R/2014/0586/FFM

Planning Application Details - Official Consultation has expired.

Location
LAND ADJACENT TO 34 - 46 ELLERBECK WAY ORMESBY
Proposal
TWO STOREY BUILDING FOR 12 SUPPORTED LIVING APARTMENTS; CAR PARKING; PERIMETER FENCING AND LANDSCAPING
Application Type
Major Application
Status
Approved
Parish(es)
Applicant
GALIFORD TRY
Applicant's Address
2 ESH PLAZA SIR BOBBY ROBSON WAY GREAT PARK NEWCASTLE UPON TYNE TYNE AND WEAR NE13 9BA
Agent
BARTONWILLMORE
Agent's Address
ROTTERDAM HOUSE 116 QUAYSIDE NEWCASTLE NE1 3DY
Agent's work phone
Agent's email
Case Officer
Mrs C Griffiths
Case Officer Telephone
01287 612629
Case Officer Email
claire.griffiths@redcar-cleveland.gov.uk
Consultation Start
23/09/2014
Weekly List Expiry Date
30/09/2014
Date Received
10/09/2014
Date Valid
17/09/2014
Expiry
17/12/2014
Consultation Expiry
17/10/2014
associated_bldreg
R/2014/0815/BR
Decision
GRANT PLANNING PERMISSION
Decision Date
17/12/2014
Decision Level
Delegated

Conditions table
# Condition Details
1 The development shall not be begun later than the expiration of THREE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2 The development hereby permitted shall be carried out in accordance with the following approved plans: P01 received by the Local Planning Authority on 10.09.2014 14.011/103B received by the Local Planning Authority on 24.10.2014 14.011/110D received by the Local Planning Authority on 24.10.2014 14.011/111/D received by the Local Planning Authority on 24.10.2014 P05 A received by the Local Planning Authority on 10.09.2014 P06 received by the Local Planning Authority on 10.09.2014 P07 received by the Local Planning Authority on 10.09.2014 L119-PP-0001 received by the Local Planning Authority on 09.10.2014 REASON: To accord with the terms of the planning application.
3 The working hours for all construction activities on this site are limited to between 08:00 and 18:00 Mondays to Friday and 08:00 to 13:00 Saturdays and not at all on a Sunday or Bank Holidays. REASON: In the interest of neighbour amenity.
4 All planting, seeding or turfing shall be carried out in the first planting and seeding season following the occupation of the buildings or the completion of the development, whichever is sooner, and any trees or plants which within a period of five years from the completion of the development die, are removed, or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species unless the Local Planning Authority gives written consent to any variation. REASON: To ensure the satisfactory implementation of the approved scheme in the interests of the visual amenities of the locality.
5 Details of the external materials (external cladding, render colour, roof tiles and curtain wall details) to be used in the carrying out of this permission (including samples) shall be submitted to, and approved in writing by the Local Planning Authority, prior to the use of the materials on site and the development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials.
6 Details of materials to be used for all hard surfaces shall be submitted to, and approved in writing by the Local Planning Authority, prior to the installation of the materials on site and the development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials.
7 The contractors car parking and materials storage shall be provided in accordance with the site set up plan received by the Local Planning Authority on 21.10.2014 and retained for the whole of the construction period. REASON: To accord with the details submitted and in the interest of highways safety.
8 Prior to the occupation of the building hereby approved the seven parking spaces shown on drawing 14.011/103B shall be made available for use. REASON: In the interest of highways safety.
9 Prior to the first occupation of the development, boundary walls and fences, including those around the bin store, shall have been erected in accordance with a scheme that has first been submitted to and agreed in writing with the Local Planning Authority. The boundary treatments shall thereafter be maintained. REASON: In the interests of visual and residential amenity.
10 The development hereby approved shall be completed in accordance with the details contained within the construction method and traffic management statement received by the Local Planning Authority on 21.10.2014. REASON: To accord with the terms of the planning application and in the interest of highways safety and neighbour amenity.
11 Implementation of Approved Remediation Scheme The remediation scheme, received by the Local Planning Authority on 20.11.2014, must be carried out in accordance with its terms. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report (referred to in PPS23 as a validation report) that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval in writing of the Local Planning Authority. REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
12 Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken and where remediation is necessary a remediation scheme must be prepared, which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority. REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
13 The drainage of the site shall be completed in accordance with the following details; Plan 003 received by the Local Planning Authority on 20.11.2014 Plan 009 A received by the Local Planning Authority on 20.11.2014 Plan 000-00 received by the Local Planning Authority on 18.11.2014 Plan 005 received by the Local Planning Authority on 20.11.2014 Surface Water Drainage Calculations received by the Local Planning Authority on 10.12.2014 REASON: To ensure that the site is adequately drained and that there is no increased risk to flooding in the area.
14 The Local Planning Authority considers that the application as originally submitted is a satisfactory scheme and therefore no negotiations have been necessary.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 128 kb 10/09/2014
Consultee Responses
Consultee response - Northumbrian Water 62 kb 23/09/2014
Consultee response - Housing Area Services 37 kb 23/09/2014
Consultee response - Highways 15 kb 24/09/2014
Consultee response - Police ALO 42 kb 26/09/2014
Consultee response - Strategic Planning 21 kb 02/10/2014
Consultee response - Planning Nuisance Officer 15 kb 14/10/2014
Consultee response - Contaminated Land Officer 16 kb 14/10/2014
Consultee response - Env Protection Contaminated Land 12 kb 12/11/2014
Consultee response - Env Protection Planning Nuisance 12 kb 12/11/2014
Consultee response - Highways 115 kb 27/11/2014
Consultee response - Environmental Protection 30 kb 10/12/2014
Consultee response - Land Contamination 18 kb 10/12/2014
Decision
Decision Notice 47 kb 17/12/2014
Location Plan
Location Plan 450 kb 10/09/2014
Representations
Neighbour Comments - Overfields Primary School 40 kb 26/09/2014
Plans
Existing Topographical Survey 243 kb 10/09/2014
Proposed Block Plan 285 kb 10/09/2014
Proposed East and West Elevations 178 kb 10/09/2014
Proposed First Floor Plan SUPERSEDED 91 kb 10/09/2014
Proposed General Section 59 kb 10/09/2014
Proposed Ground Floor Plan SUPERSEDED 140 kb 10/09/2014
Proposed North and South Elevations 309 kb 10/09/2014
Proposed Site & Roof Plan SUPERSEDED 212 kb 10/09/2014
Landscaping Plan 387 kb 13/10/2014
Site Set Up 291 kb 23/10/2014
Proposed Site and Roof Plan Amended 24 10 2014 411 kb 24/10/2014
Proposed Ground Floor Amended 24 10 2014 532 kb 24/10/2014
Proposed First Floor Plan Amended 24 10 2014 485 kb 24/10/2014
Drainage Strategy Plan 588 kb 19/11/2014
Drainage Details 20.11.2014 1286 kb 20/11/2014
Section 185 Agreement Details 20.11.2014 1874 kb 20/11/2014
Site Set Up 93 kb 24/11/2014
Supporting Documentation
Design and Access Statement 13158 kb 10/09/2014
Ground Investigation Report 16112 kb 17/09/2014
Planting Schedule 58 kb 13/10/2014
External Work Layout 20 11 2014 1512 kb 20/11/2014
Remediation Strategy 20.11.2014 5319 kb 20/11/2014
Surface Water Drainage Calculations 408 kb 10/12/2014
Consultee Name Date Letter Sent Consultation Expiry Date
Adult Services 23/09/2014 -
Cleveland Police ALO - Steve Cranston 23/09/2014 -
Councillor B Ayre (NORMANBY) 23/09/2014 -
Councillor C Simms 23/09/2014 -
Councillor W A Wall 23/09/2014 -
Engineering Team (Highways) 23/09/2014 -
Engineering Team (Highways) 19/11/2014 -
Engineering Team (Highways) 24/11/2014 -
Environmental Protection - M Gent 23/10/2014 -
Environmental Protection - M Gent 24/11/2014 -
Environmental Protection - M Gent 23/09/2014 -
Environmental Protection Team 23/10/2014 -
Environmental Protection Team 23/09/2014 -
Housing Area Services 23/09/2014 -
Northumbrian Water Ltd 23/09/2014 -
Northumbrian Water Ltd 19/11/2014 -
Northumbrian Water Ltd 24/11/2014 -
Place Investment Team 23/09/2014 -
Strategic Planning Team (Policy) 23/09/2014 -
Address Date Sent Date Reconsulted Expiry Date
Daisy Lane Ormesby Middlesbrough TS7 9JF - - -
34 ELLERBECK WAY ORMESBY MIDDLESBROUGH TS7 9QH 23/09/2014 - 14/10/2014
36 ELLERBECK WAY ORMESBY MIDDLESBROUGH TS7 9QH 23/09/2014 - 14/10/2014
38 ELLERBECK WAY ORMESBY MIDDLESBROUGH TS7 9QH 23/09/2014 - 14/10/2014
40 ELLERBECK WAY ORMESBY MIDDLESBROUGH TS7 9QH 23/09/2014 - 14/10/2014
42 ELLERBECK WAY ORMESBY MIDDLESBROUGH TS7 9QH 23/09/2014 - 14/10/2014
44 ELLERBECK WAY ORMESBY MIDDLESBROUGH TS7 9QH 23/09/2014 - 14/10/2014
46 ELLERBECK WAY ORMESBY MIDDLESBROUGH TS7 9QH 23/09/2014 - 14/10/2014
26 GARSBECK WAY ORMESBY MIDDLESBROUGH TS7 9QN 23/09/2014 - 14/10/2014
28 GARSBECK WAY ORMESBY MIDDLESBROUGH TS7 9QN 23/09/2014 - 14/10/2014
1 OAKDALE ORMESBY MIDDLESBROUGH TS7 9RF 23/09/2014 - 14/10/2014
2 OAKDALE ORMESBY MIDDLESBROUGH TS7 9RF 23/09/2014 - 14/10/2014
67 STARBECK WAY ORMESBY MIDDLESBROUGH TS7 9QQ 23/09/2014 - 14/10/2014
OVERFIELDS PRIMARY SCHOOL DAISY LANE ORMESBY MIDDLESBROUGH TS7 9JF 23/09/2014 - 14/10/2014
ORMESBY CHILDRENS CENTRE OVERFIELDS PRIMARY SCHOOL DAISY LANE ORMESBY MIDDLESBROUGH TS7 9JF 23/09/2014 - 14/10/2014
ROSEDENE NURSERY SCHOOL DAISY LANE ORMESBY MIDDLESBROUGH TS7 9LF 23/09/2014 - 14/10/2014
Site or Press Description Display Date Expiry Date
B ARTICLE 15 26/09/2014 17/10/2014