ESH PLAZA SIR BOBBY ROBSON WAY NEWCASTLE UPON TYNE NE13 9BA
Agent
BARTON WILLMORE
Agent's Address
ROTTERDAM HOUSE 116 QUAYSIDE NEWCASTLE UPON TYNE NE1 3DY
Agent's work phone
Agent's email
Case Officer
Mrs C Griffiths
Case Officer Telephone
01287 612629
Case Officer Email
claire.griffiths@redcar-cleveland.gov.uk
Consultation Start
06/02/2015
Weekly List Expiry Date
04/02/2015
Date Received
08/01/2015
Date Valid
22/01/2015
Expiry
26/06/2015
Consultation Expiry
27/02/2015
associated_bldreg
R/2015/0039/SB
Decision
GRANT PLANNING PERMISSION
Decision Date
25/06/2015
Decision Level
Delegated

Conditions table
# Condition Details
1 The development shall not be begun later than the expiration of THREE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2 The development hereby permitted shall be carried out in accordance with the following approved plans: Drainage Strategy (000-01) received by the Local Planning Authority on 12.06.2015 14.014/102 P0 received by the Local Planning Authority on 22.01.2015 14.014/101 P0 received by the Local Planning Authority on 06.01.2015 14.014/103 P2 received by the Local Planning Authority on 06.02.2015 14.014/201 P1 received by the Local Planning Authority on 22.01.2015 14.014/202 P2 received by the Local Planning Authority on 22.01.2015 14.014/203 P1 received by the Local Planning Authority on 22.01.2015 14.014/201/P1 received by the Local Planning Authority on 22.01.2015 N409-PP-0001 received by the Local Planning Authority on 28.01.2015 REASON: To accord with the terms of the planning application.
3 In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken, and where remediation is necessary a remediation scheme must be prepared, which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority. REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
4 The scheme hereby approved shall be implemented in accordance with the construction method and traffic management plan received by the Local Planning Authority on 09.04.2015 unless first agreed in writing with the Local Planning Authority. REASON: In the interest of highways safety.
5 The contractors car parking and material storage shall be installed within the site prior to the commencement of development in accordance with the details shown on the traffic management plan received by the Local Planning Authority on 09.04.2015. The details approved shall be retained for use until completion of the development unless first agreed in writing with the Local Planning Authority. REASON: To ensure the facilities are provided on site in a timely manor and in the interest of highways safety.
6 Details of materials to be used for all hard surfaces shall be submitted to, and approved in writing by the Local Planning Authority, prior to the use on site and the development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials.
7 Prior to the first occupation of the development boundary walls and fences shall have been erected in accordance with a scheme that has first been agreed in writing with the Local Planning Authority and shall thereafter be maintained. REASON: In the interests of visual and residential amenity.
8 The development, hereby approved, shall be constructed in accordance with the materials detailed on drawings 14.014/210 P1 received by the Local Planning Authority on 22.01.2015. REASON: To ensure the use of satisfactory materials and to accord with the terms of the planning application.
9 Prior to the occupation of the building hereby approved the parking spaces shown on drawing 14.014/102P0, received by the Local Planning Authority on 22.01.2015, shall be made available for use. The parking spaces shall be retained and made available for the lifetime of the development. REASON: In the interest of highways safety.
10 The working hours for all construction activities on this site are limited to between 08:00 and 18:00 Mondays to Friday and 08:00 to 13:00 Saturdays and not at all on a Sunday or Bank Holidays. REASON: In the interest of neighbour amenity.
11 All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in the first planting and seeding season following the occupation of the buildings or the completion of the development, whichever is sooner, and any trees or plants which within a period of ten years from the completion of the development die, are removed, or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species unless the Local Planning Authority gives written consent to any variation. REASON: To ensure the satisfactory implementation of the approved scheme in the interests of the visual amenities of the locality.
12 Statement of Co-operative Working: The Local Planning Authority considers that the application as originally submitted did not meet with the local policies and guidance. Following discussions with the applicant / agent a satisfactory scheme has been negotiated.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 127 kb 23/01/2015
Consultee Responses
Consultee response - Northumbrian Water 99 kb 28/01/2015
Consultee response - Police ALO 39 kb 28/01/2015
Consultee response - Highways Team (1) 41 kb 02/02/2015
Consultee response - Planning Nuisance Officer 16 kb 03/02/2015
Consultee response - Contaminated Land Officer 15 kb 03/02/2015
Consultee response - Loftus Town Council 70 kb 04/02/2015
Consultee response - Natural England 143 kb 06/02/2015
Consultee response - Highways Team (2) 35 kb 09/02/2015
Consultee response - Director of Adult Services 40 kb 10/02/2015
Consultee response - Policy 23 kb 11/02/2015
Consultee response - NEAR 71 kb 19/02/2015
Consultee response - Development Engineers 99 kb 18/06/2015
Consultee response - Northumbrian Water 64 kb 22/06/2015
Decision
Decision Notice 46 kb 25/06/2015
Location Plan
Location Plan 195 kb 08/01/2015
Plans
Site Layout Plan 2116 kb 08/01/2015
Site Plan as Existing 870 kb 08/01/2015
Ground Floor Layout Plans 860 kb 23/01/2015
Lower Ground Floor Layout Plans 386 kb 23/01/2015
Site Plan as Proposed 2338 kb 23/01/2015
First Floor Layout Plans 606 kb 23/01/2015
Elevations 2305 kb 23/01/2015
Landscaping Plan 796 kb 28/01/2015
Site Layour Plan Amended 06 02 2015 2109 kb 06/02/2015
Drainage Strategy 2434 kb 16/06/2015
Supporting Documentation
Travel Plan 1197 kb 08/01/2015
Planning Statement 274 kb 08/01/2015
Site Investigation Report 11172 kb 23/01/2015
Transport Statement 10990 kb 23/01/2015
Statement of Community Involvement 7946 kb 23/01/2015
Desk Top Study 11523 kb 23/01/2015
Design and Access Statement 11876 kb 23/01/2015
Construction Method & Traffic Management Details 675 kb 09/04/2015
Application Documents
Screening Opinion Response Reg 7 (PDF) 98 kb 19/03/2015
Consultee Name Date Letter Sent Consultation Expiry Date
Aboricultural Officer 27/01/2015 -
Adult Services 27/01/2015 -
Asset Management Team Fao Guy Allen 27/01/2015 -
Cleveland Police ALO - Steve Cranston 27/01/2015 -
Councillor D Fitzpatrick 27/01/2015 -
Councillor E M Jackson (LOFTUS) 27/01/2015 -
Councillor Mrs M Lanigan (LOFTUS) 27/01/2015 -
Engineering Team (Highways) 02/02/2015 -
Engineering Team (Highways) 06/02/2015 -
Engineering Team (Highways) 09/04/2015 -
Engineering Team (Highways) 16/06/2015 -
Environmental Protection - M Gent 27/01/2015 -
Environmental Protection Team 27/01/2015 -
Executive Management Team 27/01/2015 -
Housing Area Services 27/01/2015 -
Loftus Town Council 27/01/2015 -
Natural England 27/01/2015 -
NEAR Ltd (Archaeological Services) 27/01/2015 -
Northumbrian Water Ltd 27/01/2015 -
Northumbrian Water Ltd 16/06/2015 -
Place Investment Team 27/01/2015 -
Strategic Planning Team (Policy) 27/01/2015 -
Address Date Sent Date Reconsulted Expiry Date
Loftus Town Hall High St - - -
Site or Press Description Display Date Expiry Date
B ARTICLE 15 06/02/2015 27/02/2015