Location
GRANGETOWN FIRE STATION, TRUNK ROAD/CHURCH LANE, GRANGETOWN, TS66AA
Proposal
CHANGE OF USE OF PART OF LAND TO FORM A 'GROW AND LEARN' AREA; ERECTION OF TIMBER CLASSROOM AND INSTALLATION OF 1.8M HIGH PERIMETER FENCING AND GATES
Application Type
Full
Status
Approved
Parish(es)
Eston
Applicant
GRANGETOWN FIRE STATION
Applicant's Address
MR FRANK SWEENEY
TRUNK ROAD/CHURCH LANE
GRANGETOWN
TS66AA
Agent
GROUNDWORK SOUTH TEES
Agent's Address
MISS C GALLAGHER
26 STATION STREET
SALTBURN
TS121AE
Agent's work phone
Agent's email
Case Officer
Miss C Evans
Case Officer Telephone
01287 612629
Case Officer Email
-
Consultation Start
28/04/2009
Weekly List Expiry Date
-
Date Received
26/02/2009
Date Valid
22/04/2009
Expiry
17/06/2009
Consultation Expiry
22/05/2009
associated_bldreg
-
Decision
APPROVED
Decision Date
16/06/2009
Decision Level
Delegated
| # | Condition Details |
|---|---|
| 1 | (1) The development shall not be begun later than the expiration of THREE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990. |
| 2 | (2) On-site parking shall be provided in accordance with the details shown on Drawing no. R146-02 prior to the use hereby approved commencing and thereafter retained for that purpose. REASON: In the interests of Highway safety. |
| 3 | (5) Implementation of Approved Remediation Scheme The approved remediation scheme must be carried out in accordance with its terms prior to the commencement of development other than that required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. The Local Planning Authority must be given two weeks written notification of commencement of the remediation scheme works. Following completion of measures identified in the approved remediation scheme, a verification report (referred to in PPS23 as a validation report) that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval in writing of the Local Planning Authority. REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 4 | (6) Reporting of Unexpected Contamination In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority. An investigation and risk assessment must be undertaken in accordance with the requirements of condition 1, and where remediation is necessary a remediation scheme must be prepared in accordance with the requirements of condition 2, which is subject to the approval in writing of the Local Planning Authority. Following completion of measures identified in the approved remediation scheme a verification report must be prepared, which is subject to the approval in writing of the Local Planning Authority in accordance with condition 3. REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 5 | (7) Long Term Monitoring and Maintenance A monitoring and maintenance scheme to include monitoring the long-term effectiveness of the proposed remediation over a period of [x] years, and the provision of reports on the same must be prepared, both of which are subject to the approval in writing of the Local Planning Authority. Following completion of the measures identified in that scheme and when the remediation objectives have been achieved, reports that demonstrate the effectiveness of the monitoring and maintenance carried out must be produced, and submitted to the Local Planning Authority. This must be conducted in accordance with DEFRA and the Environment Agency’s ‘Model Procedures for the Management of Land Contamination, CLR 11’ Reason : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 6 | NOTE: The following development plan policies were relevant to this decision:- Local Development Framework Policy - CS20, DP2, DP3 and CS3. |
| 7 | REASON FOR DECISION: It is considered that the proposed development will not cause significant harm to the amenities of local residents or adversely affect the character and appearance of the area. The application does not raise any issues in respect of crime prevention or highway safety. The proposal accords with the Council's adopted Development Plan and Supplementary Planning Guidance. |
| 8 | (3) Site Characterisation An investigation and risk assessment, in addition to any assessment provided with the planning application, must be completed in accordance with a scheme to assess the nature and extent of any contamination on the site, whether or not it originates on the site. The contents of the scheme are subject to the approval in writing of the Local Planning Authority. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced. The written report is subject to the approval in writing of the Local Planning Authority. The report of the findings must include: (i) a survey of the extent, scale and nature of contamination; (ii) an assessment of the potential risks to: - human health, - property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes, - adjoining land, - groundwaters and surface waters, - ecological systems, - archeological sites and ancient monuments; (iii) an appraisal of remedial options, and proposal of the preferred option(s). This must be conducted in accordance with DEFRA and the Environment Agency’s ‘Model Procedures for the Management of Land Contamination, CLR 11’. REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
| 9 | (4) Submission of Remediation Scheme A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and historical environment must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. REASON : To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors. |
If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.
To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.
| Select all | Size | Date uploaded | |
|---|---|---|---|
| Application Documents | |||
| Decision Notice | 31 kb | ||
| Site Plan.pdf | 366 kb | 27/04/2009 | |
| Fence and Gate Details.pdf | 221 kb | 27/04/2009 | |
| Location Plan - SUPERCEDED.pdf | 374 kb | 27/04/2009 | |
| Design and Access Statement.pdf | 38 kb | 27/04/2009 | |
| Application Form.pdf | 415 kb | 27/04/2009 | |
| Elevation.pdf | 285 kb | 27/04/2009 | |
| Location plan - Amended 15 06 2009.pdf | 162 kb | 15/06/2009 | |
| Address | Date Sent | Date Reconsulted | Expiry Date |
|---|---|---|---|
| PARK BUNGALOW SOUTH LOOP ROAD GRANGETOWN MIDDLESBROUGH TS6 9AA | 28/04/2009 | - | 19/05/2009 |
| Site or Press | Description | Display Date | Expiry Date |
|---|---|---|---|
| S | SITE NOTICE ONLY | 01/05/2009 | 22/05/2009 |