Location
SOTHERBY ROAD, SOUTH BANK, TS6 6LR
Proposal
ERECTION OF PORTAL FRAME BUILDING (38.50M x 16.65M) FOR USE FOR INDUSTRIAL AND STORAGE / DISTRIBUTION (CLASSES B2 & B8) PURPOSES AND ADDITIONAL 21 PARKING SPACES
Application Type
Full
Status
Approved
Parish(es)
Eston
Applicant
LDG COMMERCIAL PROPERTIES
Applicant's Address
BURNSIDE
DALTON PIERCY
HARTLEPOOL
TS27 3HS
Agent
CAB CIVIL ENGINEERING LTD
Agent's Address
32 MILBANK CLOSE
HART VILLAGE
HARTLEPOOL
TS27 3BT
Agent's work phone
Agent's email
Case Officer
Mrs C Griffiths
Case Officer Telephone
01287 612629
Case Officer Email
claire.griffiths@redcar-cleveland.gov.uk
Consultation Start
06/12/2010
Weekly List Expiry Date
-
Date Received
24/11/2010
Date Valid
24/11/2010
Expiry
19/01/2011
Consultation Expiry
03/02/2011
associated_bldreg
-
Decision
APPROVED
Decision Date
13/01/2011
Decision Level
Delegated
| # | Condition Details |
|---|---|
| 1 | (1) The development shall not be begun later than the expiration of THREE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990. |
| 2 | (2) The development hereby permitted shall be carried out in accordance with the following approved plans: Dwg. No. 2010-LDG-01-D002Rev1, Dwg. No. 2010-LDG-01-D003Rev2 and Dwg. No. 2010-LDG-01-D001Rev1. REASON: For the avoidance of doubt. |
| 3 | (3) Unless otherwise agreed by the Local Planning Authority in writing, development other than that required to be carried out as part of an approved scheme of remediation must not commence until parts (a) to (e) have been complied with. If unexpected contamination is found after development has begun, development must be halted on that part of the site affected by the unexpected contamination to the extent specified by the Local Planning Authority in writing until condition (e) has been complied with in relation to that contamination. (a) Site Characterisation An investigation and risk assessment, in addition to any assessment provided with the planning application, must be completed in accordance with a scheme to assess the nature and extent of any contamination on the site, whether or not it originates on the site. The contents of the scheme are subject to the approval in writing of the Local Planning Authority. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The written report is subject to the approval in writing of the Local Planning Authority. The report of the findings must include: (i) a survey of the extent, scale and nature of contamination; (ii) an assessment of the potential risks to: • human health, • property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes, • adjoining land, • groundwaters and surface waters, • ecological systems, • archeological sites and ancient monuments; (iii) an appraisal of remedial options, and proposal of the preferred option(s). This must be conducted in accordance with DEFRA and the Environment Agency’s ‘Model Procedures for the Management of Land Contamination, CLR 11’. (b) Submission of Remediation Scheme A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. (c) Implementation of Approved Remediation Scheme The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report (referred to in PPS23 as a validation report) that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval in writing of the Local Planning Authority. (d) Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken in accordance with the requirements of part (a) and where remediation is necessary a remediation scheme must be prepared in accordance with the requirements of part (b), which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority. (e) Long Term Monitoring and Maintenance A monitoring and maintenance scheme to include monitoring the long-term effectiveness of the proposed remediation over a period of 5 years, and the provision of reports on the same must be prepared, both of which are subject to the approval in writing of the Local Planning Authority. Following completion of the measures identified in that scheme and when the remediation objectives have been achieved, reports that demonstrate the effectiveness of the monitoring and maintenance carried out must be produced, and submitted to the Local Planning Authority. This must be conducted in accordance with DEFRA and the Environment Agency’s ‘Model Procedures for the Management of Land Contamination, CLR 11’ REASON: To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 4 | The site is within an area identified for industrial/warehousing purposes. The design and siting of the development takes account of the principles set out in the Council’s policies and guidance. The proposal therefore accords with the Council’s adopted Development Plan. |
| 5 | NOTE: The following development plan policies were relevant to this decision:- Local Development Framework Policy CS4, CS9, CS20, DP2, DP3, DP6 and DP7. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Documents | |||
| Location Plan.pdf | 490 kb | 23/11/2010 | |
| Design and Access Statement.pdf | 1809 kb | 23/11/2010 | |
| Application Form.pdf | 240 kb | 23/11/2010 | |
| Development Images.pdf | 1216 kb | 23/11/2010 | |
| Proposed Plans and Elevations.pdf | 277 kb | 06/12/2010 | |
| Topographical Survey.pdf | 106 kb | 06/12/2010 | |
| Proposed Site Layout.pdf | 104 kb | 06/12/2010 | |
| Decision Notice | 34 kb | 13/01/2011 | |
| Address | Date Sent | Date Reconsulted | Expiry Date |
|---|---|---|---|
| M B DISTRIBUTION SKIPPERS LANE NORMANBY TS6 6UB | 06/12/2010 | - | 03/01/2011 |
| BALFOUR BEATTY POWER NETWORKS LTD SOTHERBY ROAD SOUTH BANK TS6 6LP | 06/12/2010 | - | 03/01/2011 |
| EYRE & ELLISTON WALLIS ROAD SOUTH BANK TS6 6JB | 06/12/2010 | - | 03/01/2011 |
| SYNTEX SERVICES LTD SKIPPERS LANE SOUTH BANK TS6 6UB | 06/12/2010 | - | 03/01/2011 |
| WALLIS ROAD SOUTH BANK TS6 6JB | 06/12/2010 | - | 03/01/2011 |
| CHIEFTAIN GROUP PLC SOTHERBY ROAD SOUTH BANK TS6 6LP | 06/12/2010 | - | 03/01/2011 |
| CAMPBELL MACHINE CO LTD SKIPPERS LANE SOUTH BANK TS6 6HA | 06/12/2010 | - | 03/01/2011 |
| Site or Press | Description | Display Date | Expiry Date |
|---|---|---|---|
| S | SITE NOTICE ONLY | 09/12/2010 | 30/12/2010 |