R/2002/0407/FF

Planning Application Details - Official Consultation has expired.

Location
JUNCTION WORKS, NORMANBY ROAD, SOUTH BANK, TS6 6AR
Proposal
ERECTION OF A WORKSHOP/ STORAGE BUILDING
Application Type
Full
Status
Approved
Parish(es)
Applicant
MR M D NEE T/A SKIPFREIGHT
Applicant's Address
JUNCTION WORKS NORMANBY ROAD SOUTH BANK TS6 6AR
Agent
MR M D NEE T/A SKIPFREIGHT
Agent's Address
JUNCTION WORKS NORMANBY ROAD SOUTH BANK TS6 6AR
Agent's work phone
Agent's email
Case Officer
Miss J Horne
Case Officer Telephone
Case Officer Email
Janet.Horne@redcar-cleveland.gov.uk
Consultation Start
19/06/2002
Weekly List Expiry Date
-
Date Received
22/05/2002
Date Valid
22/05/2002
Expiry
17/07/2002
Consultation Expiry
10/07/2002
associated_bldreg
-
Decision
APPROVED
Decision Date
22/07/2002
Decision Level
Delegated

Conditions table
# Condition Details
1 (1) The development shall not be begun later than the expiration of FIVE YEARS from the date of this permission. REASON: Required to be imposed pursuant to Section 91 of the Town and Country Planning Act 1990.
2 (2) Details of materials to be used on the external elevations of the development shall be submitted to and agreed in writing by the Local Planning Authority prior to the development being commenced. REASON: To ensure the use of satisfactory materials.
3 (3) There shall be no dischare of foul or contaminated drainage from the site into either groundwater or any surface waters, whether direct or via soakaways. REASON: To prevent pollution of the water environment.
4 (4) Any facilities for the storage of oils, fuels or chemicals shall be sited on impervious bases and surrounded by impervious bund walls. The volume of the bunded compound should be at least equivalent to the capacity of the tank plus 10%. If there is multiple tankage, the compound should be at least equivalent to the capacity of the largest tank, or the combined capacity of interconnected tanks, plus 10%. All filling points, vents, gauges and sight glasses must be located within the bund. The drainage system of the bund shall be sealed with no discharge to any watercourse, land or underground strata. Associated pipework should be located above ground and protected from accidental damage. All filling points and tank overflow pipe outlets should be detailed to discharge downwards into the bund. REASON: To prevent pollution of the water environment.
5 NOTE: Redcar and Cleveland Local Plan Policies GEN1, GEN2 and IND4 were relevant to this decision.
Consultee Name Date Letter Sent Consultation Expiry Date
Housing & Health Services Division 23/05/2002 -
Network Rail 24/06/2002 -
Address Date Sent Date Reconsulted Expiry Date
SOUTH BANK 19/06/2002 - 10/07/2002