R/2006/0433/OO

Planning Application Details - Official Consultation has expired.

Location
LAND AT TEESPORT, GRANGETOWN
Proposal
OUTLINE APPLICATION FOR DEVELOPMENT OF A CONTAINER TERMINAL
Application Type
Outline
Status
Approved
Parish(es)
Applicant
P D TEESPORT
Applicant's Address
17-27 QUEEN'S SQUARE MIDDLESBROUGH TS2 1AH
Agent
NATHANIEL LICHFIELD AND PARTNERS
Agent's Address
GENERATOR STUDIOS TRAFALGAR STREET NEWCASTLE UPON TYNE NE1 2LA
Agent's work phone
Agent's email
Case Officer
Mrs D Mealing
Case Officer Telephone
Case Officer Email
Doreen.Mealing@redcar-cleveland.gov.uk
Consultation Start
15/05/2006
Weekly List Expiry Date
-
Date Received
26/04/2006
Date Valid
26/04/2006
Expiry
21/06/2006
Consultation Expiry
25/10/2007
associated_bldreg
-
Decision
OUTLINE PERMISSION GRANTED
Decision Date
04/10/2007
Decision Level
Committee
Committee Date
26/04/2007

Conditions table
# Condition Details
1 (1) No part of the development hereby permitted shall be commenced until details of siting, design, external appearance, means of access and landscaping (hereinafter called the reserved matters) in respect of that part of the development have been submitted to and approved in writing by the Local Planning Authority, and the development shall not be carried out otherwise than in complete accordance with the details so approved. Application for the approval of the reserved matters for the first phase of development (as shown on drawing 9R0155/PA/1000 Revision 4) shall be made to the Local Planning Authority before the expiration of five years from the date of this permission and application for the approval of the reserved matters for the second phase of development (as shown on drawing 9R0155/PA/1000 Revision 4) shall be made to the Local Planning Authority before the expiration of fifteen years from the date of this permission. REASON: By virtue of the provision of section 92 of the Town and Country Planning Act 1990 (as amended).
2 (2) The development hereby permitted must be begun either before the expiration of five years from the date of this permission, or before the expiration of three years from the date of the approval of the last of the reserved matters for the first phase of the development (as shown on drawing 9R0155/PA/1000 Revision 4), whichever is the later. REASON: By virtue of the provision of section 92 of the Town and Country Planning Act 1990 (as amended).
3 (3) The development hereby permitted shall not be carried out other than substantially in accordance with Parameter Plans No, 9R0155/PA/1001 Revision 3 and 9R0155/PA/1002 Revision 4 contained in the planning application. REASON: The development of the site is the subject of an Environmental Impact Assessment and any alteration to the layout, land use or design which is not substantially in accordance with the approved parameter plans may have an impact which has not been assessed by that process.
4 (4) Prior to the commencement of development of each part of the development for which reserved matters have been approved, details and samples of all materials to be used in the construction of the external surfaces of the buildings and any external plant and equipment in that part of the development shall be submitted to and approved in writing by the Local Planning Authority and the development shall be implemented using the approved materials. REASON: In the interests of visual amenity to ensure a satisfactory standard of development is achieved.
5 (5) No part of the development approved by this permission shall be commenced until: a) a desk top study has been carried out for that part which shall include the identification of previous site uses, potential contaminants that might reasonably be expected given those uses and other relevant information. And using this information a diagrammatical representation (Conceptual Model of the geology and hydrogeology) for the site of all potential contaminant sources, pathways and receptors has been produced. b) A site investigation has been designed for that part of the site using the information obtained from the desk top study and any diagrammatical representations (Conceptual Model of the geology and hydrogeology). This should be submitted to, and approved in writing by the Local Planning Authority prior to that investigation being carried out on the site. The investigation must be comprehensive enough to enable: - a risk assessment to be undertaken relating to ground and surface waters associated on and off the site that may be affected, and - refinement of the Conceptual Model; and - the development of a Method Statement detailing the remediation requirements c) The site investigation has been undertaken in accordance with details approved by the Local Planning Authority and a risk assessment has been undertaken. d) A Method Statement detailing the remediation requirements, including measures to minimise the impact on ground and surface waters, using the information obtained from the Site Investigation has been submitted to the Local Planning Authority. This should be approved in writing by the Local Planning Authority prior to that remediation being carried out on the site. REASON: To protect Controlled Waters and ensure that the remediated site is reclaimed to an appropriate standard.
6 (6) If during development, significant contamination not previously identified, is found to be present at any part of the site then no further development (unless otherwise agreed in writing by the Local Planning Authority) shall be carried out at that part until the applicant has submitted, and obtained written approval from the Local Planning Authority for, an addendum to the Method Statement. This addendum must detail how this unsuspected contamination shall be dealt with. REASON: To ensure that the development complies with the approved details in the interests of protection of Controlled Waters.
7 (7) Upon completion of the remediation detailed in the Method Statement a report shall be submitted to the Local Planning Authority that provides verification that the required works regarding contamination have been carried out in accordance with the approved method Statement(s). Post remediation sampling and monitoring results shall be included in the report to demonstrate that the required remediation has been fully met. Future monitoring proposals and reporting shall also be detailed in the report. REASON: To protect Controlled Waters by ensuring that the remediated site has been reclaimed to an appropriate standard.
8 (8) Each part of the development shall be carried out in accordance with the approved Method Statement. REASON: To ensure that the development complies with approved details in the interests of protection of Controlled Waters.
9 (9) No part of the development approved by this permission shall be commenced unless the method for piling foundations for that part has been submitted to and approved in writing by the Local Planning Authority. The piling shall thereafter be undertaken only in accordance with the approved details. REASON: The site is contaminated/potentially contaminated and piling could lead to the contamination of ground water in the underlying aquifer.
10 (10) Prior to the commencement of development of each part of the development for which reserved matters have been approved, drawings showing both foul and surface water drainage (including the provision of oil interceptors and sustainable forms of drainage as far as is practicable) connected with the development shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the works shall be undertaken in complete accordance with the approved scheme. The works approved shall be completed prior to the occupation of the first building in that part of the development. The scheme shall be retained throughout the life of that part of the development unless otherwise agreed in writing with the Local Planning Authority. REASON: To prevent pollution of the water environment.
11 (11) Prior to the commencement of development an oil spill contingency plan shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the oil spill contingency plan or any replacement of the same approved in writing by the Local Planning Authority shall be implemented in accordance with the approved details. REASON: To prevent pollution of the water environment.
12 (12) Prior to the commencement of development a programme for the reclamation and construction works, which avoids disturbance to breeding birds, shall be submitted to and approved in writing by the Local Planning Authority. Construction work shall thereafter be carried out in accordance with the approved programme. REASON: To prevent unacceptable disturbance to breeding birds.
13 (13) Prior to the installation of any external lighting on any part of the new terminal, including temporary lighting, details of a scheme of external lighting to be used within that part shall be submitted to and approved in writing by the Local Planning Authority. Such details shall include the location, type, angle of direction and wattage of each light which shall be so positioned to prevent any glare or light spillage especially towards the estuary. Thereafter the lighting shall be implemented in accordance with the approved scheme. REASON: In the interests of visual amenity and to avoid nuisance or harm to fisheries resources as a result of light spillage.
14 (14) Prior to the commencement of development of each part of the site a written scheme of archaeological investigation for that part shall be submitted to and approved in writing by the Local Planning Authority. Development shall thereafter be carried out in accordance with the approved scheme of investigation unless otherwise agreed in writing by the Local Planning Authority. REASON: To enable the identification and recording of archaeological and paleaeoecological remains.
15 (15) Prior to the commencement of development a Construction Method Statement shall be submitted to and approved in writing by the Local Planning Authority. This should ensure compliance with the principles of Best Practicable Means as outlined in BS5228 Part 1 1997 and the Control of Pollution Act and include measures to minimise dust generation and noise from the site. Thereafter all work shall be carried out in strict accordance with the approved construction method statement. REASON: To prevent nuisance from noise and dust and in the interests of the visual amenity of the area.
16 (16) A Business Travel Plan shall be agreed with the Local Planning Authority and the detailed provisions of the Travel Plan shall be implemented immediately following the commencement of development of the first building of the development hereby approved. REASON: In the interest of achieving a sustainable form of development.
17 (17) Prior to the commencement of development a detailed phasing timetable for the whole site shall be submitted to and approved in writing by the Local Planning Authority. REASON: In the interest of achieving an acceptable form of development.
18 (18) Prior to the commencement of development, details of emergency access arrangements shall be submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented in full prior to the terminal coming into use. REASON: In the interests of achieving an acceptable form of development.
19 (19) No building on any part of the development hereby permitted shall exceed 14 metres in height. REASON: The development of the site is the subject of an Environmental Impact Assessment and the development of buildings in excess of this height may have an impact which has not been assessed by that process.
20 (20) Container stacking shall only take place within the areas indicated on parameter plans 9R0155/PA/1001 Revision 3 and 9R0155/PA/1002 Revision 4. REASON: The development of the site is the subject of an Environmental Impact Assessment and the storage of containers in other areas may have an impact which has not been assessed by that process.
21 (21) Container stacks shall be restricted to the maximum heights set out on parameter plans 9R0155/PA/1001 Revision 3 and 9R0155/PA/1002 Revision 4. REASON: The development of the site is the subject of an Environmental Impact Assessment and the stacking of containers above the agreed heights may have an impact which has not been assessed by that process.
22 (22) Within the quay and crane back reach area (as identified on parameter plans 9R0155/PA/1001 Revision 3 and 9R0155/PA/1002 Revision 4) the maximum crane height with the jib in the vertical position shall not exceed 100 metres. Elsewhere on the site maximum crane height shall not exceed 25 metres. REASON: The development of the site is the subject of an Environmental Impact Assessment and the use of cranes in excess of the agreed heights may have an impact which has not been assessed by that process.
23 (23) The maximum paved area of the container terminal as identified on parameter plans 9R0155/PA/1001 Revision 3 and 9R0155/PA/1002 Revision 4 shall not exceed 31 hectares. REASON: The development of the site is the subject of an Environmental Impact Assessment and an increase in the area of the container terminal may have an impact which has not been assessed by that process.
24 (24) The Northern Gateway Container Terminal: Dredging Protocol (PD Teesport, February 2007, Final Report 9S2047) submitted as Appendix 2 of the Northern Gateway Container Terminal, Supplement to the Environmental Statement, February 2007 will be implemented in full during the period of capital dredging operations. This will entail the submission of a dredging programme to the relevant statutory bodies prior to the start of these operations. REASON: To minimise the impacts on water quality, inter-tidal and sub-tidal habitat and SPA waterbird interests, and in the interests of safeguarding the broader estuaries and marine environment.
25 (25) A programme of monitoring of dissolved oxygen and suspended solid concentrations during capital dredging activities will be agreed with the Local Planning Authority prior to development commencing and thereafter implemented in accordance with the agreed scheme. REASON: To verify the findings of the Environmental Statement and supplementary documents with respect to water quality and sub-tidal habitats, and in the interests of safeguarding the broader estuaries and marine environment.
26 (26) The Seal Sands monitoring protocol (PD Teesport, February 2007) submitted as Appendix 3 of Northern Gateway Container Terminal, Supplement to the Environmental Statement, February 2007 will be implemented in full. This will entail sampling of bed sediment types, erosion/deposition measurements and silt flux recording at the recommended frequencies before, during and for a period of five years following NGCT construction. An initial report will be presented to the relevant statutory bodies after collection of data on completion of construction; annual updates will then follow and a final report issued once five years post-construction data have been gathered. REASON: To verify the finds of the ES with respect to the hydrodynamic and sedimentological effects of NGCT on the SPA/SSSI inter-tidal habitats of Seal Sands.
27 (27) A programme of monitoring waterbird usage/behaviour and noise levels will be designed, instituted and implemented on the Vopak foreshore during the period of percussive piling operations on the new NGCT quay frontage. REASON: To verify the findings of the ES with respect to noise levels and consequent waterbird disturbance derived from piling operations.
28 (28) Phase 2 of the terminal development shall not operate until the new rail terminal has been completed and is available for use and the Shell Sidings Rail Spur has been reconnected and completed to satisfaction of the Local Planning Authority. REASON: In the interests of achieving a satisfactory form of development.
29 (29) Prior to development commencing, a mammal and amphibian survey shall be carried out and the survey and any necessary mitigation measures shall be submitted to and agreed with the Local Planning Authority. REASON: To protect any mammals or amphibians which may be present on the site.
30 (30) No development approved by this planning permission shall be commenced until a scheme for water column monitoring (water quality) and suspended sediment monitoring during dredging/construction has been submitted to and approved in writing by the Local Planning Authority. Once approved, the scheme shall be complied with. REASON: To prevent the pollution of the water environment.
31 (31) No development approved by this planning permission shall be commenced until a scheme for post implementation water column monitoring has been submitted to and approved in writing by the Local Planning Authority. Once approved, the scheme shall be complied with unless otherwise agreed in writing with the Local Planning Authority. REASON: To monitor the impact on the Tees estuary ecology and water quality.
32 (32) No development approved by this planning permission shall be commenced before a report identifying the likely impact of the proposed scheme on the migratory fishery and detailing the mitigation measures necessary to offset any detrimental impact, including a timetable for these measures has been submitted to and approved in writing by the Local Planning Authority. The agreed mitigation measures shall be implemented in accordance with the timetable. REASON: To ensure the resilience of the migratory fishery is maintained.
33 (33) The development hereby granted consent shall not be brought into use unless and until the highway improvement works as shown in principle on the Steer Davis Gleave (SDG) drawing numbers 206219 001 REV C; 206219 002 REV E; 206219 003 REV D and 206219 Work_ B have been completed to the written satisfaction of the Local Planning Authority and Highways Agency. REASON: To ensure that the A19, A174, A1053 and A66 trunk roads might continue to fulfil their purpose as part of a national system of routes for through traffic, in accordance with Section 10(2) of the Highways Act 1980, maintaining the safe free flow of traffic on the road.
34 NOTE: The following development plan policies were relevant to this decision:- Local Development Framework Policy CS4, CS10, CS20, DP2 and DP3 and Policies T16 & EL7 of the Regional Planning Guidance 1 and Policies 22, 7 & 49 of the emerging Regional Spatial Strategy.
35 REASON FOR DECISION: The proposed development of the container terminal at Teesport accords with regional, sub-regional and local planning policy which seeks to encourage and promote the development of port facilities at Teesport. The location of the application is such that construction works and the operational development will not impact on local residents. Subject to suitable safeguarding conditions and monitoring regimes being set up the proposal will not adversely affect the integrity of the protected areas or have an unacceptable impact on wildlife, water quality or the sedimentary regime. It is considered that there is capacity on the rail network to accommodate additional rail traffic and subject to some junction improvements, the existing road network has sufficient capacity to accommodate additional road traffic. The proposal is therefore acceptable in highway terms. The proposal represents a sustainable form of development, on previously developed land, and one which will have significant economic and social benefits to the Tees Valley and wider region.

If you are unable to find the decision notice that relates to this planning application, please email planning_admin@redcar-cleveland.gov.uk and we will provide this document to you.

To view individual documents click on the file name for the required row and the document will open. To download a selection of individual documents, place a tick alongside each of the ones you wish to view and then click on the 'Download selected' button. To open the sub-tables, click the sub-heading for the group.

Select all Size Date uploaded
Application Form
Application Form - kb 16/05/2006
Decision
Decision Notice - kb 04/10/2007
Section 106 Teesport, Container Terminal 2000 Oct 2007 - kb 01/10/2007
Section 106 Copy Completed Agreement Oct 2015 - kb 15/10/2015
Plans
Section 3.pdf - kb 01/03/2007
Supporting Documentation
Hydrodyamics and Sedementation Studies.pdf - kb 12/05/2006
Environment Statement Non-Technical Summary - kb 16/05/2006
Transport Statement.pdf - kb 16/05/2006
Transport Harbour Revision Order.pdf - kb 16/05/2006
Environment Statement.pdf - kb 17/05/2006
Environment Statement.pdf - kb 17/05/2006
Appendix 4 Sections 7 to 11.pdf - kb 01/03/2007
Appendix 3.pdf - kb 01/03/2007
Appendix 6 fig 3.pdf - kb 01/03/2007
Environmental Statement Supplement - March 2007.pdf - kb 01/03/2007
Appendix 6 fig 1 to 2.pdf - kb 01/03/2007
Appendix 5 Sections 9 to 11.pdf - kb 01/03/2007
Appendix 2.pdf - kb 01/03/2007
Appendix 6 fig 4 to 6.pdf - kb 01/03/2007
Appendix 1.pdf - kb 01/03/2007
Appendix 5 to Section 2.pdf - kb 01/03/2007
Sections 1 to 2.pdf - kb 01/03/2007
Appendix 5 Section 8.pdf - kb 01/03/2007
Appendix 4 to Section 6.pdf - kb 01/03/2007
Sections 4 to 6.pdf - kb 01/03/2007
Appendix 5 Sections 3 to 4.pdf - kb 01/03/2007
Appendix 5 Sections 5 to 7.pdf - kb 01/03/2007
Appendix 5 appendices.pdf - kb 01/03/2007
9S2047_Appendix_A_Site_Location _Plan 20071109.pdf - kb 05/02/2008
Desk Study v1_1.PDF - kb 05/02/2008
Desk Study Appendix C vol4.PDF - kb 05/02/2008
Desk Study Appendix C vol5.PDF - kb 05/02/2008
Desk Study Appendix C vol3.PDF - kb 05/02/2008
Analytical Results.PDF - kb 05/02/2008
Report Teesport Northern Gateway 20071005_1532 Benx Xyl BaP.xls - kb 05/02/2008
CLR7 Max Test 1995 Data.PDF - kb 05/02/2008
Report Teesport Northern Gateway 20071004_1839 pH 8.xls - kb 05/02/2008
CLR7 Max Test ALL Data.PDF - kb 05/02/2008
CLR7 Max Test 2005 Data.PDF - kb 05/02/2008
In Situ Results.PDF - kb 05/02/2008
CLR7 Mean Test 1995 Data.PDF - kb 05/02/2008
CLR7 Mean Test ALL Data.PDF - kb 05/02/2008
CLR7 Mean Test 2005 Data.PDF - kb 05/02/2008
Appendix C vol2.PDF - kb 14/02/2008
Appendix C vol1.PDF - kb 14/02/2008
Desk Study.pdf - kb 14/02/2008
Site Investigation report.pdf - kb 14/02/2008
Appendix B Map.pdf - kb 14/02/2008
Appendix D - kb 08/11/2011
Appendix F - kb 08/11/2011
Appendix E - kb 08/11/2011
SI Report v 2 CD - kb 08/11/2011
Phase I Report CD - kb 08/11/2011
Appendix C - kb 08/11/2011
component parts - kb 08/11/2011
Condition 5 - 14 02 2008 - kb 08/11/2011
Appendix B Borehole Logs - kb 26/11/2012
Appendix A Figures 1 - 4 - kb 26/11/2012
CONDITION DISCHARGE APPLICATION
COVERING LETTER COND 10 12 14 15 18 29 - kb 14/10/2015
COND 18 - EMERGENCY ACCESS - kb 14/10/2015
COND 29 - MAMMAL SURVEY - kb 14/10/2015
COND 14 - ARCHAEOLOGY WRITTEN SCHEME - kb 14/10/2015
COND 15 - CONSTRUCTION MAN PLAN - kb 14/10/2015
COND 10 - PB3751-PLN-1000 rev P2 - kb 14/10/2015
COND 12 - BREEDING BIRDS NOTE - kb 14/10/2015
COND 29 - AMPHIBIAN NOTE - kb 14/10/2015
CONDITION 11 - OIL SPILL PLAN - kb 15/10/2015
Covering letter cond 4 - kb 04/11/2015
cond 4 PB4043 - CON - 3010 T1 - kb 04/11/2015
Cond 17 - Phasing plan - kb 04/11/2015
Cond 5 - Site investigation and monitoring programme - kb 04/11/2015
APPLICATION CONDITION 5 C D - kb 13/11/2015
REPORT 5 C D - kb 13/11/2015
Phasing plan cond 17 revised - kb 11/12/2015
Consultee Name Date Letter Sent Consultation Expiry Date
- 11/05/2006 -
Housing & Health Services 12/05/2006 -
Housing & Health Services 15/03/2007 -
Joint Strategy Unit 11/05/2006 -
Natural England 11/05/2006 -
Network Rail 11/05/2006 -
Northumbrian Water Ltd 11/05/2006 -
Planning and Regeneration Programme 11/05/2006 -
Technical Services (Regulatory) 12/05/2006 -
Technical Services (Regulatory) 15/03/2007 -
Address Date Sent Date Reconsulted Expiry Date
DEE CEE FREIGHT SERVICES KINKERDALE ROAD TEESPORT GRANGETOWN TS6 6 15/05/2006 - 05/06/2006
CLEVELAND POTASH STORAGE BOULBY ROAD TEESPORT GRANGETOWN TS6 6 15/05/2006 - 05/06/2006
CAT (UK) KINKERDALE ROAD TEESPORT GRANGETOWN TS6 6 15/05/2006 - 05/06/2006
ALBERMARLE CORPORATION KINKERDALE ROAD TEESPORT GRANGETOWN TS6 6 15/05/2006 - 05/06/2006
ASDA STORAGE KINKERDALE ROAD TEESPORT GRANGETOWN TS6 6 15/05/2006 - 05/06/2006
TEESPORT NORTH S/S KINKERDALE ROAD TEESPORT GRANGETOWN TS6 6 15/05/2006 - 05/06/2006
CONTAINERSHIPS KINKERDALE ROAD TEESPORT GRANGETOWN TS6 6 15/05/2006 - 05/06/2006
Site or Press Description Display Date Expiry Date
B ARTICLE 15 19/05/2006 09/06/2006