R/2009/0766/FFM

Planning Application Details - Official Consultation has expired.

Location
WESTFIELD ESTATE, LOFTUS, TS134XB
Proposal
DEMOLITION OF EXISTING DWELLINGS AND ERECTION OF 123 NO. MIXED RESIDENTIAL DEVELOPMENT INCLUDING RELOCATION OF SUBSTATION
Application Type
Major Application
Status
Approved
Parish(es)
Loftus CP
Applicant
COAST AND COUNTRY HOUSING ASSOCIATION
Applicant's Address
REDCAR HOUSING OFFICE 14 ENNIS SQUARE REDCAR TS10 5JR
Agent
ID PARTNERSHIP NORTHERN
Agent's Address
FAO MR K DILLON ST JUDES BARKER STREET NEWCASTLE UPON TYNE NE21AS
Agent's work phone
Agent's email
Case Officer
Miss J Horne
Case Officer Telephone
Case Officer Email
Janet.Horne@redcar-cleveland.gov.uk
Consultation Start
23/11/2009
Weekly List Expiry Date
-
Date Received
13/11/2009
Date Valid
18/11/2009
Expiry
17/02/2010
Consultation Expiry
29/03/2010
associated_bldreg
-
Decision
APPROVED
Decision Date
08/03/2010
Decision Level
Delegated

Conditions table
# Condition Details
1 (1) The development shall not be begun later than the expiration of THREE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2 INFORMATIVE: The Highway Authority advise that they would not permit commencement on site without either a Section 219/220 Notice (1) or a Section 38 Agreement (Highways Act 1980) being in place.
3 (2) The development hereby approved shall be built in accordance with the plan(s) Plan No. s HT20_01; HT20_02; HT21_01; HT20_02; HT22_01; HT22_02; Ht22_03; HT30_01; HT30_02; HT31_01; HT31_02; HT32_01; HT32_02; HT33_01; HT33_02; HT33_03; HT34_01; HT34_02; HT34_03; HT35_01;HT35_02; HT40_01; HT40_02; HT41_01; HT41_02;SL_001 Rev M and SL_002 unless first agreed in writing with the Local Planning Authority. REASON: For the avoidance of doubt.
4 (3) Any contamination not considered in the Reclamation Method Statement but identified during the reclamation works should be subject to further risk assessment and remediation proposals first agreed with the Local Planning Authority. A report demonstrating that the works were carried out in accordance with the approved scheme (the 'Validation Report') should be submitted to the Local Planning Authority within 2 months of completion of the development. REASON: The site may be contaminated as a result of past or current uses and/or is within 250 metres of a site which has been landfilled and the Local Planning Authority wishes to ensure that the proposed development can be implemented and occupied with adequate regard to environmental and public protection.
5 (4) A minimum of 10% of the sites energy requirements shall be provided by embedded renewable energy, unless otherwise first agreed in writing with the Local Planning Authority. REASON: In the interests of sustainability.
6 (5) Details of the external materials to be used in the carrying out of this permission (including samples) shall be submitted to, and approved in writing by the Local Planning Authority, prior to the commencement of development and the development shall not be carried out except in accordance with the approved details. REASON: To ensure the use of satisfactory materials.
7 (6) None of the proposed new dwellings shall be occupied until the access and car parking to it has been provided. REASON: In the interests of highway safety.
8 (7) For the proposed new dwellings a cycle store shall be provided prior to first occupation of those dwellings where garage facilities are not proposed in a position and in accordance with details that have first been submitted to the Local Planning Authority and approved in writing. The approved scheme shall be implemented in its entirety. REASON: To provide alternative storage facilities.
9 (8) Notwithstanding the details submitted details of materials to be used for all hard surfaces shall be submitted to and agreed in writing by the Local Planning Authority prior to the commencement of any of the highways development. REASON: To reserve the rights of the Local Planning Authority with regard to these matters.
10 (9) Notwithstanding the submitted landscaping scheme a revised landscaping scheme shall be submitted to, and approved in writing by, the Local Planning Authority prior to the occupation of any of the dwellings hereby approved. The details shall include size, type and species of plant and indicate the proposed layout and surfacing of all open areas together with the final treatments to the retaining walls. A programme of work should also be submitted and implemented in accordance with the approved details. REASON: To reserve the rights of the Local Planning Authority with regard to these matters.
11 (10) All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in the first planting and seeding season following the occupation of the buildings or the completion of the development, whichever is sooner, and any trees or plants which within a period of five years from the completion of the development die, are removed, or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species unless the Local Planning Authority gives written consent to any variation. REASON: To ensure the satisfactory implementation of the approved scheme in the interests of the visual amenities of the locality.
12 (11) No material shall be removed from the existing buildings on the site and none of them shall be demolished until:- (a) Surveys have been undertaken to determine the presence of bats and these have been completed in respect of the existing buildings; (b) A scheme of mitigation measures in respect of any species identified has been submitted to, and approved by, the Local Planning Authority; and (c) Any Licences required to be obtained from Natural England under the Habitats Directive in respect of European Protected Species have been obtained. Thereafter the approved mitigation measures must be implemented as part of the development. REASON: To ensure the protection of any Protected Species that may be at this site.
13 (12) No trees on or overhanging the site other than those identified on the approved plans to be removed shall be lopped, topped, pruned or felled without the prior written consent of the Local Planning Authority. REASON: In the interests of the visual amenities of the locality.
14 (13) Prior to the commencement of the development in the vicinity of any of the trees, details of the methods to be used to protect the existing trees and hedgerows on the site from construction work shall be submitted to the Local Planning Authority for approval in writing. The approved details shall be implemented in their entirety unless otherwise agreed in writing. REASON: To ensure the continued health and presence of the trees and hedgerows at this site.
15 (14) No construction works approved by this permission shall be commenced until a scheme for the provision and implementation of a surface water drainage and regulation system (including a Surface Water Management Plan) has been submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented prior to the construction of any impermeable surfaces draining to the system unless otherwise agreed in writing with the Local Planning Authority. REASON: To ensure satisfactory drainage at this site.
16 (15) Prior to the commencement of any development relating to boundary walls/fences and retaining walls details of those new boundary walls/fences and retaining walls shall have been submitted to the Local Planning Authority for approval. The approved details shall include type of materials and be implemented prior to the occupation or reoccupation of any of the dwellings at this site. REASON: In the interests of visual and residential amenity.
17 (16) Prior to the occupation of the 63rd new dwelling the children’s play area shall be available for use in accordance with a scheme that has first been submitted to and approved in writing by the Local Planning Authority. REASON: To ensure adequate play facilities are available at this site.
18 (17) Prior to the completion of the last dwelling at this site an art feature shall have been installed at the site in accordance with the details that have first been submitted to and approved by the Local Planning Authority. REASON: To ensure the provision of the art feature.
19 (18) Prior to the commencement of development details of a contractor’s compound shall be submitted for approval in writing by the Local Planning Authority. The approved details shall be fully implemented prior to commencement of works and remain until completion of construction/building works at this site. REASON: In the interests of highway safety.
20 (19) Prior to the commencement of development details of a scheme to prevent the deposit of mud/debris onto the highway shall have been submitted to the Local Planning Authority for approval in writing. The approved details shall be fully implemented prior to the commencement of works and be retained for the period of construction/building works. REASON: In the interests of highway safety.
21 (20) Prior to the commencement of works details of a traffic management plan shall be submitted to the Local Planning Authority for approval in writing. The approved scheme shall be implemented fully prior to the commencement of the works and shall be retained for the duration of construction/building works. REASON: In the interests of highway safety.
22 (21) At no time during the construction/building works shall the adopted highway be blocked or obstructed without first obtaining the agreement of the Local Planning Authority. REASON: In the interests of highway safety.
23 (22) ‘One- way’ glass shall be installed within the first floor front elevations of the dwellings proposed on Plots 34, 35, 92, 93, 100 and101 in accordance with a scheme that has first been submitted to and approved in writing with the Local Planning Authority. The approved scheme shall be implemented in its entirety unless otherwise first agreed in writing with the Local Planning Authority. REASON: In the interests of residential amenity.
24 (23) Prior to the commencement of construction of any of the dwellings hereby approved full details of existing and proposed ground levels together with finished floor levels for each of the buildings shall have first been submitted to the Local Planning Authority for approval in writing. The approved details shall; be implemented in their entirety unless otherwise first agreed in writing with the Local Planning Authority. REASON: To ensure a satisfactory form of development.
25 (24) Prior to the commencement of any highway works a plan shall be submitted to the Local Planning Authority for approval in writing that shows the corrected forward visibility splay for the junction in the vicinity of parking spaces 46-49 (inclusive). The approved junction shall be implemented in its entirety. REASON: In the interests of highway safety.
26 (25) The proposed highway infrastructure for the development shall be the subject of a Stage 2 Road Safety Audit. The Audit shall be carried out in accordance with DMRB HD19/03 and shall be submitted to the Local Planning Authority for approval in writing prior to the commencement of any highway infrastructure works. REASON: In the interests of highway safety.
27 (26) The proposed highway infrastructure for the development shall be the subject of a Stage 3 Road Safety Audit. The Audit shall be carried out in accordance with DMRB HD19/03 and shall be submitted to the Local Planning Authority for approval in writing prior to the commencement of any highway infrastructure works. REASON: In the interests of highway safety.
28 (27) Stage 4 (Monitoring) road Safety Audits shall be carried out using 12 month and 36 months of accident data from the tie the infrastructure (as set out in conditions 26 and 27 above) become operational. The audits shall be carried out in accordance with DMRB HD19/3 and shall be submitted to the Local Planning Authority for approval in writing. REASON: In the interests of highway safety.
29 (28) Prior to the commencement of development for plots 1 to 45 full engineering details of the retaining structure proposed adjacent to North Road/Hummersea Lane shall be submitted to the Local Planning Authority for approval in writing. The approved details shall be implemented in their entirety. REASON: In the interests of highway safety.
30 INFORMATIVE: The Highway Authority advise that before any works are commenced a joint condition survey with the developer, their contractor and the Highway Authority shall be undertaken of Westfield Terrace, Westfield Way and North Road/Hummersea Lane.
31 INFORMATIVE: The Highway Authority advise that the developer should contact the Council’s naming and Numbering Officer, Sandra Beaty on 01287 612538 to make arrangements for the correct postal address for the development prior to the commencement of any works.
32 INFORMATIVE: The Highway Authority advise that the carriageway and footways shall be designed and constructed, drained and lit to a standard suitable for adoption in accordance with the Redcar and Cleveland design Guide and Specification.
33 REASON FOR DECISION: The proposal due to its scale and location would, bearing in mind the current form of development, be unlikely to create conditions that would be detrimental to the character or appearance of the area, biodiversity, local residential amenity, highway safety or crime prevention. The proposal therefore accords with the aims of Policies: CS6, CS13, CS15, CS17, CS20, CS24, DP2, DP3, DP5, DP7 and DP13 of the Redcar and Cleveland Local Development Framework.
34 NOTE: The following development plan policies were relevant to this decision:- Local Development Framework Policy CS6, CS13, CS15, CS17, CS20, CS24, DP2, DP3, DP5, DP7 and DP13.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Decision
Compliance Discharge Notice Cond 15 - kb 19/05/2025
Decision notice - kb 08/03/2010
Compliance Discharge Notice Cond 25 - kb 19/05/2025
Compliance Discharge Notice Cond 5 - kb 19/05/2025
Compliance Discharge Notice Cond 11 And 13 - kb 19/05/2025
Compliance Discharge Notice Cond 14 - kb 19/05/2025
Compliance Discharge Notice Cond 18, 19 And 20 - kb 19/05/2025
Application Documents
Solar Information.pdf - kb 30/10/2009
P S - Front Page.doc - kb 11/11/2009
PS - Contents.doc - kb 12/11/2009
Planning Statement - Final.doc - kb 12/11/2009
Landscape Design Statement.pdf - kb 12/11/2009
Swept Paths Analysis and Visibility Splays SUPERCEDED.pdf - kb 12/11/2009
Flood Risk Assessment.pdf - kb 12/11/2009
Garden Sheds Information.pdf - kb 13/11/2009
Existing Site Plan.pdf - kb 13/11/2009
Extended Phase 1 Habitat Survey.pdf - kb 13/11/2009
Design and Access Statement OLD.pdf - kb 13/11/2009
House Type 20 Elevations.pdf - kb 13/11/2009
Ground Contamination Report.pdf - kb 13/11/2009
House Type 21 Floor Plan.pdf - kb 13/11/2009
House Type 21 Elevations.pdf - kb 13/11/2009
House Type 20 Floor Plan.pdf - kb 13/11/2009
House Type 34 Ground and First Floor Plan.pdf - kb 13/11/2009
House Type 34 Elevations.pdf - kb 13/11/2009
House Type 35 Elevations.pdf - kb 13/11/2009
House Type 34 Second Floor Plan .pdf - kb 13/11/2009
House Type 33 Ground and First Floor Plan.pdf - kb 13/11/2009
House Type 33 Elevations.pdf - kb 13/11/2009
House Type 32 Floor Plan.pdf - kb 13/11/2009
House Type 32 Elevations.pdf - kb 13/11/2009
House Type 30 Floor Plan.pdf - kb 13/11/2009
House Type 31 Elevations.pdf - kb 13/11/2009
House Type 31 Floor Plan.pdf - kb 13/11/2009
House Type 22 First Floor Plan.pdf - kb 13/11/2009
House Type 30 Elevations.pdf - kb 13/11/2009
House Type 22 Ground Floor Plan.pdf - kb 13/11/2009
House Type 22 Elevations.pdf - kb 13/11/2009
Boundary Treatment Details of Fences and Walls.pdf - kb 13/11/2009
Arboricultural Implication Assessment Retained Trees on Proposed Layout.pdf - kb 13/11/2009
Arboricultural Implication Assessment Report.pdf - kb 13/11/2009
Affordability Housing Statement.pdf - kb 13/11/2009
Transport Statement SUPERCEDED.pdf - kb 13/11/2009
Streetscapes SUPERCEDED.pdf - kb 13/11/2009
Streetscapes Colour Sheet 2.pdf - kb 13/11/2009
Statement of Community Involvement.pdf - kb 13/11/2009
House Type 41 Floor Plan.pdf - kb 13/11/2009
House Type 41 Elevations.pdf - kb 13/11/2009
House Type 40 Elevations.pdf - kb 13/11/2009
House Type 35 Floor Plan.pdf - kb 13/11/2009
House Type 33 Second Floor Plan.pdf - kb 13/11/2009
House Type 40 Floor Plan.pdf - kb 13/11/2009
Site Location Plan.pdf - kb 13/11/2009
AIA TPP REVISED Phase 1, Westfield Estate 12.11.09.dwg - kb 13/11/2009
Planning Statement.pdf - kb 16/11/2009
Design and Access Statement - SUPERCEDED.pdf - kb 17/11/2009
Tree Plan.pdf - kb 20/11/2009
REPORT of Construction Ecological Management Plan.pdf - kb 03/12/2009
REPORT of Implementation of Construction Ecological Management Plan.pdf - kb 03/12/2009
REPORT of Nesting Bird Survey.pdf - kb 03/12/2009
REPORT of Reptile Survey.pdf - kb 03/12/2009
Proposed Site Layout Hard Landscaping.pdf - kb 07/12/2009
Streetscapes 04 12 09 - SUPERCEDED.pdf - kb 07/12/2009
Curtilage Treatment Boundary Plan SUPERCEDED.pdf - kb 07/12/2009
Copy of Drawing Register.xls - kb 07/12/2009
Transport Statement Amended 10 12 2009.pdf - kb 10/12/2009
Road Safety Audit Stage 1 - SUPERCEDED.pdf - kb 11/12/2009
Design and Access Statement - AMENDED 11 12 2009.pdf - kb 14/12/2009
Bat Survey.pdf - kb 23/12/2009
Road Safety Audit Stage 1 - Amended 23 12 2009.pdf - kb 23/12/2009
Draft Plots 73 - 79.pdf - kb 15/01/2010
Draft Retaining Wall.pdf - kb 15/01/2010
Proposed Access Road.pdf - kb 15/01/2010
Proposed Access Road Sheet 2.pdf - kb 15/01/2010
Proposed Access Road Sheet 1.pdf - kb 15/01/2010
Typical Sections.pdf - kb 03/02/2010
Retaining Wall Coloured.pdf - kb 03/02/2010
Site Layout SUPERCEDED.pdf - kb 03/02/2010
Longsection Sheet 2 of 2 Rev P3.pdf - kb 03/02/2010
Landscape Outline Proposals SUPERCEDED.pdf - kb 03/02/2010
Longsection Sheet 1 of 2 Rev P3.pdf - kb 03/02/2010
General Arrangement Rev P3 - SUPERCEDED.pdf - kb 03/02/2010
Additional Swept Path Analysis.pdf - kb 08/02/2010
Stage 1 Road Safety Audit SUPERCEDED.pdf - kb 08/02/2010
Retaining Wall to Plots 11 and 23.pdf - kb 16/02/2010
Site Layout 17 02 10 - SUPERCEDED.pdf - kb 18/02/2010
Landscape Outline Proposals 17 02 10 - SUPERCEDED.pdf - kb 18/02/2010
Curtilage Treatment Boundary Plan 17 02 10 - SUPERCEDED.pdf - kb 18/02/2010
Application Form - AMENDED 23 12 2009.pdf - kb 19/02/2010
Retaining Wall.pdf - kb 19/02/2010
Retaining Wall Section.pdf - kb 19/02/2010
Swept Paths Analysis and Visibility Splays 10 12 09 - SUPERCEDED.pdf - kb 19/02/2010
Swept Paths and Visibility Splays AMENDED 01 03 2010.pdf - kb 01/03/2010
Stage 1 Road Safety Audit AMENDED 01 03 10.pdf - kb 01/03/2010
Streetscapes AMENDED 01 03 10.pdf - kb 01/03/2010
SAJ JN0132-Dwg-0016 Revised Site Layout Car Parking Swept Path Analyis.pdf - kb 01/03/2010
SAJ JN0132-Dwg-0015 Revised Site Layout Refuse Vehicle Collection Swept Path Analyis.pdf - kb 01/03/2010
Landscape Outline Proposals AMENDED 01 03 10.pdf - kb 01/03/2010
Curtilage Treatment Boundary Plan AMENDED 01 03 10.pdf - kb 01/03/2010
Comments on Highway Layout Rev P5.pdf - kb 01/03/2010
General Arrangement AMENDED 01 03 2010.pdf - kb 01/03/2010
Site Layout AMENDED 01 03 10.pdf - kb 16/03/2011
All About Trees - kb 07/11/2011
Planning Statement - kb 07/11/2011
Consultee Name Date Letter Sent Consultation Expiry Date
Condition Discharge - Janet Horne 18/10/2012 -
Condition Discharge - Janet Horne 12/12/2012 -
Condition Discharge - Janet Horne 28/02/2013 -
Condition Discharge - Peter Armstrong 28/02/2013 -
Condition Discharge - Peter Armstrong 18/10/2012 -
Condition Discharge - Rob Duckworth 26/10/2012 -
Planning and Regeneration Programme 23/12/2009 -
Address Date Sent Date Reconsulted Expiry Date
2 WESTFIELD WAY LOFTUS SALTBURN BY THE SEA TS134XD 23/11/2009 - 14/12/2009
16 PARK TERRACE LOFTUS SALTBURN TS134HU 23/11/2009 - 14/12/2009
7 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
6 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
4 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
5 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
3 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
1 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
2 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
15 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
16 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
14 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
11 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
12 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
13 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
10 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
9 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
8 SEYMOUR HILL TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HX 23/11/2009 - 14/12/2009
12 DUNCAN PLACE LOFTUS SALTBURN-BY-THE-SEA TS134PR 23/11/2009 - 14/12/2009
14 SOUTH VIEW LOFTUS SALTBURN-BY-THE-SEA TS134JL 23/11/2009 - 14/12/2009
2 PARK TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HU 23/11/2009 - 14/12/2009
15 SOUTH VIEW LOFTUS SALTBURN-BY-THE-SEA TS134JL 23/11/2009 - 14/12/2009
5 PARK TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HU 23/11/2009 - 14/12/2009
4 PARK TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HU 23/11/2009 - 14/12/2009
3 PARK TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HU 23/11/2009 - 14/12/2009
1 PARK TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HU 23/11/2009 - 14/12/2009
6 PARK TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HU 23/11/2009 - 14/12/2009
1 ROBINSON TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HY 23/11/2009 - 14/12/2009
16 SOUTH VIEW LOFTUS SALTBURN-BY-THE-SEA TS134JL 23/11/2009 - 14/12/2009
4 ROBINSON TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HY 23/11/2009 - 14/12/2009
3 ROBINSON TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HY 23/11/2009 - 14/12/2009
2 ROBINSON TERRACE LOFTUS SALTBURN-BY-THE-SEA TS134HY 23/11/2009 - 14/12/2009
17 SOUTH VIEW LOFTUS SALTBURN-BY-THE-SEA TS134JL 23/11/2009 - 14/12/2009
18 SOUTH VIEW LOFTUS SALTBURN-BY-THE-SEA TS134JL 23/11/2009 - 14/12/2009
GRACE PEAKS DUNCAN PLACE LOFTUS SALTBURN-BY-THE-SEA TS134PR 23/11/2009 - 14/12/2009
14 DUNCAN PLACE LOFTUS SALTBURN-BY-THE-SEA TS134PR 23/11/2009 - 14/12/2009
19 SOUTH VIEW LOFTUS SALTBURN-BY-THE-SEA TS134JL 23/11/2009 - 14/12/2009
20 SOUTH VIEW LOFTUS SALTBURN-BY-THE-SEA TS134JL 23/11/2009 - 14/12/2009
6 WESTFIELD WAY LOFTUS SALTBURN-BY-THE-SEA TS134XD 23/11/2009 - 14/12/2009
17 BEECH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XB 23/11/2009 - 14/12/2009
8 ASH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XA 23/11/2009 - 14/12/2009
24 BEECH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XB 23/11/2009 - 14/12/2009
22 BEECH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XB 23/11/2009 - 14/12/2009
6 ASH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XA 23/11/2009 - 14/12/2009
4 WESTFIELD WAY LOFTUS SALTBURN-BY-THE-SEA TS134XD 23/11/2009 - 14/12/2009
26 BEECH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XB 23/11/2009 - 14/12/2009
4 ASH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XA 23/11/2009 - 14/12/2009
2 WESTFIELD WAY LOFTUS SALTBURN-BY-THE-SEA TS134XD 23/11/2009 - 14/12/2009
20 BEECH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XB 23/11/2009 - 14/12/2009
2 ASH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XA 23/11/2009 - 14/12/2009
25 BEECH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XB 23/11/2009 - 14/12/2009
21 BEECH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XB 23/11/2009 - 14/12/2009
19 BEECH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XB 23/11/2009 - 14/12/2009
10 WESTFIELD WAY LOFTUS SALTBURN-BY-THE-SEA TS134XD 23/11/2009 - 14/12/2009
8 WESTFIELD WAY LOFTUS SALTBURN-BY-THE-SEA TS134XD 23/11/2009 - 14/12/2009
18 BEECH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XB 23/11/2009 - 14/12/2009
23 BEECH GROVE LOFTUS SALTBURN-BY-THE-SEA TS134XB 23/11/2009 - 14/12/2009
29 LIME WALK LOFTUS SALTBURN-BY-THE-SEA TS134XL 23/11/2009 - 14/12/2009
36 WESTFIELD WALK LOFTUS SALTBURN-BY-THE-SEA TS134XN 23/11/2009 - 14/12/2009
11 PINE WALK LOFTUS SALTBURN-BY-THE-SEA TS134XW 23/11/2009 - 14/12/2009
9 PINE WALK LOFTUS SALTBURN-BY-THE-SEA TS134XW 23/11/2009 - 14/12/2009
7 PINE WALK LOFTUS SALTBURN-BY-THE-SEA TS134XW 23/11/2009 - 14/12/2009
5 PINE WALK LOFTUS SALTBURN-BY-THE-SEA TS134XW 23/11/2009 - 14/12/2009
3 PINE WALK LOFTUS SALTBURN-BY-THE-SEA TS134XW 23/11/2009 - 14/12/2009
33 LIME WALK LOFTUS SALTBURN-BY-THE-SEA TS134XL 23/11/2009 - 14/12/2009
1 PINE WALK LOFTUS SALTBURN-BY-THE-SEA TS134XW 23/11/2009 - 14/12/2009
19 PINE WALK LOFTUS SALTBURN-BY-THE-SEA TS134XW 23/11/2009 - 14/12/2009
37 WESTFIELD WALK LOFTUS SALTBURN-BY-THE-SEA TS134XN 23/11/2009 - 14/12/2009
21 PINE WALK LOFTUS SALTBURN-BY-THE-SEA TS134XW 23/11/2009 - 14/12/2009
17 PINE WALK LOFTUS SALTBURN-BY-THE-SEA TS134XW 23/11/2009 - 14/12/2009
25 PINE WALK LOFTUS SALTBURN-BY-THE-SEA TS134XW 23/11/2009 - 14/12/2009
23 PINE WALK LOFTUS SALTBURN-BY-THE-SEA TS134XW 23/11/2009 - 14/12/2009
15 PINE WALK LOFTUS SALTBURN-BY-THE-SEA TS134XW 23/11/2009 - 14/12/2009
KENILWORTH CARE HOME DUNCAN PLACE LOFTUS TS13 4PR 23/11/2009 - 14/12/2009
WINDRUSH NORTH ROAD LOFTUS TS13 4HP 23/11/2009 - 14/12/2009
WESTFIELD HOUSE DUNCAN PLACE LOFTUS TS13 4PR 10/12/2009 - 31/12/2009
HOPE COTTAGE DUNCAN PLACE LOFTUS TS13 4PR 10/12/2009 - 31/12/2009
ALLOTMENT ASSOCIATION DUNCAN PLACE LOFTUS TS13 4PR 10/12/2009 - 31/12/2009
LOFTUS TOWN COUNCIL RE: WESTFIELD ALLOTMENTS 81A HIGH STREET LOFTUS TS134HG 23/11/2009 - 14/12/2009
Site or Press Description Display Date Expiry Date
B ARTICLE 15 27/11/2009 18/12/2009