R/2013/0651/FFM

Planning Application Details - Official Consultation has expired.

Location
LAND AT STOKESLEY ROAD GUISBOROUGH
Proposal
RESIDENTIAL DEVELOPMENT (188 DWELLINGS) WITH ASSOCIATED VEHICULAR AND PEDESTRIAN ACCESSES INCLUDING LANDSCAPING
Application Type
Major Application
Status
Approved
Parish(es)
Guisborough CP
Applicant
BELLWAY HOMES LTD
Applicant's Address
Agent
NATHANIEL LICHFIELD & PARTNERS
Agent's Address
NATHANIEL LICHFIELD & PARTNERS GENERATOR STUDIOS TRAFALGAR STREET NEWCASTLE TYNE AND WEAR NE1 2LA
Agent's work phone
Agent's email
Case Officer
Miss J Horne
Case Officer Telephone
Case Officer Email
Janet.Horne@redcar-cleveland.gov.uk
Consultation Start
09/10/2013
Weekly List Expiry Date
16/10/2013
Date Received
23/09/2013
Date Valid
26/09/2013
Expiry
28/11/2014
Consultation Expiry
06/11/2013
associated_bldreg
R/2013/0575/IN
Decision
GRANT PLANNING PERMISSION
Decision Date
13/11/2014
Decision Level
Committee
Committee Date
09/01/2014

Conditions table
# Condition Details
1 The development shall not be begun later than the expiration of THREE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2 The development hereby permitted shall be carried out in accordance with the following approved plans: Pod Drawing SD-00.01 Location Plan • Pod Drawing SD-00.02 Existing Site Plan • Pod Drawing SD-10.01 Rev B Masterplan As Proposed • Pod Drawing SD-10.02 Rev A Masterplan As Proposed Colour Layout • Pod Drawing SD-10.03 Rev A Masterplan As Proposed Spatial Syntax • Pod Drawing SD-10.04 Rev A Boundary Treatment Plan • Pod Drawing SD-10.05 Rev A Adoption Diagram • Pod Drawing SD-30.01 Rev A Street Scenes • Pod Drawing SD-40.01 Rev A Site Sections • Pod Drawing SD-50.01 Ash Housetype Elevations and Floor Plans • Pod Drawing SD-50.02 Birch Housetype Elevations and Floor Plans • Pod Drawing SD-50.03 Chestnut Housetype Elevations and Floor Plans • Pod Drawing SD-50.04 Hazel Housetype Elevations and Floor Plans • Pod Drawing SD-50.05 Hawthorne Housetype Elevations and Floor Plans • Pod Drawing SD-50.06 Willow Housetype Elevations and Floor Plans • Pod Drawing SD-50.07 Juniper Housetype Elevations and Floor Plans • Pod Drawing SD-50.08 Maple Housetype Elevations and Floor Plans • Pod Drawing SD-50.09 Rowan Housetype Elevations and Floor Plans • Pod Drawing SD-50.10 Acacia Housetype Elevations and Floor Plans • Pod Drawing SD-50.11 Alder Housetype Floor Plans • Pod Drawing SD-50.12 Alder Housetype Elevations • Pod Drawing SD-50.13 T2 Housetype Elevations and Floor Plans • Pod Drawing SD-50.14 T3 Housetype Elevations and Floor Plans • Pod Drawing SD-50.15 Willow Corner Housetype Elevations and Floor Plans • Pod Drawing SD-50.16 Chestnut Semi-Detached Elevations and Floor Plans • Pod Drawing SD-50.17 Birch Detached Housetype Elevations and Floor Plans • WYG Drawing C001 Rev C Proposed Site Access Junction • Southern Green Drawing 811/001 Rev C Landscape Strategy REASON: To accord with the terms of the planning application.
3 Prior to the commencement of development a construction traffic management plan shall be submitted to and agreed in writing with the Local Planning Authority. The scheme hereby approved shall then be implemented in accordance with the construction traffic management plan. REASON: In the interest of highways safety.
4 Prior to the occupation of of any part of the development hereby approved a Travel Plan shall be submitted to and agreed in writing with the Local Planning Authority. The approved travel plan scheme shall be implemented for the lifetime of the development. REASON: In the interest of highways safety.
5 Prior to the commencement of development a scheme for preventing the deposition of mud/debris on the highway shall be submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented in its entirety and adhered to for the lifetime of the construction period. REASON: In the interests of highway safety.
6 Prior to the commencement of development, details shall be submitted to and agreed in writing by the Local Planning Authority, of proposals to provide contractors car parking and material storage within the site. The details approved shall be implemented and retained for use until completion of the development. REASON: In the interest of highway safety.
7 Notwithstanding the landscape strategy submitted a landscaping scheme shall be submitted to, and approved in writing by, the Local Planning Authority prior to the commencement of development. The details shall include size, type and species of plant and indicate the proposed layout and surfacing of all open areas. A programme of work shall also be submitted and implemented in accordance with the approved details. REASON: To reserve the rights of the Local Planning Authority with regard to these matters.
8 All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in the first planting and seeding season following the occupation of the buildings or the completion of the development, whichever is sooner, and any trees or plants which within a period of ten years from the completion of the development die, are removed, or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species unless the Local Planning Authority gives written consent to any variation. REASON: To ensure the satisfactory implementation of the approved scheme in the interests of the visual amenities of the locality.
9 The proposed junction with the existing highway (Stokesley Road) shall be provided in accordance with the details set out on Plan C001 Rev C and have a visibility splay of 4.5 x 90m. The area enclosed by this splay shall be maintained to ensure there are no obstructions or any vegetation greater than 600mm in height. These junction and visibility works shall be fully implemented prior to the occupation of the first dwelling on the site. REASON: In the interests of highway safety
10 The development hereby approved shall be carried out in full accordance with all ecological mitigation measures, advice and recommendations contained within the E3 Ecology Extended Phase 1 and Protected Species Survey (July 2010) and E3 Ecology Bat Survey (September, 2013). REASON: In the interests of the protection of protected species and habitats
11 No development shall take place until a Scheme of Lighting for the site has been approved and in writing by the Local Planning Authority. Development shall be carried out in accordance with the approved details and thereafter be maintained. REASON: In the interests of amenity.
12 Prior to the first occupation of the development boundary walls and fences shall have been erected in accordance with a scheme that has first been agreed in writing with the Local Planning Authority and shall thereafter be maintained. REASON: In the interests of visual and residential amenity.
13 The working hours for all construction activities on this site are limited to between 08:00 and 18:00 Mondays to Friday and 08:00 to 13:00 Saturdays and not at all on a Sunday or Bank Holidays. REASON: In the interest of neighbour amenity.
14 In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken, and where remediation is necessary a remediation scheme must be prepared which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority Following completion of the development a report must be submitted confirming that unexpected contamination was not encountered during the development. REASON:In the interests of public protection.
15 Details of the external materials to be used in the carrying out of this permission (including samples) shall be submitted to, and approved in writing by the Local Planning Authority, prior to the commencement of development and the development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials.
16 Details of materials to be used for all hard surfaces shall be submitted to, and approved in writing by the Local Planning Authority, prior to the commencement of the development and the development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials.
17 A minimum of 10% of the sites energy requirements shall be provided by embedded renewable energy, unless otherwise first agreed in writing with the Local Planning Authority. REASON: In the interests of sustainability.
18 Any vegetation clearance on site should avoid the bird breeding season (March to August inclusive), unless a checking survey by an appropriately qualified ecologist has confirmed that no active nests are present immediately prior to works. REASON: In the interests of the protection of breeding birds
19 No development shall take place until a scheme for protecting existing occupants adjacent to the proposed development from noise, and vibration has been submitted to, and approved in writing by the Local Planning Authority. The approved scheme shall be in accordance but not exclusive with mitigation measures stated in Chapter J (paras J6.2-J6.5) of the environmental statement and be retained until the development is complete. Measured pre construction ambient noise levels suggest daytime noise levels of circa 56dBLAeq, therefore according to Table E.1 BS5228-1:2009. Construction noise shall not exceed 65dBLAeq at any noise sensitive receptor around the site. Monitoring to ensure compliance with this standard shall be carried out by the applicant in accordance with a scheme to be agreed and approved with the Local Authority and be retained until the development is complete. REASON: In the interests of residential amenity.
20 No development shall take place until a scheme for protecting the occupants of the proposed development from noise from the road network has been submitted to, and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details. REASON: In the interests of residential amenity
21 No development shall take place until a scheme for protecting the existing and proposed occupants from dust has been submitted to, and approved in writing by the Local Planning Authority. The approved scheme shall be in accordance but not exclusive with mitigation measures stated in Chapter K para K5.6 of the environmental statement and be retained until the development is complete. REASON: In the interests of residentional amenity.
22 Prior to the commencement of development a Drainage Strategy shall be submitted to the Local Planning Authority and approved in writing. The strategy shall include the following mitigation measures: 1. Limiting the surface water run-off generated from the site so that it will not exceed the run-off from the undeveloped site and not increase the risk of flooding off-site. Discharge should be restricted to the pre development Greenfield run-off rate. 2. Provision of compensatory flood attenuation to accommodate the 1 in 100 year event plus 30% for climate change. The development shall be carried out in accordance with the approved strategy. REASON: In the interests of achieving a satisfactory drainage
23 An art feature or features shall be incorporated into the development in accordance with a scheme that has first been submitted to and approved in writing by the Local Planning Authority. The approved details shall be implemented in their entirety before the final completion of the final dwelling. REASON: To incorporate art into the development in accordance with LDF Policy DP5.
24 Details of the two play areas to be provided at this site shall be submitted to the Local Planning Authority for approval in writing. The approved details shall be provided in accordance with the agreed phasing plan and thereafter be maintained. REASON: To ensure the provision of play facilities at this site.
25 No trees or hedges shall be lopped topped or removed unless expressly approved in writing by the Local Planning Authority. REASON: In the interest of amenity and ecology.
26 Details of existing, proposed and finished floor levels together with any bunding or other engineering works proposed to be undertaken shall be submitted to the Local Planning Authority for approval in writing prior to the commencement of construction. The approved details shall be implemented in their entirety. REASON: In the interests of visual and residential amenity.
27 Any temporary drainage scheme to be installed/constructed at this site shall have been the subject of the prior approval of the Local Planning Authority. REASON: In the interests of the amenity and ecology.
28 Tree protection measures highlighted in BS5837:2012 shall be adopted and a 2m high fence installed to the outside edge of the drip line of the following groups of trees for the duration of construction:Grove Hill Plantation (South Western corner of site) and the small group of trees within the North Western corner of the site adjacent to Stokesley Road. REASON: To ensure the continued health of these trees.
29 Statement of Co-operative Working: The Local Planning Authority consider that the application as originally submitted required clarification and amendment. Following correspondence the agent a satisfactory scheme has been negotiated. .

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 162 kb 23/09/2013
Consultee Responses
Consultee response - Town Council 15 kb 21/10/2013
Consultee response - Archaeological Advice 140 kb 24/10/2013
Consultee response - Environment Agency 23 kb 31/10/2013
Consultee response - Natural England 145 kb 31/10/2013
Consultee response - Northumbrian Water 93 kb 14/11/2013
Consultee response - National Park 74 kb 19/12/2013
Decision
Section 106 Agreement 1291 kb 12/11/2014
Decision Notice 59 kb 13/11/2014
Location Plan
Location Plan 246 kb 01/10/2013
Plans
House Types 3647 kb 01/10/2013
Master Plan layout - Adoption Diagram SUPERSEDED 9769 kb 01/10/2013
Landscaping Survey SUPERSEDED 12005 kb 01/10/2013
Site Access 305 kb 01/10/2013
Site Plan as Existing 446 kb 01/10/2013
Site Sections 3235 kb 01/10/2013
Street Scene Elevations 8601 kb 01/10/2013
Master Plan Layout - Spatial Syntax SUPERSEDED 10926 kb 01/10/2013
Master Plan Layout - Colour SUPERSEDED 10635 kb 01/10/2013
Master Plan Layout - Boundary Treatments SUPERSEDED 10799 kb 01/10/2013
Master Plan Layout - B & W SUPERSEDED 9943 kb 01/10/2013
Agent Response to comments 19 11 13 8269 kb 19/11/2013
Adoption Diagram Amended 20.11.13 9238 kb 20/11/2013
Boundary Treatment Plan Amended 20.11.13 9830 kb 20/11/2013
Landscape Strategy Plan Amended 20.11.13 7124 kb 20/11/2013
Spatial Syntax Amended 20.11.13 11067 kb 20/11/2013
Street Scenes 8576 kb 20/11/2013
Site Sections 3257 kb 20/11/2013
Masterplan as Proposed SUPERSEDED 9400 kb 20/11/2013
Masterplan as Proposed (Colour) Amended 20.11.13 10454 kb 20/11/2013
Masterplan as Proposed Amended 21.11.13 9378 kb 21/11/2013
Supporting Documentation
Environmental Statement - Technical Appendices 55524 kb 01/10/2013
Environmental Statement - Non-Technical Reports 749 kb 01/10/2013
Environmental Statement - Technical Reports 5897 kb 01/10/2013
Design and Access Statement 34523 kb 01/10/2013
Planning Statement 1221 kb 01/10/2013
Public Utilities Statement 4239 kb 01/10/2013
Transport Assessment 16064 kb 01/10/2013
Summary Statement 2469 kb 01/10/2013
Statement of Community Involvement 2541 kb 01/10/2013
Application Documents
Officer Report 205 kb 19/12/2013
Section 278 Notice 454 kb 13/07/2015
Compliance Decision Notice 2013 0651 Conds 4, 7, 17, 18, 20 169 kb 15/05/2015
Compliance Decision Notice 2013 0651 Conds 3, 5, 6, 7, 11, 12, 15, 16, 19, 21 And 27 198 kb 15/05/2015
Consultee Name Date Letter Sent Consultation Expiry Date
Aboricultural Officer 09/10/2013 -
Asset Management Team Fao Guy Allen 09/10/2013 -
Commercial Investment (Regen) 09/10/2013 -
Councillor G Jeffery (HUTTON) 09/10/2013 -
Councillor P Spencer (HUTTON) 09/10/2013 -
Councillor V Halton (HUTTON) 09/10/2013 -
Director of Children & Families 09/10/2013 -
Economic Development Manager 09/10/2013 -
Engineering Team 09/10/2013 -
Engineering Team (Highways) 09/10/2013 -
Environment Agency 09/10/2013 -
Environmental Protection Team 09/10/2013 -
Guisborough Town Council 09/10/2013 -
Housing Area Services 09/10/2013 -
Jane Parry - test 09/10/2013 -
Natural England 09/10/2013 -
NEAR Ltd (Archaeological Services) 09/10/2013 -
Neighbourhood - Guisborough 09/10/2013 -
North York Moors National Park 09/10/2013 -
Northern Powergrid 09/10/2013 -
Northumbrian Water Ltd 09/10/2013 -
Regeneration (East Cleveland) - Ian Stewart 09/10/2013 -
Sports Development - Health Improvement 09/10/2013 -
Strategic Planning Team (Policy) 09/10/2013 -
Address Date Sent Date Reconsulted Expiry Date
10 DEEPDALE GUISBOROUGH TS14 - - -
59 HUTTON LANE GUISBOROUGH TS14 AW - - -
- - - -
10 Tedworth Close Guisborough North Yorkshire TS14 7PR - - -
- - - -
60 GREAT AUK GUISBOROUGH TS14 8PQ - - -
- - - -
60 GREAT AUK GALLEY HILL GUISBOROUGH TS14 8PQ - - -
- - - -
- - - -
27 Mossdale grove - - -
11 Deepdale Guisborough TS14 8JY - - -
3 LITTLE GREBE GALLEY HILL GUISBOROUGH TS14 8PA - - -
85 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
89 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
15 Ryedale Guisborough TS14 8JE - - -
2 ROWAN AVENUE GUISBOROUGH TS14 8DR - - -
102 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
- - - -
- - - -
4 WEARDALE PINE HILLS GUISBOROUGH TS14 8JL - - -
- - - -
19 ROSEDALE CRESCENT GUISBOROUGH TS14 8HZ - - -
97 FARNDALE DRIVE GUISBOROUGH - - -
15 glendale pinehills guisborough ts148jf - - -
107 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
107 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
- - - -
5 Swallow close Guisborough North Yorkshire TS14 8HL - - -
97 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
115 Farndale Drive Guisborough TS14 8JX - - -
118 Farndale Dr TS14 8JX - - -
7 BRANSDALE GUISBOROUGH TS14 8JR - - -
7 BRANSDALE GUISBOROUGH TS14 8JR - - -
- - - -
16 WHINCHAT TAIL GUISBOROUGH TS14 8PW - - -
27 EVENDALE PINEHILLS GUISBOROUGH TS14 8JW - - -
105 FARNDALE DRIVE GUISBOROUGH - - -
14 BRANSDALE GUISBOROUGH TS14 8JR - - -
24 Farndale Drive Guisborough TS148JA - - -
103 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
23 Askewdale Guisborough Cleveland TS14 8JG - - -
- - - -
8 BRANSDALE GUISBOROUGH TS14 8JR - - -
7 Bernaldby Avenue Guisborough TS14 8DB - - -
89 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
71 farndale drive Guisborough TS14 8JJ - - -
Askewdale Guisborough - - -
25 Staindale Guisborough TS14 8JU - - -
17 BRANSDALE GUISBOROUGH TS14 8JR - - -
3 Rufftail Guisborough - - -
91 FARNDALE DRIVE GUISBOROUGH - - -
24 CAMPION DRIVE GUISBOROUGH TS14 8EU - - -
27 Mossdale grove Pine hills - - -
20 askewdale Guisborough - - -
4 Askewdale Guisborough TS14 8JG - - -
25 Staindale Guisborough TS14 8JU - - -
5 Swallow close Guisborough North Yorkshire TS14 8HL - - -
134 Enfield Chase Guisborough Cleveland TS14 7LQ - - -
- - - -
88 Farndale Drive Guisborough TS14 8JX - - -
68 ACKLINGTON ROAD MORPETH NORTHUMBERLAND NE65 0NG - - -
101 Farndale Drive Guisborough - - -
- - - -
19 Askewdale - - -
3 Rufftail Guisborough TS14 8PN - - -
- - - -
15 tindale pine hills guisborough ts14 8jh - - -
7Spring Lodge Gardens TS14 8DE - - -
First Floor, 4 Bransdale Guisborough TS14 8JR - - -
- - - -
25 Staindale Guisborough TS14 8JU - - -
- - - -
5 Trefoil Close Guisborough TS14 8DT - - -
5 Swallow Close Guisborough North Yorkshire TS14 8HL - - -
3 Staindale Guisborough TS14 8JU - - -
18 LARK DRIVE GUISBOROUGH TS14 8HP - - -
20 Staindale Guisborough TS14 8JU - - -
- - - -
- - - -
37 Meath Way Guisborough TS14 7PG - - -
- - - -
10 MOSSDALE GUISBOROUGH TS14 8JB - - -
11 Deepdale Guisborough TS14 8JY - - -
10 FARNDALE DRIVE GUISBOROUGH TS14 8JA - - -
114 Farndale Drive - - -
- - - -
- - - -
5 Swallow close Guisborough North Yorkshire TS14 8HL - - -
Tudor Croft Stokesley Road Guisborough TS14 8DL - - -
11 OSPREY CLOSE GUISBOROUGH TS14 8HN - - -
17 FARNDALE DRIVE GUISBOROUGH TS14 8JD - - -
5 EVENDALE GUISBOROUGH TS14 8JW - - -
101 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
100 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
14 CAMPION DRIVE GUISBOROUGH TS14 8EU - - -
FRAMARTUR 6 WEARDALE GUISBOROUGH TS14 8JL - - -
15 Evendale Guisborough Cleveland TS148JW - - -
11 Weardale Guisborough TS14 8JL - - -
23 Evendale Pine Hills Guisborough TS14 8JW - - -
5 NEWTONDALE GUISBOROUGH TS14 8EY - - -
113 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
12 BRACKEN CRESCENT GUISBOROUGH TS14 8DU - - -
10 Tindale Pinehills Guisborough TS14 8JH - - -
19 Deepdale Guisborough TS14 8JY - - -
29 ASKEWDALE GUISBOROUGH TS14 8JG - - -
107 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
107 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
7 BERNALDBY AVENUE GUISBOROUGH TS14 8DB - - -
24 KINGFISHER DRIVE GUISBOROUGH TS14 8HS - - -
8 CAMPION DRIVE GUISBOROUGH TS14 8DY - - -
19 SORRELL GROVE GUISBOROUGH TS14 8DP - - -
2 Tindale Guisborough TS14 8JH - - -
14 CAMPION DRIVE GUISBOROUGH TS14 8EU - - -
115 Farndale Drive Guisborough TS14 8JX - - -
47 FALCON WAY GUISBOROUGH TS14 8HT - - -
113 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
98 FARNDALE DRIVE GUISBOROUGH TS14 8JX - - -
13 RYEDLE GUISBOROUGH TS14 8JE - - -
31 STAINDALE GUISBOROUGH TS14 8JU - - -
81 Farndale Drive Guisborough TS14 8JX - - -
24 Farndale Drive Guisborough Cleveland TS14 8JA - - -
27 Askewdale Guisborough TS14 8JG - - -
57 Montagus Harrier Guisborough TS14 8PB - - -
5 Lucerne Drive, Hutton Meadows, Guisborough. TS14 8DZ - - -
115 Farndale Drive Guisborough TS148JX - - -
123 Aldenham Road - - -
9 LYNDALE GUISBOROUGH TS14 8JN - - -
7 BRANSDALE GUISBOROUGH TS14 8JR - - -
7 BRANSDALE GUISBOROUGH TS14 8JR - - -
83 Farndale Drive TS148JX - - -
29 Deepdale Guisborough TS14 8JY - - -
11 LITTLE CRAKE GUISBOROUGH TS14 8PL - - -
6 ASKEWDALE GUISBOROUGH - - -
- - - -
9, Langdale Guisborough Cleveland. - - -
6 overdale Guisborough - - -
10 FARNDALE DRIVE GUISBOROUGH TS14 8JA - - -
21 Taunton Vale Hunters Hill Guisborough Cleveland TS14 7NB - - -
25 SHALLOW CLOSE GUISBOROUGH TS14 8HL - - -
6 WYKEHAM AVENUE GUISBOROUGH TS14 8LE - - -
25 Staindale Guisborough TS14 8JU - - -
10 DEEPDALE GUISBOROUGH TS14 - - -
14 Sorrel Grove - - -
- - - -
28 SORRELL GROVE GUISBOROUGH - - -
- - - -
49 Deepdale Guisborough TS14 8JY - - -
21 Uppergarth gardens, Guisborough. Ts146ha. - - -
73 Farndale Drive Guisborough TS14 8JJ - - -
- - - -
1 Kirkdale Guisborough Cleveland TS148EX - - -
36 Haymore Street Middlesbrough TS56JD - - -
6 BRANSDALE GUISBOROUGH TS14 8JR 09/10/2013 - 30/10/2013
7 BRANSDALE GUISBOROUGH TS14 8JR 09/10/2013 - 30/10/2013
8 BRANSDALE GUISBOROUGH TS14 8JR 09/10/2013 - 30/10/2013
9 BRANSDALE GUISBOROUGH TS14 8JR 09/10/2013 - 30/10/2013
81 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
83 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
85 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
87 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
89 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
91 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
93 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
95 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
97 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
99 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
103 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
105 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
107 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
109 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
111 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
113 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
115 FARNDALE DRIVE GUISBOROUGH TS14 8JX 09/10/2013 - 30/10/2013
3 BRANSDALE GUISBOROUGH TS14 8JR 09/10/2013 - 30/10/2013
21 SWALLOW CLOSE GUISBOROUGH TS14 8HL 09/10/2013 - 30/10/2013
23 SWALLOW CLOSE GUISBOROUGH TS14 8HL 09/10/2013 - 30/10/2013
25 SWALLOW CLOSE GUISBOROUGH TS14 8HL 09/10/2013 - 30/10/2013
UPPER FLAT 4 BRANSDALE GUISBOROUGH TS14 8JR 09/10/2013 - 30/10/2013
LOWER FLAT 4 BRANSDALE GUISBOROUGH TS14 8JR 09/10/2013 - 30/10/2013
4 BRANSDALE GUISBOROUGH TS14 8JR 09/10/2013 - 30/10/2013
14 SWALLOW CLOSE GUISBOROUGH TS14 8HL 09/10/2013 - 30/10/2013
16 SWALLOW CLOSE GUISBOROUGH TS14 8HL 09/10/2013 - 30/10/2013
18 SWALLOW CLOSE GUISBOROUGH TS14 8HL 09/10/2013 - 30/10/2013
LOWCROSS FARM GUISBOROUGH TS14 8HB 09/10/2013 - 30/10/2013
TERRY WEALANDS RECYCLING LOWCROSS FARM GUISBOROUGH TS14 8HB 09/10/2013 - 30/10/2013
LOWCROSS LIVERIES LOWCROSS FARM GUISBOROUGH TS14 8HB 09/10/2013 - 30/10/2013
18 STAINDALE GUISBOROUGH TS14 8JU - - -
9, The Zetland, Saltburn-by-the-Sea Cleveland TS12 1BU - - -
Site or Press Description Display Date Expiry Date
P DEPARTURE 11/10/2013 01/11/2013
S DEPARTURE 16/10/2013 06/11/2013