R/2010/0816/FF/CD1

Planning Application Details - Official Consultation has expired.

Location
SITE 3, TOD POINT ROAD INDUSTRIAL ESTATE, WARRENBY, REDCAR, TS10 5AU
Proposal
CONDITION DISCHARGE 5D ELECTRICITY SUBSTATION AND CONTROL ROOM ASSOCIATED WITH OFFSHORE WIND FARM (AMENDED SCHEME)
Application Type
Condition Discharge
Status
Decision
Parish(es)
Applicant
-
Applicant's Address
-
Agent
-
Agent's Address
-
Agent's work phone
Agent's email
Case Officer
Mrs L Hall
Case Officer Telephone
01287 612343
Case Officer Email
Lyndsey.Hall@redcar-cleveland.gov.uk
Consultation Start
-
Weekly List Expiry Date
-
Date Received
24/11/2011
Date Valid
24/11/2011
Expiry
19/01/2012
Consultation Expiry
-
associated_bldreg
-
Decision
-
Decision Date
05/02/2015
Decision Level
Delegated

Conditions table
# Condition Details
1 (1) The development shall not be begun later than the expiration of THREE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2 (2) The development hereby permitted shall be carried out in accordance with the following approved plans: JAB/101602/802 25.10.2010 JAB/101602/801 25.10.2010 REASON: For the avoidance of doubt.
3 (3) Details of materials to be used for all vehicle surfaces shall be submitted to, and approved in writing by the Local Planning Authority, prior to the commencement of the development and the development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials.
4 (4) Any installations of plant, machinery, or extract ventilations (including any fans), should be checked for potential levels of noise emanating form the premises before the development commences. Any noise emitted from new units should not contribute any more than 3dBA to existing background noise levels, when measured at a distance of 1 meter from the façade of any adjacent dwelling and when calculated as a Leq(A) of 10 minutes. REASON: In the interest of the amenities of the area
5 (5) Unless otherwise agreed by the Local Planning Authority in writing, development other than that required to be carried out as part of an approved scheme of remediation must not commence until parts (a) to (d) have been complied with. (a) Site Characterisation An investigation and risk assessment, in addition to any assessment provided with the planning application, must be completed in accordance with a scheme to assess the nature and extent of any contamination on the site, whether or not it originates on the site. The contents of the scheme are subject to the approval in writing of the Local Planning Authority. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The written report is subject to the approval in writing of the Local Planning Authority. The report of the findings must include: (i) a survey of the extent, scale and nature of contamination; (ii) an assessment of the potential risks to: • human health, • property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes, • adjoining land, • groundwaters and surface waters, • ecological systems, • archeological sites and ancient monuments; (iii) an appraisal of remedial options, and proposal of the preferred option(s). This must be conducted in accordance with DEFRA and the Environment Agency’s ‘Model Procedures for the Management of Land Contamination, CLR 11’. (b) Submission of Remediation Scheme A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. (c) Implementation of Approved Remediation Scheme The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report (referred to in PPS23 as a validation report) that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval in writing of the Local Planning Authority. (d) Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken in accordance with the requirements of part (a) and where remediation is necessary a remediation scheme must be prepared in accordance with the requirements of part (b), which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority. REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
6 INFORMATIVE NOTE: At no point should the adopted highway be blocked up with out the prior consent of the Councils Highways Maintenance section.
7 INFORMATIVE NOTE: The applicant is reminded that it is the responsibility of anybody carrying out building work to ensure mud, debris or deleterious material is not deposited from the site onto the public highway and, if it is, it shall be cleared by that person.
8 NOTE: The following development plan policies were relevant to this decision:- Local Development Framework Policy CS20, DP2, DP3, CS21, CS22, CS24, DP1.
9 REASON FOR DECISION: It is considered that the proposed development will not cause significant harm to the amenities of local residents or adversely affect the character and appearance of the area. The application does not raise any issues in respect of crime prevention or highway safety. The proposal accords with the Council's adopted Development Plan and Supplementary Planning Guidance.