R/2011/0898/FF

Planning Application Details - Official Consultation has expired.

Location
SSI TEESSIDE REDCAR BLAST FURNACE SITE REDCAR
Proposal
ERECTION OF A PULVERISED COAL INJECTION PLANT WITH ANCILLARY WORKS
Application Type
Full
Status
Approved
Parish(es)
Applicant
SAHAVIRIYA STEEL INDUSTRIES UK LIMITED
Applicant's Address
STEEL HOUSE REDCAR CLEVELAND TS10 5QW
Agent
JACOBS
Agent's Address
1 CITY WALK LEEDS WEST YORKSHIRE LS11 9DX
Agent's work phone
Agent's email
Case Officer
Mr D Pedlow
Case Officer Telephone
01287 612546
Case Officer Email
David.Pedlow@redcar-cleveland.gov.uk
Consultation Start
27/01/2012
Weekly List Expiry Date
23/02/2012
Date Received
07/12/2011
Date Valid
20/01/2012
Expiry
16/03/2012
Consultation Expiry
22/02/2012
associated_bldreg
R/2012/0513/BR
Decision
APPROVED
Decision Date
27/04/2012
Decision Level
Delegated

Conditions table
# Condition Details
1 The development shall not be begun later than the expiration of THREE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2 The development hereby permitted shall be carried out in accordance with the following approved plans: (Drwg No C.G2M0-RB-1200-M-LAY002, Drwg No C.G2M0-RB-1200-M-LAY003, Drwg No C.G2M0-RB-1200-M-LAY004, C.G2M0.RB.120214-M/LAY001 REV1, P.G2M0.RB.71123-Z/BLP001, P.G2M0.RB.5105-Z/FPB003, P.G2M0.RB.5105-Z/FPB001) received by the Local Planning Authority on (07/12/11) REASON: To accord with the terms of the planning application.
3 The development hereby permitted shall be carried out in accordance with the details included within the Environmental Report December 2011 as received by the Local Planning Authority on 07/12/11. REASON: To accord with the terms of the planning application.
4 Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken and where remediation is necessary a remediation scheme must be prepared subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority. REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
5 The mitigation measures set out within section 9.8 of the Environmental Report (December 2011) shall be implemented in full during the construction phase of development. REASON: To ensure the proposed development does not result in adverse ecological conditions.
6 No on site vegetation clearance should take place between 1st March and 31st August unless a qualified ecologist undertakes a checking survey immediately prior to clearance and confirms that no active nests are present. REASON: To ensure breeding birds are not disturbed
7 REASON FOR DECISION: The site is within an area identified for industrial/warehousing purposes. The design and siting of the development takes account of the principles set out in the Council’s supplementary planning guidance. The proposal therefore accords with the Council’s adopted Development Plan.
8 NOTE: The following development plan policies were relevant to this decision:- Local Development Framework Policy CS10, CS20, DP1, DP2, DP3, DP6 and DP7.
9 Informative Note: The applicant is reminded that it is the responsibility of anybody carrying out building work to ensure mud, debris or deleterious material is not deposited from the site onto the public highway and, if it is, it shall be cleared by that person.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form 242 kb 07/12/2011
Location Plan
Location Plan 825 kb 07/12/2011
Plans
General Arrangement 1049 kb 07/12/2011
Site Layout Plan 529 kb 07/12/2011
Site Plan 196 kb 07/12/2011
Elevations 569 kb 07/12/2011
Waste Gas Main General Arrangement 140 kb 07/12/2011
Elevations 315 kb 07/12/2011
Floor Layout 106 kb 07/12/2011
Sections 107 kb 07/12/2011
Sections 101 kb 07/12/2011
Supporting Documentation
Planning and Design and Access Statements 1586 kb 07/12/2011
Technical Report 6265 kb 01/02/2012
Enviromental Report 31022 kb 01/02/2012
Application Documents
Officer Report 73 kb 26/04/2012
Decision Notice 41 kb 27/04/2012
Consultee Name Date Letter Sent Consultation Expiry Date
Councillor E Howden 01/02/2012 -
Councillor R Goddard (DORMANSTOWN) 01/02/2012 -
Councillor S Thompson 01/02/2012 -
Engineering Team (Highways) 01/02/2012 -
Environment Agency 01/02/2012 -
Environmental Protection Team 01/02/2012 -
Health & Safety-Food 01/02/2012 -
Health & Safety-Food (Food Team) 01/02/2012 -
Natural England 01/02/2012 -
Regeneration (Redcar) 01/02/2012 -
RSPB 01/02/2012 -
Address Date Sent Date Reconsulted Expiry Date
COATHAM BAY HOLIDAY CAMP MAJUBA ROAD REDCAR TS10 5BJ 01/02/2012 - 22/02/2012
CLEVELAND GOLF CLUB MAJUBA ROAD REDCAR TS10 5BJ 01/02/2012 - 22/02/2012
MARSH FARM HOUSE TOD POINT ROAD WARRENBY REDCAR TS10 5BE 01/02/2012 - 22/02/2012
C H BRIGGS PLANT LTD TOD POINT ROAD WARRENBY REDCAR TS10 5BE 01/02/2012 - 22/02/2012
Site or Press Description Display Date Expiry Date
B ARTICLE 15 27/01/2012 17/02/2012